                       AGENDA


              Special Meeting


              Thursday 7 March 2019

                 commencing at 10.00am
         Council Chambers, 9 Pelican Street, Tewantin



Committee:   Crs Tony Wellington (Chair), Jess Glasgow, Ingrid Jackson,
             Joe Jurisevic, Frank Pardon, Brian Stockwell, Frank Wilkie



                    “Noosa Shire – different by nature”
Log in to download the original file

2019-03-07 Special Meeting Agenda(PDF, 2MB).pdf · 1.6 MB (small file)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

Full text of the other 15 sections

Section 2

SPECIAL MEETING AGENDA                                         7 MARCH 2019


TABLE OF CONTENTS



ITEM                                                                   PAGE

ATTENDANCE & APOLOGIES                                                      -

REPORTS

1.     1718T147 TEWANTIN ADMINISTRATION BUILDING ROOF REFURBISHMENT        3

2.     PLANNING & ENVIRONMENT COURT APPEAL NO. 456/2018 – PROPOSED
       CLEARING OF VEGETATION IN DAVID LOW WAY, ACCESS AND OFFSET
       PLANTING IN BEACH RESERVE                                           9


MEETING CLOSURE                                                             -




                                                                 Page 2 of 16

Section 3

SPECIAL MEETING AGENDA                                                                        7 MARCH 2019


1.                       1718T147 TEWANTIN ADMINISTRATION BUILDING ROOF REFURBISHMENT
Document i nformati on




Author                              Building & Facilities Coordinator, Chris Steel
                                    Infrastructure Services Department

Index                               ECM / Project and Contract / 1718T147 – 06 Reports to Council
                                    ECM / Subject / Assets / Buildings
                                    ECM / Property (T1) / 9 Pelican Street Tewantin

Attachments                         1.    1718T147 – Evaluation Workbook


EXECUTIVE SUMMARY
This report provides a recommendation for the contract award of the preferred contractor for the
Tewantin Administration Building roof replacement and solar installation.

RECOMMENDATION
That Council note the report by the Building Facilities Coordinator to the Special Meeting dated 7
March 2019 and award contract 1718T147 to Midson Constructions (Qld) Pty Ltd for an initial lump
sum price of $701,786.00 (excl. GST), and a final contract price of $649,978.00 (excl. GST)
following the small-scale technology certificate rebate.

REPORT
The proposed contract is to rehabilitate the existing roof on the Tewantin Administration Building
and installation of a new 90kW PV solar system. The roof is part of the original build and has come
to the end of its useful life. The 90kW solar system is part of Zero Emissions Noosa (ZEN) plan
and will provide sustainable energy for the building.
The contract works are proposed to commence on site at the beginning of April 2019 with
construction anticipated to be completed by the end of June 2019.

1.                       Design
The Tewantin Administration Building roof design will remain identical to the original with a slight
change in pitch to ensure storm compliance. The roofing design has taken into consideration the
close proximity of the river to ensure protection from the salt air.

2.                       Tender Process
Due to the value of the works being greater than $200,000 and the complex nature of the project,
Council went out to tender in accordance with the Local Government Act 2009 to obtain
experienced and capable contractors.
The invitation to tender 1718T147 was released via LG Tender Box on 6 September 2018 and
advertised in local publications, the Sunshine Coast Daily on 8 September 2018 and the Noosa
News on 11 September 2018.
The tender closed at 2.00pm, Tuesday 2 October 2018 with two submissions received (listed in
alphabetical order).
                        Infraco Pty Ltd
                        Midson Construction (Qld) Pty Ltd
A key component of the tender was the request by Council to include the 90kW solar PV system
with Solar Edge monitoring. The design and tender scope of the solar system was provided by
ERM Power in collaboration with Council’s ZEN.


                                                                                                Page 3 of 16

Section 4

SPECIAL MEETING AGENDA                                                                7 MARCH 2019


3.    Tender Assessment
The tender evaluation panel (below) comprised both internal staff and two external experts who
undertook an assessment of the two conforming tender submissions.
     Council Officers
      -   Building and Facilities Coordinator (Evaluation Chair)
      -   Facilities Officer
      -   Project Manager, Transport Innovation
      -   Work Health and Safety Advisor
     External Experts
      -    Mode Design (Roof)
      -    ERM Power (Solar)

