SUPERSEDED Decision Notice MCU15/0109
Officer: Denis Wallace Direct Telephone: 07 53296239 Our Reference: MCU15/0109 Your Reference: M2652 16 September 2016 Altum Constructions C/- JFP Urban Consultants Pty Ltd PO Box 6 MAROOCHYDORE QLD 4558 Dear Sir/Madam Decision Notice Sustainable Planning Act 2009 I refer to your application and advise that on 15 September 2016, Council decided to approve the application in full subject to conditions. Details of the decision are as follows: application details Application No: MCU15/0109 Street Address: Links Drive, Noosa Heads Real Property Description: Lot 6 SP 178340 Planning Scheme: The Noosa Plan (16 September 2013) Decision details The following type of approval has been issued: Development Permit for Material Change of Use of Premises - Multiple housing Type 4 - Conventional (44 units) Relevant period of approval The relevant period for this development approval is 4 years starting the day that this development approval takes effect. assessment manager conditions PLANNING When Conditions must be Complied With Unless otherwise stated, all conditions of this Decision Notice must be complied with prior to the use commencing, and then compliance maintained at all times while the use continues. Approved Plans Development undertaken in accordance with this approval must generally comply with the approved plans of development. The approved plans are listed in the following table, and may be further amended by the conditions of this approval. Plan No. Rev. Plan/Document Name Date DA01 06 LOCATION PLAN & PROJECT SUMMARY by Blackburne Jackson Design 14/7/16 DA02 10 SITE PLAN by Blackburne Jackson Design 14/7/16 DA03 11 SITE PLAN by Blackburne Jackson Design 14/7/16 DA04 05 SITE PLAN by Blackburne Jackson Design 14/7/16 DA05 05 SITE SECTIONS by Blackburne Jackson Design 08/07/16 DA06 05 BUILDING A: PLANS ELEVS & SECTION by Blackburne Jackson Design 14/7/16 DA07 05 BUILDING B: : PLANS by Blackburne Jackson Design 14/7/16 DA08 05 BUILDING B: ELEVATIONS & SECTION by Blackburne Jackson Design 14/7/16 DA09 05 BUILDING C: PLANS 14/7/16 DA10 05 BUILDING C: ELEVATIONS & SECTION by Blackburne Jackson Design 14/7/16 DA11 06 BUILDING D: BASEMENT by Blackburne Jackson Design 14/7/16 DA12 06 BUILDING D: LEVELS 1 & 2 14/7/16 DA13 05 BUILDING D: ELEVATIONS & SECTION by Blackburne Jackson Design 14/7/16 DA14 05 BUILDING E: BASEMENT by Blackburne Jackson Design 14/7/16 DA15 05 BUILDING E: LEVEL 1 by Blackburne Jackson Design 14/7/16 DA16 05 BUILDING E: LEVEL 2 by Blackburne Jackson Design 14/7/16 DA17 05 BUILDING E: ELEVATIONS by Blackburne Jackson Design 14/7/16 DA18 05 BUILDING E: SECTION by Blackburne Jackson Design 14/7/16 DA19 06 BUILDING F & G: BASEMENT by Blackburne Jackson Design 14/7/16 DA20 05 BUILDING F & G: LEVEL 1 by Blackburne Jackson Design 14/7/16 DA21 05 BUILDING F & G: LEVEL 2 by Blackburne Jackson Design 14/7/16 DA22 05 BUILDING F: ELEVATIONS by Blackburne Jackson Design 14/7/16 DA23 05 BUILDING F: ELEVATION & SECTIONS by Blackburne Jackson Design 14/7/16 DA24 05 BUILDING G: ELEVATIONS by Blackburne Jackson Design 14/7/16 DA25 05 BUILDING G: ELEVATIONS & SECTION by Blackburne Jackson Design 14/7/16 DA26 02 FINISHES PALETTE & SCHEDULE by Blackburne Jackson Design 14/7/16 DA28 02 FIRE & EVACUATION MANAGEMENT PLAN by Blackburne Jackson Design 14/7/16 DA30 06 HEIGHT PLANE PROJECTIONS by Blackburne Jackson Design 14/7/16 DA31 06 HEIGHT PLANE PROJECTIONS by Blackburne Jackson Design 14/7/16 DA101 05 LANDSCAPING LOWER POOL prepared by Blackburne Jackson Design 14/7/16 DA102 05 LANDSCAPING UPPER POOL prepared by Blackburne Jackson Design 14/7/16 DA103 05 BUILDING D LANDSCAPING prepared by Blackburne Jackson Design 14/7/16 DA104 05 BUILDING E LANDSCAPING prepared by Blackburne Jackson Design 14/7/16 DA105 05 BUILDING G & F LANDSCAPING prepared by Blackburne Jackson Design 14/7/16 DA106 05 BUILDING F & CORNER LANDSCAPING prepared by Blackburne Jackson Design 14/7/16 DA107 05 PLANT SPECIES PALETTE & HARDSCAPE MATERIALS prepared by Blackburne Jackson Design 14/7/16 15128/SK10 A2 Concept Siteworks and Drainage Layout Plan, prepared by Morgan Consulting Engineers 19/04/16 15128/SK11 A2 Concept Siteworks and Drainage Layout Plan –Sheet 1, prepared by Morgan Consulting Engineers 19/04/16 15128/SK12 A2 Concept Siteworks and Drainage Layout Plan – Sheet 2, prepared by Morgan Consulting Engineers 19/04/16 15128/SK13 A1 Concept Road 1 Longitudinal Section, prepared by Morgan Consulting Engineers 19/04/16 15128/SK14 A1 Concept Road 2 Longitudinal Section, prepared by Morgan Consulting Engineers 19/04/16 Nature and Extent of Approved Use The approved development comprises 4 x 1 bedroom, 22 x 2 bedroom and 18 x 3+ bedroom units, subject to compliance with the further requirements of Condition 4. Prior to the issue of a development permit for Operational Works associated with this approval, amended plans shall be submitted demonstrating compliance with The Noosa Plan’s limits for population density and gross floor area by reducing those aspects by a minimum of 1 person and 38m2 respectively. Building Height The maximum height of the development must not exceed the reduced levels shown on the approved plans. Certification must be submitted to Council from a Licensed Surveyor confirming the constructed buildings do not exceed the maximum height requirement