NOOSA COUNCIL IDAS Development Application Decision Notice                                                   4 of 14


10.   Cleared vegetation is to be suitably processed by one of the following methods and removed from the
      site:-

      10.1. Processing through a woodchipper or shredder. The resulting mulch is to be stockpiled loose in
            heaps of less than 1000 cubic metres, less than 2.5 metres high with a minimum of 10 metres
            between edges of heaps.

      10.2. Disposal for firewood.

      10.3. Disposal for landscaping purposes.

      10.4. Transport to alternative site for breaking down materials provided that all necessary permits have
            been obtained to allow the alternate site to be used for this purpose.

      10.5. The Applicant is advised that other methods may be considered provided full details of the method
            are submitted.

11.   The vegetation removed from the site shall be replaced with 14 tube stock trees (minimum 200mm pot
      diameter) consisting of a mixture of native, endemic species such as Corymbia citriodora, Corymbia
      intermedia, Corymbia tessellaris, Callitris columellaris, or Eucalypts of local origin. This vegetation shall
      not be planted within the sewerage zone of influence area.

12.   The large Bloodwood (Corymbia spp.) adjacent to the driveway entry shall be retained except where
      required to be removed following the issue of a Development Permit for Operational Works for access and
      carparking. Should the tree be required to be removed, then a suitable 100 litre replacement tree such
      as Corymbia intermedia or Corymbia tessellaris shall be planted in the front setback area of Lot 1.

13.   All replacement vegetation shall be maintained for a minimum period of 12 months prior to the release of
      the security bond.

14.   Security in the form of a cash bond or trading bank guarantee to the sum of $5,000 must be submitted, to
      secure performance of all conditions of this approval, prior to the issue of a Development Permit for
      building works. The cash bond or trading bank guarantee will be returned on performance of the
      conditions of approval less any costs incurred by Council in respect of enforcing performance of this
      permit.
Landslide Hazard
15.   A geotechnical report, prepared by a registered professional engineer shall be obtained, and it shall:-

      15.1. certify that the site is not at risk from landslide emanating from the site or from other land; and
     15.2. identify methods of stabilising all buildings, accessways and uses areas.
     The development shall implement any recommendations of the geotechnical report.
Demolition or Relocation of Existing Dwelling
16.   Infrastructure including reticulated water, sewerage, stormwater, and electricity are to be protected from
      damage and made safe to the standard required by the regulatory authority.

17.   All infrastructure must be disconnected, capped or sealed including:-

      17.1. electricity meters removed and electrical wires disconnected; and

      17.2. telephone lines are disconnected; and

      17.3. high speed data cables and television provider boxes are disconnected and removed to the
            standard required by the regulatory authority.

18.   All building materials containing asbestos, including asbestos cement sheeting or roofing and lagging,
      must be removed from the building and disposed of in accordance with industry best practice.

19.   Waste generated during construction must be stockpiled in a centralised location and covered as required
      to prevent material being blown onto adjoining properties including the road reserve or food waste from
      generating vermin. All site waste must be disposed of to an approved waste disposal facility either directly
      or via an approved waste receptacle and collection service. Storage areas are to be located near the
      temporary access to the site so that access can be gained with out damage to infrastructure.




AOP2 c:\docume~1\aop2\locals~1\temp\bcl technologies\easypdf 5\@bcl@5008a612\@[email protected]

Used in these records

About this file

File size
63 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

00156A98.001.pdf · 63 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.