Arboricultural Impact Assessment - Palm Lakes Resort Cooroy - Revision 1 - IAS17818 - 22 August 2025
Appendix 2: Tree Management Plan (TMP) – Works
Progress: Development Phase
Stage Tasks Specific Outcomes
Pre-construction Phase
Prepare and finalise Project Arborist to be appointed Submit Arboricultural reports
Arboricultural Impact Review tree details in all approved including Arboricultural
Assessments for Arboricultural reports following any new Impact Assessment for final
submission to Council issue of plans Council Approval
Project Arborist to conduct Prior to meeting: Prestart Certification and
Prestart Meeting with all TPZ temporary protection/fencing installed approvals in place & available
representatives involved in Arboricultural Report, TPP (including TPS) & onsite with CMP
construction Council approval copies to be included in
CMP and made available to onsite crews
Commencement - Construction Phase
Initial Site Preparation Project Arborist to supervise all tree work. Compliance Certification of
Construction crew or others are not to Arboricultural works for
remove any part of a tree. Arborist prestart lodgement to Council
site inspection.
Arborist certification of TPZ
measures.
Prestart Toolbox Meeting All relevant onsite crews to be briefed by Arborist Site Audit Reporting
Project Arborist prior to commencement of system to be in place. Copies
each work phase. of Arboricultural Report to be
Project Arborist must be notified and onsite retained onsite.
at all times when construction works are
within or close to TPZ. Arboricultural Site Audit
Note: Onsite attendance of Project Arborist Statement/s will not be
is a condition for issue of Arboricultural Site issued retrospectively
Audit Statement/s.
Construction Phase
Site Establishment Project Arborist to monitor tree health Instigate remedial tree care
during establishment phase including bulk measures if required
earthworks, changes in hydrology etc.
Construction work Site Manager to liaise with and ensure Any remedial tree works to
Project Arborist is advised in time to allow be carried out by qualified
them to be present for all work carried out arborists under supervision
within TPZ area including any work likely to of Project Arborist.
affect identified tree/s. Any deviation/s from
approved plans to be approved by Project Project Arborist is
Arborist. Project Arborist to provide ongoing responsible for issue of
Site Audit Certification of all work within Arborist Site Audit Reports.
TPZ
Practical Completion Project Arborist to carryout review of tree On Project Arborist approval,
health and vigour and advise on TPZ fencing. carryout removal of
remaining temporary tree
protection measures
Post Construction Phase
Final Arborist inspection Carryout tree health review and provide Issue of final Arborist Site
recommendations for required tree care. Audit Compliance Statement
for inclusion in final DA
documentation and sealing.
90 | P a g e www.independentarb.com.au
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Appendix B - Arborist Report 22 August 2025.pdfRelated documentApplication case desk ↗
About this file
- File size
- 29.7 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.