of this Decision Notice. Performance Bond Security in the form of a cash bond or trading bank guarantee to the sum of $20,000 must be submitted to Council, to secure performance of all conditions of this approval, prior to the site pre-start meeting. The cash bond or trading bank guarantee will be returned on performance of the conditions of approval less any costs incurred by Council in respect of enforcing performance of this permit. Council reserves the right to call upon the bond or guaranteed sum to effect compliance with conditions. Street Identification The street address of the development must be clearly visible and discernible from the primary frontage of the site by the provision of a street number and, where appropriate, the building name. Water & Sewer Connections An underground connection to reticulated water and sewerage must be provided to the development site in accordance with the standards and requirements of Northern SEQ Distributor–Retailer Authority (Unitywater). A Certificate of Completion from the Northern SEQ Distributor–Retailer Authority (Unitywater) must be submitted to Council that certifies an underground connection to reticulated water and sewerage has been provided to the development site. Building Appearance All air conditioning units or other mechanical equipment must be fully enclosed or screened such that they are not visible from the street frontages or adjoining properties. All deck and balcony areas above ground floor must not be enclosed by permanent fixtures such as shutters, louvers, glass panelling or the like. External colours and finishes of the building must comprise of muted environmental tones that blend with the natural environment, as indicated on approved plan DA26 “Finishes Palette / Schedule” by Blackburne Jackson Design. Broad areas of light coloured walls (which appear white) shown on building elevations to Buildings D, E, F & G on the approved plans are not approved. Fencing Any new boundary fencing must be constructed to allow for the movement of fauna. Such fencing must: allow adequate clearance at ground level for local macropods not include use of barbed wire or similar materials provide regular opportunities for passage over and through for fauna Storage Each dwelling unit must be provided with an allocated secure storage area(s) within the basement carpark. Outdoor Lighting Devices Lighting associated with the use must be designed, sited, installed and tested to comply with Table 2.1 & 2.2 of Australian Standard AS4282-1997 “Control of the obtrusive effects of outdoor lighting” using a control level of 1. Certification must be submitted to council from a suitably qualified person* prior to commissioning the operation of the development which certifies that all outdoor lighting devices comply with AS4282-1997 and the requirements of this Decision Notice. Community Management Statement Any proposed Community Management Statement required for the development pursuant to the Body Corporate and Community Management Act 1997 must be submitted to Council for endorsement at the same time as submission of the Building Format Plan (or similar) to Council for compliance assessment. All clauses and by-laws of the proposed Community Management Statement must accord with the requirements of this Decision Notice. Landscaping Works The development site must be landscaped. The works must be undertaken in accordance with an Operational Works approval and Planning Scheme Policy 3 Landscaping Plants and Guidelines and must include in particular: the works shown on the Approved Plans the use of large tree species to provide visual screening of the bulk of the buildings. compliance with the approved bushfire management plan for the development. vegetated screening of any electrical transformers, bin storage areas, and the like, from the road frontage and the southern pathway. retention of the existing vegetation along the Resort Drive road reserve frontage. the provision of street furniture, specifically a public bench situated approximately half way up the path in the southern road reserve. control of all weeds species listed in the following standards and legislation: declared plants under the Land Protection (Pest and Stock Route Management) Act 2002 and sub-ordinate Regulation 2003. Undesirable species as listed in Planning Scheme Policy 3 Landscaping Plants and Guidelines All entry statements, fences, batters, retaining walls and buffer/screen plantings must be located entirely within private land and not within the public road reserve. The existing vegetation along the Resort Drive frontage road reserve, eastern road reserve and located outside of the 6m zone in the southern road reserve must be retained in accordance with an Arborist Report prepared by a qualified person* and endorsed through an Operational Works approval.