24. A 5% cost of works to become Council assets or $1,500 bond (whichever is the greater) will
be imposed on construction works during the maintenance period, which is a minimum period
of 12 months duration. Such bond must be lodged by, and shall only be accepted from the
Developer for the works.
25. Certification of completed works must be provided to Council by the supervising engineer.
26. The works to become Council assets will not be accepted "On Maintenance" until the
landscaping is completed.
27. These works are also to be in compliance with the relevant conditions of Development Permit
No. 2005/0391.
28. Notwithstanding that Council has checked the plans with due care, where it is found during
construction that variations from Council's standards exist, then Council standards shall apply
5 REFERRAL AGENCY CONDITIONS
The referral agencies applicable to this application are:
Referral Trigger Referral Status Referral Agency Referral Address
Nil
6 APPROVED PLANS/DOCUMENTS
The approved plans and / or documents for this development approval are listed in the following
table:
Plan / Document No. Rev. Plan / Document Name Date
0501 – LA 01 Landscape Plan – Tropical Plantscapes August 2007
16322-OW1 Operational Works & Drainage June 2007
(Sediment Control Plan) – SCG
Consulting Engineers
16322-H2 A Hydraulics Services (Stormwater 24 August 2006
Drainage Plan) – SCG Consulting
Engineers
0501 – A 07 Perspectives (Access Section) – design May 2007
42 Pty Ltd
0501 – A 01’A’ A Basement Floor Plan (Access & June 2007
Carpark) – design 42 Pty Ltd
7 ADVISORY NOTES
The following Advisory Notes are for information purposes only and do not form conditions of
approval:
1. Should any changes or modifications to the approved plans be required as a result of
construction constraints, a Change to an Existing Approval Application under the Integrated
Planning Act must be made. Amended plans clearly indicating the changes must be lodged
with this application along with the appropriate fees.
Aboriginal Cultural Heritage Act 2003
There may be a requirement to establish a Cultural Heritage Management Plan and/or obtain
approvals pursuant to the Aboriginal Cultural Heritage Act 2003 (ACH Act).
Page 5 of 8
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Decision Notice - 010.2007.00002081.001 [As Published]Related documentApplication case desk ↗
About this file
- File size
- 63 KB (small file)
- File type
No other editions are linked here.