The tenders were evaluated against the following criteria:
     Capability and Resourcing
     Contract Experience and Capacity
     Methodology
     Quality
     Health and Safety
     Environment and Sustainability
     Contribution to local Economy
     Price
Clarifications of tender submission responses, including the tendered lump sum price breakdown,
were sought from both respondents, after which Midson Constructions (Qld) Pty Ltd was
shortlisted.
Evaluation was delayed as a result of clarifications raised during the evaluation process. Items
requiring clarification included the solar design, Solar STC’s fixed cost, potential contract variation
concerns, site management, and Council staff relocation during work and workplace health and
safety. The evaluation team met on several occasions to discuss the tenders and also with the
short listed contractor to finalise clarifications and project delivery via presentations.
Under the Federal Government’s Small-scale Renewable Energy Scheme, Small-scale
Technology Certificates (STCs) are a tradable commodity attached to eligible installations of
renewable energy systems (including solar panels). Clarification was sought and confirmed from
Midson Constructions (Qld) Pty Ltd regarding this element due to Council being bound by the
Statutory Bodies Financial Arrangement Act 1982 which does not allow Council to enter into
derivative transactions. The confirmed amount is noted in the Finance section below.
The evaluation panel considers Midson Constructions (Qld) Pty Ltd to be the most advantageous
to Council and presents the best value for money. Midson Constructions (Qld) Pty Ltd’s tender
submission is favourable on the following basis:
     demonstrated previous experience with similar large value commercial projects of this
      nature;
     demonstrated good track record working for Noosa Council and on other similar projects;
     Midson Constructions (Qld) Pty Ltd have the necessary resources and processes in place to
      deliver the project;
     Competitive pricing.

4.    Program
As part of the tender clarification process, Midson Constructions (Qld) Pty Ltd clarified that
completion of the project could be accomplished before the end of financial year in June 2019 with
a three-month project completion time frame, weather permitting.


                                                                                         Page 4 of 16

Section 5

SPECIAL MEETING AGENDA                                                                       7 MARCH 2019


5.      Access and Noise Considerations During Construction
The Tewantin Administration Building will remain operational during the construction phase of the
project, with access restricted to the Level 3 main entrance and other areas at certain times
throughout a working day, due to crane lifts and works being completed above Council staff work
areas.
During construction, excessive noise may be experienced by staff and this may require some areas
to be restricted for extended periods and staff relocated. Buildings and Facilities has established a
working group to plan the scheduled relocations to meet business needs, and the working group
has begun identifying areas and strategies for staff relocation.
The schedule and timing of staff relocations can only be finalised and agreed upon once the tender
has been awarded. The working group will communicate advance notice to staff to mitigate
disruption to business.

Previous Council Consideration
Nil

Finance
Council’s capital program includes funding for the Tewantin Administration Building roof
replacement and solar installation. Council has currently allocated $770,000.00 (excl. GST) in the
current budget, representing a revised budget increase based on the tender submissions and solar
component costs.

 Item                                                                               Cost (excl. GST)
 Costs to date (December 2018)                                                                         $9,969
 Tendered Contract Value                                                                            $771,965
 Superintendent Costs                                                                                $12,000
 less Small-scale Technology Certificates (STCs) rebate                                             ($51,808)
 Project sub-total                                                                                  $742,126
 Potential relocation costs - includes ICT, Accommodation/Lease and Internal                         $72,040*
 Building and Facilities costs

 Total Project Cost                                                                              $814,166.00

*Whilst these costs are not anticipated, based on project team discussions to date with stakeholders/staff
along with the potential for utilising existing Council facilities, they have been included as a ‘worse case’
scenario.

Risks & Opportunities
 Finance Risks                                   Mitigation
 Council requests for scope increases            This is to be mitigated through the Project Control Group
                                                 (PCG) and Capital Works Executive (CWE) management
                                                 and limitation of client requested scope variations
 Contractor claims for variations for            Mitigation through PCG and CWE with allowances made
 unforeseen issues.                              within the contingency.
 Energex delay the solar connection              Continued communication with the solar provider and
 approval                                        Energex to maintain the scheduled completion.
 Additional costs due to staff relocation        Existing Council facility options, staff working from home,
 during the project                              as well as allowing for relocation costs within the project
                                                 costs.




                                                                                                Page 5 of 16

Section 6

SPECIAL MEETING AGENDA                                                                        7 MARCH 2019


    Program Risks                                  Mitigation
    There is a potential that the project is       Construction through the typically dry season aims to
    delayed due to bad weather.                    mitigate this.
    Materials supply, including solar system.      Continued communication and frequent meetings with the
                                                   contractor to ensure industry suppliers are providing
                                                   updates on project timing.
    Resource risk                                  Midson Constructions (Qld) Pty Ltd has nominated a
                                                   capable team undertaking construction. The appointment
                                                   of an external superintendent mitigates the resource risk
                                                   for Council.
    Construction takes longer than allowed for.    The contractor has demonstrated to be well resourced
                                                   with an ability to increase crews to reduce risk of delays.
    Energex delay the solar connection             Midson Constructions (Qld) Pty Ltd will ensure continued
    approval.                                      communication with the solar provider and Energex to
                                                   maintain the scheduled completion.

    Safety Risks                                   Mitigation
    Work place health and safety issues            Midson Constructions (Qld) Pty Ltd have demonstrated
    throughout project, including high risk work   extensive experience at working at heights and would be
    due to working at heights.                     appointed as the principal contractor responsible for all
                                                   work place health and safety of the site.
    Council staff experience excessive noise       B&F working group to organise relocations through pre
                                                   designated areas and locations.

    Scope and Quality Risks                        Mitigation
    Risk of not meeting project objectives.        To be managed through Council officer reviews/
                                                   milestone meetings, and supported by specialist
                                                   consultants who developed the original design and
                                                   specifications.