*(Refer to Advisory Note) Fauna Management Vegetation must only be removed or disturbed in accordance with a Fauna Management Plan prepared by a qualified person* and endorsed through an Operational Works approval. *(Refer to Advisory Note) Any domestic cats kept on the property must be permanently confined within buildings and/or cat enclosures for the purpose of protecting proximate wildlife. All and successive community management statements must include a provision to enable the enforcement of this requirement. Bushfire Management The development must be carried out in accordance with section 7.0 of the Bushfire Hazard Assessment and Management Plan (document ref. AA1345BFIRE Rev.3) dated July 2016 prepared by Duke Environmental listed within this Decision Notice. A copy of the Bushfire Hazard Assessment and Management Plan listed within this Decision Notice must be provided to the nearest fire authority. Certification must be submitted to Council from a qualified person* which certifies that the development has been constructed in accordance with the bushfire management conditions of this Decision Notice, prior to the commencement of use. *(Refer to Advisory Note) ENGINEERING External Works External works, pathways, must be provided in accordance with an Operational Works approval, unless already constructed, and must include in particular: A new 2.0 metre wide concrete pathway must be constructed along the full length of the eastern boundary lines for Lot 6 SP178340 (this property) and Lot 3 SP 221524 (the adjoining site) generally within the created pathway reserve and to alignment protects existing trees. A new concrete pathway must be constructed within the unformed road reserve south to the site. This pathway must connect to the pathway along the eastern boundary and connect to the existing cul-de-sac end of Resort Drive, and shall be 2.0m wide and reduced to a minimum width of 1.5 meter where necessary to protect existing vegetation. The pathways must be designed and constructed in accordance with relevant standards and best engineering practice using method/s of construction that minimising impact on natural flora and fauna and maintenance needs also ensuring pedestrian safety. This condition is imposed pursuant to s665 of the Sustainable Planning Act 2009 being non-trunk infrastructure. Site Access and Driveways A sealed access driveway must be provided from the existing cul-de-sac of Resort Drive to all parking and manoeuvring areas of the development generally in accordance with approved plans and must be undertaken in compliance with an Operational Works approval and include in particular: Driveway crossover in accordance with IPWEAQ standard drawing RS-051. Compliant grades within the road verge to match any existing or future pathway. The relocation or modification to any existing services affected by the driveway construction. Suitable safety or traffic control measures, including warning signage, to improve driver awareness of pedestrians and enhance pedestrian and traffic safety. Two temporary cul-de-sac ends with a turning circle 9.0m in radius minimum must be constructed at both of the termination ends of the proposed driveway. The turning circles must be constructed of stable sealed surface, compacted gravel or an approved material to allow for vehicles, particularly refuse collection trucks, to turn around in forward gear. The works must include any required batters and/or retaining walls and be undertaken in accordance with an Operational Works approval. Car Parking A minimum of 80 car parking spaces must be provided and marked on the site generally in accordance with the approved plans. The works must be undertaken in accordance with an Operational Works approval and must include in particular: 15 visitor parking spaces within the total, which are clearly marked for that purpose and accessible at all times for visitor use. Crossfalls, gradients and vehicle headroom in accordance with Australian Standard AS2890: Parking Facilities. All car parking areas and access driveways must be maintained exclusively for vehicle parking and maneuvering and kept in a tidy and safe condition at all times. All car and bicycle parking areas must be line marked in accordance with approved plans, no dividing walls be constructed unless a further application for amendment is approved by Council. Directional signage must be provided to direct visitors and customers to building blocks and the car parking spaces provided on site. Service Vehicles Service vehicle parking, manoeuvring and standing spaces must be provided on the site. The works must be undertaken in accordance with an Operational Works approval and must provide suitable parking locations for emergency service vehicles. Internal Pedestrian Pathway Internal pedestrian pathways networks must be provided for the development generally in accordance with the approved plans. The works must be undertaken in compliance with an Operational Works approval and include: Footpath and steps 1.5m wide minimum of concrete or other approved materials throughout the development taking into consideration accessibility for people with disabilities. Signage and lighting at strategic locations to direct people to building entries and other facilities as may be required. Stormwater Drainage The site must be provided with a stormwater drainage system connecting to a lawful point of discharge. The works must be undertaken in compliance with a development permit for operational works and must include in particular: Stormwater collection and pipe system in accordance with the requirements of latest Queensland Urban Drainage Manual (QUDM) and related guidelines. Stormwater retention and/or detention systems must be provided within the property to ensure all stormwater runoffs from the site are maintained to its predevelopment rates for all storm events up and including 1% AEP. Electricity and Telecommunication Services Unless otherwise stipulated by telecommunications legislation at the time of construction, the development must be provided with all necessary conduits, pits and pipes to accommodate the future connection of optic fibre technology telecommunications. Certification must be submitted to Council from all relevant service providers which certifies that the development has met the requirements of this Decision Notice and all applicable legislation at the time of construction. Easements Prior to issue any Development Permit for Operation works the applicant must provide confirmation of a registered access easement has been created over the adjoining site, Lot 3 SP221524, to accommodate the proposed temporary turning circles of 9.0 metre in radius and 4.0 metre wide road shoulder for batter and retaining works generally in accordance the approved plans. Unless otherwise agreed in writing by the relevant service provider, any public or third party infrastructure located on the subject site must be placed within an easement registered against the title of the property. All easements must be designed in accordance with the planning scheme and granted at no cost to the Grantee. Where the Grantee is Council or a service authority, the easement documentation must be in accordance with the Grantee’s standard easement terms. Draft easement documentation must be submitted to Council for endorsement. All works must be kept clear of any existing or proposed easements on the subject land, unless agreed otherwise in writing by the Grantee. Earthworks and Retaining Walls All excavation and fill and associated batters and retaining works must be undertaken in accordance with an Operational Works approval and contained entirely within the subject site unless written permission from the respective landowner(s) is provided to Council. All works must be carried out in accordance with a site-specific geotechnical investigation report prepared by a qualified person* and submitted for endorsement by Council as part of the Development Application for Operational Works. The geotechnical investigation must be undertaken in accordance with the relevant provisions of AS 3798 Guidelines on Earthworks for Commercial and Residential Development and address all stability issues concerning the development site. *(Refer to Advisory Note) Acid Sulfate Soils Where excavations of non-imported soils below the elevation of 5m AHD are necessary for construction, the application for Operational Works for Bulk Earthworks, Stormwater and /or Landscaping must demonstrate and include certification from a suitably experienced and qualified geotechnical engineer of methods necessary to ensure construction and operation of the development: is consistent with Queensland Acid Sulfate Soil Technical Manual: Soil Management Guidelines; and will not result in the release of acid or associated metals; and will not cause localised lowering of groundwater. Erosion and Sediment Control Prior to the completion of the development, all site surfaces must be effectively stabilised. For the purpose of this condition, an effectively stabilised surface is defined as one that does not, or is not likely to result in visible evidence of soil loss caused by sheet, rill or gully erosion or lead to sedimentation, or lead to water contamination. WATER QUALITY Noosa Springs Lake Management The application for operational works approval must demonstrate, through water balance calculations prepared by a hydraulic engineer, that the hydraulic residence time of the Noosa Springs Lake System will not be reduced as a result of stormwater management on the site. Where stormwater runoff from the site will enter the Noosa Springs Lake System, Quarterly monitoring is required of stormwaters directed from the development to the Noosa Springs Lake System. Monitoring must be undertaken by a suitably qualified person using NATA accredited methods for the following parameters. Nitrite plus Nitrate as N (NOx) Total Kjeldahl Nitrogen (TKN) Total Nitrogen as N (TKN + NOx) Total Nitrogen as N Total Phosphorus as P Reactive Phosphorus as P (Dissolved) Reactive Phosphorus – Filtered Water quality monitoring results must be retained in electronic form by the property owner for a minimum of 5 years and must be made available to Noosa Council on request. This monitoring must continue until notified by Noosa Council that it is no longer needed. During the first 5 years of operation, for a minimum of 5 rainfall events per year, stormwater at the following locations and times must be collected and sampled for Total Nitrogen, Total Phosphorous and Total Suspended Solids using NATA accredited methods.: The release point from Precinct E2 for all waters directed to the Noosa Springs lake system. At monitoring point W6 shown on Plan A – Water Quality Monitoring Locations Noosa Springs by Jelliffe Environmental (Qld) Pty Ltd. The time for collection of water samples for monitoring must be quantified by the applicant’s hydraulic engineer within the Operational Works application for stormwater. The time for water quality monitoring shall be a minimum of the time of concentration for all waters from Precinct E2 destined for the Noosa Springs Lake System to reach