    Public Disruption and Council
                                                   Mitigation
    Reputation Risks
    Noise from plant and equipment may be a        This will be minimised as much as possible with noisy
    cause of disruption to local residents.        works completed during business hours.
    Solar system does not export to the grid as    Energy usage would be at approx. 85% of total capacity
    per design.                                    based on a seven day week of power creation.

Consultation
External Consultation - Community & Stakeholder
Liaison with neighbouring properties will be undertaken.

Internal Consultation
        Corporate Services was consulted on both the procurement processes and budget.
        Infrastructure Services was consulted on the tender scope, submissions and value.
        Workplace Health and Safety (Executive Support) was consulted on the evaluation of tender
         submissions.
        Environment and Sustainable Development was consulted on the tender scope and
         evaluation of submissions.




                                                                                                  Page 6 of 16

Section 7

SPECIAL MEETING AGENDA                                                                  7 MARCH 2019


Departments/Sections Consulted:

 X   Chief Executive Officer       Community Services                      x   Corporate Services
     Executive Officer             Director                                X   Director
 X   Executive Support             Community Development                   X   Financial Services
                                   Community Facilities                        ICT
                                   Libraries & Galleries                   X   Procurement & Fleet
                                   Local Laws                                  Property
                                   Waste & Environmental Health                Revenue Services

     Executive Services        X   Environment & Sustainable Development   X   Infrastructure Services
     Director                      Director                                X   Director
     Community Engagement          Building & Plumbing Services                Asset Management
     Customer Service              Development Assessment                  X   Buildings and Facilities
     Governance                    Economic Development                        Civil Operations
     People and Culture        X   Environmental Services                      Disaster Management
                                   Strategic Land Use Planning             X   Infrastructure Planning,
                                                                               Design and Delivery




                                                                                            Page 7 of 16

Section 8

SPECIAL MEETING AGENDA   7 MARCH 2019




                           Page 8 of 16

SPECIAL MEETING AGENDA                                                                 7 MARCH 2019

                                                                       Att. 1- Evaluation Spreadsheet
                                            Final Evaluation

            NOOSA SHIRE COUNCIL        Weighted Attribute Evaluation Spreadsheet - Final Evaluation

             Sa
                                                            PRICE
         (Conforming Tenders Only}                        * Price includes
                                                       Respondent's STC repate
       7
       2
         NON-CONFORMING TENDERS

                                                              1               2

                                                                Resutant
         Evaluation Criteria                                    score x
       femratmenne              fm |                           om | ae | wo |
         fometnmceones |                    oe |» |                 | = | ae |
         a
         Se ee
       feammaseisy                   |           | | sm | om | 20 |
         emomnesme | = | |                                          | = | om |
       foment                        |       =      | = f= |                 |  em |
         nee, =                                                      |     se

         Total Fees (Pc}                     35%           $684,251         $649,978
         Average Fees (Pav) $_..______._-_-_. $667,115
         Price Score                                          37             103
         Normalised Price Score (Pn)                         35              100
         Weighted Price Score (Pw)

                                                        Building & Facilities Coordinator, Infrastructure Services
                                                             Facilities Officer, Infrastructure Services
                                                             Project Manager, Infrastructure Services
                                                                  External Technical Expert
                                                               WHAS Advisor, Executive Services

           The Contract Administrator confirms the above scores and   ———
                      weightings of this evaluation              =<———~,
        [Contract Administrator's signature:|       | Bulking & Facilities Coordinator, Infrastructure Services |

   Copy of 1718T147 - Evaluation Workbook V4   Page 1                                     1/03/2018
                                                                                          Page 8 of 16

Section 9

SPECIAL MEETING AGENDA                                                                                7 MARCH 2019


2.                       PLANNING & ENVIRONMENT COURT APPEAL NO. 456/2018 – PROPOSED CLEARING
                         OF VEGETATION IN DAVID LOW WAY, ACCESS AND OFFSET PLANTING IN BEACH
                         RESERVE
Document i nformati on




Author                              Manager Development Assessment, Kerri Coyle
                                    Environment & Sustainable Development Department

Index                               ECM/ Application / RAL17/0501 / Case/ 456/2018 (Kenlynn Pty Ltd)

Attachments                         1.   Original Proposal Plans
                                    2.   Amended Proposal Plans


EXECUTIVE SUMMARY
Not applicable.

RECOMMENDATION
That Council note the report by the Manager Development Assessment to the Special Meeting
dated 7 March 2019 regarding Planning & Environment Court Appeal No. 456/2018 and instruct
its solicitor to advise the Court and the Appellant as follows:
1.                       As road authority for the area, that it does not accept nor will it permit the removal of
                         vegetation and the maintenance thereof into the future for the purposes of achieving sight
                         lines in David Low Way as proposed by the traffic engineers in their joint report of 21
                         December 2018;
2.                       That it will not allow site access in the location presently proposed by the Appellant’s
                         development proposal; and
3.                       As trustee of the adjoining beach reserve, that it does not accept the Appellant’s proposal to
                         provide offset planting in the beach reserve, nor will it undertake any responsibility for
                         maintenance thereof into the future.