the release point from Precinct E2, and within a maximum of 24 hours of commencement of rainfall events that generate runoff from Precinct E2. The 90th percentile concentrations of Total Nitrogen, Total Phosphorus and Total Suspended Solids measured within runoff from Precinct E2 must not be higher than the 90th percentile concentrations of those parameters measured within the receiving Noosa Springs Lake System. The applicant must notify Noosa Council within 24 hours of becoming aware of non-compliance with this condition. The application for Operational Works Approval must include: A monitoring strategy prepared by a suitably qualified person to demonstrate how the water monitoring obligations of this development approval will be met. A stormwater infrastructure design that incorporates a facility suitable for obtaining the water samples needed to fulfil the obligations of this development approval; Stormwater Quality Management All stormwater runoff from hardstand and fertilised landscaped areas of the development, including runoff destined for groundwater infiltration must be treated to achieve pollution reduction targets to achieve an 80% reduction in Total Suspended Solids, 60% reduction in Total Phosphorus and 45% reduction in Total Nitrogen compared to an untreated scenario. Where proprietary devices are proposed, maintenance must be in accordance with the manufacturer’s specifications. For vegetated stormwater assets, maintenance must be in accordance with the Water by Design Maintaining Vegetated Stormwater Assets, Version 1 Manual (2009). Material extracted from stormwater quality treatment devices during servicing and cleaning is to be removed from the site and disposed of by either a licensed waste removal contractor or by other lawful means Prior to issue of Operational Works approval, a 10 year maintenance contract including expected cost forecast, must be entered into for maintenance of any on site water quality treatment device. Records of maintenance activities undertaken are to be kept and made available to council officers upon request. Ongoing maintenance of stormwater quality treatment devices in accordance with this development approval must be detailed within any community management statement applicable to operation of the development. The Operational Works application for landscaping must demonstrate the landscaping design incorporates locally endemic vegetation adapted to grow on the sites indigenous soil, and requires no fertiliser or other external nutrient requirements after the first 3 years of establishment WASTE MANAGEMENT Waste Storage The development must provide waste storage and disposal facilities in accordance with Planning Scheme Policy 9, Waste Management, including an external imperviously paved area correctly sized for all refuse and recycling containers and suitably screened from public places and neighbouring properties. The site must be provided with a bin wash area with a cold-water tap, hose and drain outlet connected to sewer, via a bucket trap. The drain outlet is to be designed to prevent storm water entry to the sewerage system which can be achieved by a bunded area, with a nib wall height of 100mm maximum, enclosing a wash area of 700mm x 700mm minimum (max 0.7m²). Alternatively, the waste area can be roofed, or another appropriate design approved by Council. A Waste Management Plan (Operational) in accordance with Planning Scheme Policy No. 9 Waste Management and Planning Scheme Policy 11, Waste Management Plans* must be submitted for the day-to-day operation of the development and approved by Council’s Waste and Environmental Health Section, prior to issue of development permit for operational works. The Plan must include the following information: - types of wastes that will be generated from the activities approved within the development. estimated volumes or tonnage of both recyclables and waste generated. methods to be used for dealing with garden waste. initiatives to minimize waste either by waste prevention, reduction, re-use or recycling. description of procedures for getting all waste to the bins; the storage of bins and the collection of bins by the contractor. description of the design details of waste storage and recycling areas including size, location, elevation and floor plan, methods of bin washing and system to prevent storm water getting into sewer via the bin wash. description of types and volume of waste storage containers to be used. waste and recycling storage area shall include the provision of containers for all waste and recycling materials including putrescible matter, non-recycling waste, paper/ cardboard, glass, aluminium/steel cans, waste oil, styrofoam boxes, etc, and bin washing facilities connected to sewer. detailed description of vehicular access routes to collect waste. Where collection is off street, access must allow vehicles to enter and leave the site in a forward direction. ENVIRONMENTAL HEALTH Noise Written certification from a suitably qualified person must be submitted to Council confirming that sound pressure levels from all mechanical plant and equipment comply with the following : Air-conditioning and Refrigeration: 7am to 10pm: Maximum level allowable = background + 5dB(A) 10pm to 7am: Maximum level allowable = background + 3dB(A) Pumps: 7am to 7pm: Maximum level allowable = background + 5dB(A) 7pm to 10pm: Maximum level allowable = background + 3dB(A) 10pm to 7am: No audible noise. Assessment and certification is required immediately after installation of the equipment and prior to any occupation of the building. All equipment should be operating at the same time to test the overall noise level created, with the measurement location at either the residential boundary or outside the most exposed part of an affected building - whichever is the closest to the plant/equipment. The certification must be submitted to Council, which certifies that operational noise from any fixed plant and equipment complies with the requirements of this Decision Notice. referral agencies Not Applicable. Advisory notes The following notes are included for guidance and information purposes only and do not form part of the assessment manager conditions: Aboriginal Cultural Heritage Act 2003 There may be a requirement to establish a Cultural Heritage Management Plan and/or obtain approvals pursuant to the Aboriginal Cultural Heritage Act 2003 (ACH Act). The ACH Act establishes a cultural heritage duty of care which provides that: “A person who carries out an activity must take all reasonable and practicable measures to ensure the activity does not harm Aboriginal cultural heritage”. It is an offence to fail to comply with the duty of care. Substantial monetary penalties may apply to individuals or corporations breaching this duty of care. Injunctions may also be issued by the Land and Resources Tribunal, and the Minister administering the ACH Act can also issue stop orders for an activity that is harming or is likely to harm Aboriginal cultural heritage or the cultural heritage value of Aboriginal cultural heritage. You should contact the Cultural Heritage Unit on 07 3247 6212 to discuss any obligations under the ACH Act. Equitable Access and Facilities The plans for the proposed building work have NOT been assessed for compliance with the requirements of the National Construction Code - Building Code of Australia (Volume 1) as they relate to people with disabilities. Your attention is also directed to the fact that in addition to the requirements of the National Construction Code as they relate to people with disabilities, one or more of the following may impact on the proposed building work: the Disability Discrimination Act 1992 (Commonwealth); the Anti-Discrimination Act 1991 (Queensland); and the Disability (Access to Premises – Buildings) Standards. Development Compliance Inspection Prior to the commencement of the use, please contact Council's DA Planning Section to arrange a Development Compliance Inspection. Resubmission of Amended Plans Required Conditions of this Decision Notice require resubmission of plans to Council with amendments. Please address the amended plan/s to Council’s Planning Assessment Branch with the Reference No. MCU15/010, separate to any Operational Works application. Infrastructure Charges This Development Permit will trigger an “Infrastructure Charge Notice” to be issued in accordance with Council’s “Charges Resolution” made pursuant to the Sustainable Planning Act 2009 and in conjunction with the State Planning Regulatory Provision (Adopted Charges). Building and Construction Industry (Portable Long Service Leave) Levy The QLeave levy must be paid prior to the issue of a development permit where it is required. Council will not be able to issue a Decision Notice without receipt of details that the Levy has been paid. QLeave contact: 1800 803 481 (free call) or (07) 3212 6855. Co-ordination of Operational Works Assessment Additional application fees apply to Operational Work applications where the different aspects of the works are lodged separately. Significant savings in application fees will result if all works are lodged in a single application. Preparation of a Preliminary Construction Management Plan The works identified in this Decision Notice will be required to be carried out in accordance with a Construction Management Plan endorsed by Council through an approval for Operational Works. To ensure expedient assessment of any Operational Works application, the applicant is advised to submit a preliminary Construction Management Plan that addresses the requirements of the planning scheme. In particular, the preliminary Construction Management Plan should address the following: Traffic management during all aspects of the construction phase including: A Traffic Management Control Plan in accordance with the Manual of Uniform Traffic Control Devices (MUTCD) detailing all temporary signage and traffic control measures prior to construction. Maintenance of safe pedestrian access across the frontage of the site both during daily construction and after daily construction has ceased. Proposed fencing to the site during the construction phase of the development. Maintenance and protection of water quality and existing drainage lines through the construction site, through the implementation of appropriate erosion and sediment control measures. Works programme identifying key components of the works and their respective durations. Establishment of a communication protocol with the general public, adjoining owners, emergency services and local businesses to advise of agreed construction times, impacts on traffic