REPORT
A report on a development application to subdivide 1 lot into 6 residential lots and create an access
easement at 2 David Low Way, Castaways Beach was considered by Council at its Ordinary
Meeting on 18 January 2018.
Council at its Ordinary Meeting on 18 January 2018 resolved to refuse the application for the
following reasons:
1.                       The proposed development is contrary to the Overall and Specific Outcomes of the Eastern
                         Beaches Locality Code of the Noosa Plan. The development proposes significant clearing
                         that is contrary to the Locality Code which requires protection of the vegetated character and
                         views from the David Low Way and protection of native vegetation.
2.                       The proposed development is contrary to the Biodiversity code as it involves clearing of
                         vegetation that is mapped as Environmental Protection and Riparian vegetation under the
                         Noosa Plan.
3.                       The proposed development will result in unacceptable impacts on the visual amenity and
                         character of the area.
4.                       The applicant has not demonstrated that a compliant, safe access is able to be provided to
                         the site in accordance with required standards. To achieve a safe access significant clearing
                         of vegetation and earthworks in the road reserve is also likely to be required.

                                                                                                         Page 9 of 16

Section 10

SPECIAL MEETING AGENDA                                                                             7 MARCH 2019


5.    The proposal is an overdevelopment of the site with the resultant development form
      detrimentally affecting the environmental and amenity values of the site.
6.    The proposed development represents a poor planning outcome for the site, with the
      subdivision layout failing to provide street frontage for the lots and an excessive number of
      lots with access via an easement. The proposed access arrangements are likely to result in
      ongoing management and maintenance issues for future residents of these lots.
The applicant subsequently appealed the decision seeking that the application be approved subject
to reasonable and relevant conditions. During the course of the appeal the applicant changed their
proposal reducing the number of lots proposed from 6 to 5 lots. The original proposal plans are
included as Attachment 1 and the amended lot layout is included as Attachment 2.
The amended plans primarily increase the area to be protected by an environmental covenant from
3590m2 to 3750m2, change the location of the covenant areas and increase the setback from the
riparian zone to the proposed building envelope from 56m to a minimum of 60m. The proposed
driveway access remains in a similar location to the original proposal plans but with some minor
changes to improve the driveway grade. Overall the layout and access generally remain the same
and do not resolve the reasons for refusal and address the conflicts with The Noosa Plan.
Council’s experts and the Appellant’s experts including planning, ecology, bushfire and traffic have
since completed joint expert reports on the amended plans and the matter is now set down for
hearing for 5 days commencing 18 March 2019 in Brisbane.
Review of the joint expert reports prepared for the appeal show that while both traffic experts agree
that a safe access can be achieved to the site, the appellant’s proposal will necessitate the removal
of substantial vegetation in the road reserve on David Low Way (and maintenance of that area of
the road reserve) to ensure sight line safety requirements are met with respect to access to and
from the site. The extent of clearing required to achieve satisfactory sight lines varies between the
experts but in both cases if the appeal is allowed by the Court, it would be expected that the clearing
in the road reserve would be undertaken for the proposed access. The extent of clearing required
is detailed in the diagrams below for both traffic experts. Notably no vegetation was required to be
cleared in the road reserve for the approved 2 lot subdivision for the site.




               Figure 1: Appellant’s Traffic Engineer’s Assessment of Sight Lines & Required Clearing




                                                                                                        Page 10 of 16

Section 11

SPECIAL MEETING AGENDA                                                                             7 MARCH 2019




                Figure 2: Council’s Traffic Engineer’s Assessment of Sight Lines & Required Clearing

The difference in opinion between the expert traffic engineers on the required clearing for sight
lines varies due to a difference between the traffic experts about which sight distance standards
apply. The Appellant’s traffic engineer adopts the Australian Standards applicable for an access
driveway while still acknowledging that the sight distance for an intersection would be desirable.
Council’s traffic engineer identifies that Austroads applies, as he considers this to be the definitive
design standard for higher order roads such as David Low Way. Council’s traffic engineer also
considers that the existing driveway location is likely to achieve safer sight lines than that achieved
at the Appellant’s proposed location. Council’s traffic engineer also casts doubt upon the access
grading with respect to the pedestrian/cycle path located within the road reserve from a safety
perspective.
Notwithstanding the expert traffic engineer’s opinions on satisfactory sight lines, the vegetation in
the road reserve is reasonably intact native coastal vegetation and contributes significantly to the
vegetated character of David Low Way. The Noosa Plan seeks to protect this vegetation and
concern is raised about the extent of vegetation that may be lost if the Appellant’s appeal is
successful.
The Appellant has also recently (on 15 February 2019) advised that they would be willing to accept
a condition requiring vegetation offsets in the adjoining beach reserve, which they would maintain
for 3 years or if Council preferred a financial contribution calculated under the Queensland
Environmental Offsets Policy made.
Such a proposed offsetting arrangement is not consistent with The Noosa Plan or the draft planning
scheme for significant vegetation with the planning schemes instead both seeking to retain and
enhance vegetation. It is also clear that while the Appellant’s vegetation management and
offsetting plan is still being reviewed by Council’s expert ecologist, the plan is not desirable as the
area being cleared and the proposed offset area are 2 different ecosystems (and so the plan does
not achieve a like for like) and given the beach reserve is highly exposed, the proposed planting is
unlikely to be successful. The proposed offsetting arrangement would also require significant
ongoing maintenance by Council into the future.
The proposal therefore raises a number of matters which the Council is entitled to consider from
the viewpoint of its separate role as road authority (in respect to works in the David Low Way road
reserve) and trustee (in the case of the offset vegetation maintenance proposal in the adjacent
beach reserve).
These matters have been brought to Council’s attention as they do raise significant issues for
Council that will impact on the character of this part of David Low Way; the safety of David Low