and services and other relevant issues. identification of complaint management procedures including: Contact details for the on-site manager. Dispute resolution procedures. Details on the location of external fill sites/sources, the haulage route, type of vehicle to be utilised during filling operations and frequency of usage. NB any damage to the existing road system as a result of haulage operations shall be fully repaired at the applicant’s expense It is acknowledged that the Construction Management Plan will be a draft document requiring finalisation upon appointment of the Principal Contractor employed to construct the works and a final document will be required to be submitted at the Pre-Start Meeting for the project. Qualified Person For the purpose of preparing a Geotechnical Report, and for certifying geotechnical stability for the development, a qualified person is considered to be a person who: is a Registered Professional Engineer of Queensland (RPEQ); and has a degree in civil engineering or engineering geology; and Has a minimum of 5 years experience in the field of geotechnical engineering or engineering geology. property notes Not Applicable preliminary approval overriding planning scheme Not Applicable further development permits required Type of Development Permit required Subject of the required Development Permit Development Permit for Building Works All Building Works Development Permit for Operational Works Landscaping, vegetation removal, carparking and access, site civil works, earthworks, roadworks, erosion and sediment control, frontage works, pedestrian pathways, and stormwater management. self assessable codes The following codes for self-assessable development related to the development approval issued under this Decision Notice must be complied with. Advertising Devices Code submissions There were 3 properly made submissions about the application. In accordance with Sustainable Planning Act 2009, the name and address of the principal submitter for each properly made submission is provided and attached. reasons/grounds for approval Not Applicable RIGHTS OF APPEAL You are entitled to appeal against this decision. A copy of the relevant appeal provisions from the Sustainable Planning Act 2009 is attached. During the appeal period, you as the applicant may suspend your appeal period and make written representations to Council about the conditions contained within the development approval. If Council agrees or agrees in part with the representations, a “negotiated decision notice” will be issued. Only one “negotiated decision notice” may be given. Taking this step will defer your appeal period, which will commence again from the start the day after you receive a “negotiated decision notice”. (Refer to Part 8 “Dealing with decision notices and approvals” - Division 1 “Changing decision notices and approvals during applicant’s appeal period” of the Sustainable Planning Act 2009.) OTHER DETAILS If you wish to obtain more information about Council’s decision, electronic copies are available on line at www.noosa.qld.gov.au, or at Council Offices. Yours faithfully Kerri Coyle Manager Planning & Environment cc Unitywater Enc: Infrastructure Charge Notice Infrastructure Agreement Approved Plans/Documents List of Submitters Appeal Rights List of Submitters SUSTAINABLE PLANNING ACT 2009 & SUSTAINABLE PLANNING REGULATION 2009 Only Properly Made Submissions are to be included in this notice (s335 (1) (l)) Name Email Address Address Marcus Dolby Marcus@dolbyproperty,com.au Heather Marshall [email protected] 837/100 Resort Drive, Noosa Heads A & P Taylor [email protected] Appeal Rights SUSTAINABLE PLANNING ACT 2009 & SUSTAINABLE PLANNING REGULATION 2009 The following is an extract from the Sustainable Planning Act 2009 (Chapter 7). MATERIAL CHANGE OF USE, RECONFIGURING A LOT & OPERATIONAL WORKS Division 8 Appeals to court relating to development applications and approvals 461 Appeals by applicants (1) An applicant for a development application may appeal to the court against any of the following— (a) the refusal, or the refusal in part, of the development application; (b) any condition of a development approval, another matter stated in a development approval and the identification or inclusion of a code under section 242; (c) the decision to give a preliminary approval when a development permit was applied for; (d) the length of a period mentioned in section 341; (e) a deemed refusal of the development application. (2) An appeal under subsection (1)(a), (b), (c) or (d) must be started within 20 business days (the applicant’s appeal period) after— (a) if a decision notice or negotiated decision notice is given—the day the decision notice or negotiated decision notice is given to the applicant; or (b) otherwise—the day a decision notice was required to be given to the applicant. (3) An appeal under subsection (1)(e) may be started at any time after the last day a decision on the matter should have been made. 462 Appeals by submitters—general (1) A submitter for a development application may appeal to the court only against— (a) the part of the approval relating to the assessment manager’s decision about any part of the application requiring impact assessment under section 314; or (b) the part of the approval relating to the assessment manager’s decision under section 327. (2) To the extent an appeal may be made under subsection (1), the appeal may be against 1 or more of the following— (a) the giving of a development approval; (b) any provision of the approval including— (i) a condition of, or lack of condition for, the approval; or (ii) the length of a period mentioned in section 341 for the approval. (3) However, a submitter may not appeal if the submitter— (a) withdraws the submission before the application is decided; or (b) has given the assessment manager a notice under section 339(1)(b)(ii). (4) The appeal must be started within 20 business days (the submitter’s appeal period) after the decision notice or negotiated decision notice is given to the submitter. 