                                                                                                       Page 11 of 16

Section 12

SPECIAL MEETING AGENDA                                                                7 MARCH 2019


Way being an important part of the major road network; and raise ongoing maintenance issues for
Council. The Appellant’s proposals in respect to vegetation removal in David Low Way, the
proposed access location and the proposed offset planting arrangement are not desirable and
have adverse impacts. It is therefore recommended that Council advise the Court and the
Appellant that Council will not accept them, in its capacity as road authority (in respect to works in
the David Low Way road reserve) and trustee (in the case of the offset vegetation maintenance
proposal in the adjacent beach reserve).
The recommendation is worded accordingly.

Previous Council Consideration

Ordinary Meeting, 18 January 2018, Item 3, Page 4
That Council note the report by the Development Planner to the General Committee Meeting dated
15 January 2018 regarding Application RAL17/0501 for a Development Permit for Reconfiguring a
Lot – (1 into 6 residential lots), situated at 2 David Low Way, Castaways Beach and:
A.    Refuse the application for the following reasons:
      1.    The proposed development is contrary to the Overall and Specific Outcomes of the
            Eastern Beaches Locality Code of the Noosa Plan. The development proposes
            significant clearing that is contrary to the Locality Code which requires protection of the
            vegetated character and views from the David Low Way and protection of native
            vegetation.
      2.    The proposed development is contrary to the Biodiversity code as it involves clearing
            of vegetation that is mapped as Environmental Protection and Riparian vegetation
            under the Noosa Plan.
      3.    The proposed development will result in unacceptable impacts on the visual amenity
            and character of the area.
      4.    The applicant has not demonstrated that a compliant, safe access is able to be
            provided to the site in accordance with required standards. To achieve a safe access
            significant clearing of vegetation and earthworks in the road reserve is also likely to be
            required.
      5.    The proposal is an overdevelopment of the site with the resultant development form
            detrimentally affecting the environmental and amenity values of the site.
      6.    The proposed development represents a poor planning outcome for the site, with the
            subdivision layout failing to provide street frontage for the lots and an excessive
            number of lots with access via an easement. The proposed access arrangements are
            likely to result in ongoing management and maintenance issues for future residents of
            these lots.
B.    Advise the utility service providers that there is significant vegetation within the road reserve
      adjacent 2 David Low Way, Castaways Beach that requires detailed assessment prior to
      installation of any services to minimise potential impacts on this vegetation.
C.    Note the report is provided in accordance with Section 63(5) of the Planning Act 2016.

Ordinary Meeting, 19 April 2018, Item 1, Page 4
That Council note the report by the Manager Development Assessment to the Planning &
Environment Committee Meeting dated 10 April 2018 regarding Planning & Environment Court
Appeal No. 456/2018 and agree to defend the appeal.




                                                                                       Page 12 of 16

Section 13

SPECIAL MEETING AGENDA                                                                   7 MARCH 2019


Finance & Risk
If the Appellant’s appeal is successful and Council does not take a position on the matters raised
in this report then it would not be appropriate for Council to later refuse to permit the clearing in the
road reserve, the proposed access and offsetting arrangement.
The cost of preparation for this appeal is $192,243 as at 31 December 2018, with the trial likely to
cost Council a further $120,000.

Consultation
External Consultation - Community & Stakeholder
Wakefield Sykes - Solicitor

Internal Consultation
Departments/Sections Consulted:

    Chief Executive Officer       Community Services                            Corporate Services
    Executive Officer             Director                                      Director
    Executive Support             Community Development                         Financial Services
                                  Community Facilities                          ICT
                                  Libraries & Galleries                         Procurement & Fleet
                                  Local Laws                                    Property
                                  Waste & Environmental Health                  Revenue Services

    Executive Services        x   Environment & Sustainable Development     x   Infrastructure Services
    Director                      Director                                      Director
    Community Engagement          Building & Plumbing Services                  Asset Management
    Customer Service          x   Development Assessment                        Buildings and Facilities
    Governance                    Economic Development                          Civil Operations
    People and Culture        x   Environmental Services                        Disaster Management
                                  Strategic Land Use Planning               x   Infrastructure Planning,
                                                                                Design and Delivery




                                                                                           Page 13 of 16

Section 14

SPECIAL MEETING AGENDA   7 MARCH 2019




                          Page 14 of 16

SPECIAL MEETING AGENDA                                                                            7 MARCH 2019

                                                                                                  ATTACHMENT 1
       ‘This plan has been prepared a5 3 proposed subdivision                                                   _
     | and should not be used for any offer purpose.
       The dimensions, areas and total number of lots shown                                                      >
       hereon are subject to Seid survey and are also to the                                                     a
     Sep              ee                                  XS                                 G,                 iD
       Therefore, no reilance should be placed on the  =                             co                           Cc
       Information on this pan for any financial deatings                       ~=N\           »                i
          otving the land.                                                                                       za
                                                                                Ae                   Cre        .
                                                    &,                         :                          =     is
         I                                         9                                       }                    ix
                                                   ~w                                                  "          Ww
                                                                  HF                                             ae
                                                 Q                             jtal Arca            ow            i
          N                                      Ss              ip           FFIEC ne                          Hi
                                                =          f                  Xs             2                 i; =
                                    .          a           is    hwy        Se \                                i
                                                 een!     YR   fe       ;         ~                              a
                                                  Propsaed                                                      zs:

                                         Newt pad.                         oe                 ie,       159
                                                                         /                            OP BIG NRT
                                     nm                  ue                        |
                                                         3                          ae       Cov K
                                                              c                              AOR |

                                                               hoe                                               wo
                                                       ny           RN                   Sam                    0
                                                         6
                                                  oo         t                              n                   5
    [| Covenant (Coastal)                          %                                716        a                zs
                                                      Oo                         Total Area
    [| Covenant (Road Buffer}                                  05)                 LEX mt                       x
                                                    New  Road    \                N
    [| Building Envelope                              Init      a             Sabet                             9
                                               %         Th    20s                                              °
    a--- New Road                                        g          \s\.<                                        nw
                                                                                                                >
            Easement Schedule                                                                                   rc
                                                        2 Road       :                                           Uv
       A          712       ‘Access/Services/Council      "           2                                         =
       B        711,713     Access/Services/Council                                                             >
       c      711,712,714   Access/Services/Council
       D      711-713,715  Access/Services/Council           =      oo)                                         =
       E      711-714.716  | Access/Services/Council         >        -
       F        711-715     Access/Services/Council          4
                                                                      :      %             Note:
           Statistics Table                                                        Building Envelopes reflect
                                                                                  minimum building setbacks
   ‘ares average [od                                                                  oe     es te
    Road            |S             Cd                                              Noosa Planning Scheme.
   [Park         CT      CN GS
   [Covenant—|           aia                                    Contour Note:
                                                        Contour Intervals are at 1.0m (minor) and 5.0m (major)
                 vio                 id                    Scale 1:750 = Lengths are m Metres.
                                     a
   at Eu                 ee        See, KenlynnPty Ltd                                             [rowne. sooees |
   SRVETOR Lee cos anew            SITE:  Proposed Lote 711-716 & & AF & CovHJIN SP CUENT:          SCALE  +:750 (a3)