463 Additional and extended appeal rights for submitters for particular development applications (1) This section applies to a development application to which chapter 9, part 7 applies. (2) A submitter of a properly made submission for the application may appeal to the court about a referral agency’s response made by a prescribed concurrence agency for the application. (3) However, the submitter may only appeal against a referral agency’s response to the extent it relates to— (a) if the prescribed concurrence agency is the chief executive (environment)—development for an aquacultural ERA; or (b) if the prescribed concurrence agency is the chief executive (fisheries)—development that is— (i) a material change of use of premises for aquaculture; or (ii) operational work that is the removal, damage or destruction of a marine plant. (4) Despite section 462(1), the submitter may appeal against the following matters for the application even if the matters relate to code assessment— (a) a decision about a matter mentioned in section 462(2) if it is a decision of the chief executive (fisheries); (b) a referral agency’s response mentioned in subsection (2). 464 Appeals by advice agency submitters (1) Subsection (2) applies if an advice agency, in its response for an application, told the assessment manager to treat the response as a properly made submission. (2) The advice agency may, within the limits of its jurisdiction, appeal to the court about— (a) any part of the approval relating to the assessment manager’s decision about any part of the application requiring impact assessment under section 314; or (b) any part of the approval relating to the assessment manager’s decision under section 327. (3) The appeal must be started within 20 business days after the day the decision notice or negotiated decision notice is given to the advice agency as a submitter. (4) However, if the advice agency has given the assessment manager a notice under section 339(1)(b)(ii), the advice agency may not appeal the decision. 465 Appeals about decisions relating to extensions for approvals (1) For a development approval given for a development application, a person to whom a notice is given under section 389, other than a notice for a decision under section 386(2), may appeal to the court against the decision in the notice. (2) The appeal must be started within 20 business days after the day the notice of the decision is given to the person. (3) Also, a person who has made a request under section 383 may appeal to the court against a deemed refusal of the request. (4) An appeal under subsection (3) may be started at any time after the last day the decision on the matter should have been made. 466 Appeals about decisions relating to permissible changes (1) For a development approval given for a development application, the following persons may appeal to the court against a decision on a request to make a permissible change to the approval— (a) if the responsible entity for making the change is the assessment manager for the application— (i) the person who made the request; or (ii) an entity that gave a notice under section 373 or a pre-request response notice about the request; (b) if the responsible entity for making the change is a concurrence agency for the application—the person who made the request. (2) The appeal must be started within 20 business days after the day the person is given notice of the decision on the request under section 376. (3) Also, a person who has made a request under section 369 may appeal to the court against a deemed refusal of the request. (4) An appeal under subsection (3) may be started at any time after the last day the decision on the matter should have been made. 467 Appeals about changing or cancelling conditions imposed by assessment manager or concurrence agency (1) A person to whom a notice under section 378(9)(b) giving a decision to change or cancel a condition of a development approval has been given may appeal to the court against the decision in the notice. (2) The appeal must be started within 20 business days after the day the notice of the decision is given to the person. [word/footer1.xml] Page 19 of 19 [word/footer2.xml] PO Box 141 P. (07) 5329 6500 [email protected] TEWANTIN QLD 4565 F. (07) 5329 6501 www.noosa.qld.gov.au Page 1 of 19 [word/header1.xml] MCU15/0109 [Attachment: image3.png (image text)] K Coy fs [Attachment: image4.png (image text)] a mm NOOSA COUNCIL
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalSearchable page text hides email addresses. Original files are unchanged and may show email addresses.