                                                                                                    Page 14 of 16

Section 15

SPECIAL MEETING AGENDA   7 MARCH 2019




                          Page 15 of 16

SPECIAL MEETING AGENDA                                                                  7 MARCH 2019

       Tis plan has been prepared as 3 proposed subdivision                                          —
     1 and should not be used for any other purpose.
       The dimensions, areas and total number of lots shown
     @ hereon are subject to Seid survey and are also to the : 7 5 Soe   atte     7      ay           >
                 ee ee ee                           Ag       Le a rt ns        A          ms         RO
       Cartticate of Title for this stie has not bean obtained. Ce) aw. oe thy Pa     ,               w
      Sect eense, |                        AN          Pat         Ree                   Ma          |S
       Therefore, no rellance should be placed on the | ae     ok  Saas eo          ‘we ©            a
                                              ae |        or       ate        a ie ew :               <
          orving                                   4        -  wee    =    25       irs       Sirs   =
       The aerial photo undertay is destved from information ry A oy A tna ?o 4    ee ey SOR         7
     , supplied by Nearmap.com. It is approximate only. 2 > beg hp Bf a        SR =,       Xe i -    iz
                                           ‘ne           7,     eet      ey     a     i     he        “
    ——= New Road                           CL        gs caeme       tas         od Mag                35
                                     =       |         Eicon: areal ga 2           bea is             Se
                                      we.   /€          TE Total Area (iy                             §
                                      Pe    a      Tt hk Ne ee              ne    \        eee eS     zt
                                      mee   7A         5    oS he. Fee a ON a
                                    +x } Ma J       P|    "|      ah  “as, A     ¥  aX  ; = : Ry Finn He
                                    ar 3 = i       5 Be   PE 4 i    Ts       ie       ho pity         i
                                    hie        :      i   +    e   .        oe        AT    ya
                                    SY a en een      F pA         op oA ae          a      ae         i
                                    SS     gm      tS               A        ee     ar          ae
                                    i) ng _        |. 23 Ba   : =    2 — Sony : ‘   kf | MS Y, , <
                                    ce     |       f° $8  RS      P12               hf
                                      ce   ’     .   Bt ol a " ates Gime | f * ..  ie Pe        Ww)
                                     i A i      A       PE: > — mee      0 eal         bes er   «
                                     "           ey E>  ~~     en an my    ah       8     .      .
                                          3        Ie ati     tS            SL      a        158: |
                                   » poame       = a ie         ol      Ee
                                    i”         i          es —— "OF        613m? | Re     . ne
                                    Po           We Rag oe fe
                                          a         told      Total area
                                       .     1       —2oh       PCy    Rr                  -    ;
                                           ‘      , ‘eats wh  ba      Bo)         ef   "      * !
                                    ane           ie     Sp. 8 me Hide       oe  SE oeee              wn
                                       ape          Bet “a               565 m* fT Teams     ;
                                    1:              he   Syrea                  e          eC
                                                  Negi           775 SSS oa ah               eh:      Ow
                                         we        AAS       Ya             ee ee
                                    a               vi Eh                 7 bf Me                    0
                                    rm > 3) oe       i 7 % Soe              e otRn aS       K ia     <
                                    ie  a             Neer way Bee 7             bldg Eos
                                    pe                   ERE Sa bald  Ba 7 87   3aBimne       ary
                                    Ke      a>   ae          as   7  mes         eA   in             n
                                    Pee     ~~  ss         Wes     =                 ia     ae        oO
                                    Soo we      | AM    A ie 5          t                            z
                                    So                 a UR              eT                          v
               Note:                ee             oe      ae    NB             Be                   a
        Building Envelopes refiect    FR oe!       7 Pe                ae                             oO
       minimum building setbacks      Piss,    a         Se! ee
         as per schedule 1 of the   f ‘ ab        —  (EC ee is                 iota ey
        Noosa Planning Scheme.      Le       a       en         Nt     ie a       ia
                                                      Shy te                                         >
            Easement Schedule                    me               et ee              ;               rr
                                                   a.  ee      “ee The, ae       aN                   uv
       A         712      Access/Services/Council      { } as. e     mbH.     aes
       B        711,713   Access/Services/Council “y   tee      : oe et            a                 >
       o      711,712,714 | Access/Services/Council] [J Fi  7k        ne       5     >
       D      711-713,715 | Access/Services/Council ;    SU       Ph et     a                        =
       E      711-714,716 Access/Services/Council   nd   a     a\ pe       i eae
       F        711-715   Access/Services/Council    i.  Saree   )   >  BS ae
           Statistics Table                        We        r ‘ Ree .~
                                                      ;  ‘3       fe» SR my
    a a                                             rae |     eiaee           bs mY
   fArearange      | Sadar 336m |                 oo      fi  Fiz     ri    te ead
    [Areaaverage | 160im'                           ee"            hE      ee    WE
                                                © 5S         Dal at   Bae          ae
    [Park TN
    [Covenant            seam                             Contour Note:
                                                   Contour Intervais are at 1.0m (minor) and 5.0m (major)
                 no                                   Seale 1:780 = lengths are m Metres.
                 REVInION                                                Seen
                                 i/o
    poe sfc |i] gemma,                                                    [Kony Pty Lid
              os  se LEVEL DATUM: | SITE: Propoced Lots 711-716 6 & AF & Cov HIN & PV CUENT- SCALE 4-750 (A3)

                                                                                          Page 15 of 16

Section 16

SPECIAL MEETING AGENDA   7 MARCH 2019




                          Page 16 of 16

SPECIAL MEETING AGENDA                                                                         7 MARCH 2019

                                                                                                ,i TS  -  :
     oa           I                ve ar               ra       /  y          canis    aie           ;
      ns        Wf j                      mg         Sa   OPT oe              oi         ee         ae         e
            yy)        Of ys                |        ie                      ras  deo    eanyme aur amen | 3 Gp
                  0) OM      eS                Pa TD   as ee                  tn of Hikes emaeaitiataien ota  ||7
          9                 ee                                                  ee         ee                 lla
          *   f            tT      i   ro     /                                 ae   aes    a x    - =
        one)         A             ee Soe                                  [=~ Covenant Schedule =‘)
        een) i       b     pe ms        J     are              —_          ~ 2s         a                     4
    ——    ii          u FS    spf? /    fa wes FES ve Pe                     -   ey cnt  ah.    r    Manageme: 3
      3   oF oy Ex» eS a   et  hts (wr : ‘nak ~~ a a ue   ps    . >     :      me i |= st re A -  ster     al ; .
   a                  eae a      nes ot               a F cespgaeh               oo) ge      oe           ‘   ij
   Pee FS Oe                          1g             at            ee    |  al                 eee         ||
   Om face                   ae, Total Area fe                       Ee  |   ON   al oP   meee          mH     vj
        Df                           8087       ge OT                            SN       orators               e
          ¥   Hy  a                            vig Mot C    eae         ‘             a    a    ,  :
    Y   Bee Pee            "       ef    7  1     ME ot              aaa       ee Seka         aa         \
    Fe     ee pe         a                 Co   NE OS                  ey ee   es          Sioa                 z
    Q    |)     BRI       bo                  WONG               tS         ee              ee
     Je      Ae             ;       tie VA   ~ ye      he? pase 2      hess “3 . “F718 cf           ==
      3     [a ee            =      aes   P  ‘  -       a     a  -              .    ee  dee 2 ns —
     an egy     oot Bee       =~    ye       eT        ee     at    a   £ -|    Se pets 2714715 Lae      a
   : on oe                            OS    ck,          ee         i        aes 6   eee ie         ee cnn
    ®  ) n  5  \   y    cl,           }  me. -  hex  fe    i. ¢      4 SP         *    ‘  - Wis,   "
   = | “     y Faso        a                     | AES $9     rote : ee i    a ae Soy; me  - 2
      Y er      Co  Fr eb     Tata         7   baa      “el     hy Pn      *      ES, ra  er yt
        -:          r@                                  ia                    en    ak tag 4
       : ‘     .    ee,              be be Pi  a ee ot       ae    te    cies       + eo   ae       ’
   a     ‘    iC   Aby'                ee        fa         Bae!      > ie        a     Ts     sae
       4. Sah                    tt            TRY se                 RS       eee
       RS    BB cor ol apt cae m                     g    e  I pT ge oe                    a
                    i                   —           :   s    a       -          <A    Cs   :
         4     ;               AE a         —} 5        ae Chg                be                oe            w
     4            te        | Blog Er             i hs      teal" Yee              ME a                       ¢
       af      oS  ee              f              es nies 2 >                   “    : ie #',.                oO
     \  aS            ,                     yl     oe      .      5 .     2%       F 4s a     ae
                                                          eB           s&s            ae                      0
     1       OD rrp. | *c       .                 Pt     eure?        .  N         fi lr :                    =
    ' ' ,      —,       \                          ij  nee      eee    wa         pts oe      ste             <
        bi                                           Liao  Sieg ’        :           ;     ,
            een   te?           es              oe   Oe ae            ey         ae       Pore
   >                    >                          i       a         a                                        O
        1    a                Ni "7       f       ty    _      om ‘       A.   ee         aa
   -       New Road   5 2,  a    He        at    iat    tm",  aan 4        ree    ri      e   ing Envelopes   =
   ~       BO mB:      ; \   Ke pre     ve       "  3 ey a ees         oe      ae TS             .             uv
    a 4 =             is NS |             ee            ox      ae        >  fe                203            DD
   els ;  \   aA      +e M    8 al      + Moy                    = af          a re                é           oO
        “y      a     =    , Sage       >  —      .         Pree Oe <5) Be oe      4     PD
           ae         ww              "      “oi  4             _     a, a   ya ae       ee
                     Ne   N          fa.                 ee                  ‘                                U
           &           .  a          Pe     Gas,              el       -    i    &     -   y ae   :
             dm    ;   w               :         %  nim %    es     :  la y= oe yee ~      ote:                oO
        a               ware               a So pace                                                          ”
    *       ‘ \    L     ‘ i.       ry,  Pi oN   Bo   |         w aa     Sols        gar ee       ie          >
       Nee        ah Ge      ce A     Date            Segal           9             i eter
        rt      i            7           -   ce     .            _"    yo      a        or Say   7
   2s Se 27                           Pe  oh                                a)        «Contour Not
    na         vA) aw.                ke     ee        Op a       ei A) Se pea        oe     ee eal           -
   ,     AS?        , \l   es bas:                      Oe         4 oe     bE
           a        7, ts   ie     Paw        '       ro      WD oss ee oI           a       =,     3
           ri           =                ae       ene      raaN        les          Btatictice 7 ‘able
     :          0            ie      ptt,            we a eee |                ee            eS     __|
     ee          hy    yin    Or Vee ae     ae  3       yn      a ea   a        i          | WUC: fps 3897 m* |
     eS                   ar a               es                 26) [weravesee
   Rigs           ||        RBM   CENOE              a  ge a ag
   Fee              |    I              ee   a       aS                   Pe           eg Oe
   ie    ae        |, i  é   ie       er ts   nf         ae Fis ted    i     fal Site Ay rd aT * Fim      |
   Aerial map sourced from Nearldap
                                     Seale 1:750 = Lengths are In Metres.
                     eae ene               eee eee Ree ee                     LF
                    10     o    0    2    2    4     450  6    7     8    9    WO   10
                      LEVEL DATUM: 2iTe-Propoced Lots 711-716 8 E a         CUENT:                SCALE  1:750(A3)
  fos ee                         ceremeeee, | Kenymn Pty Ltd                                      [ane ‘set

                                                                                                 Page 16 of 16

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.