Planning Report - 13 Eumundi-Noosa Road, Noosaville QLD 4566 - Dual Occupany
Performance outcomes Acceptable outcomes Response
Council's Building and Plumbing Services for 2. telephone lines are disconnected;
decommissioning plumbing apparatus including: and
1. sanitary drains or reticulated water 3. data cables are disconnected and
supply; and removed.
2. septic tanks, holding tanks or on-
AO7.3 Complies with AO7.3
site treatment systems.
A temporary crossing is provided to protect road
The proposed development will ensure a
reserve infrastructure including kerb and channel.
temporary crossing will be provided if required.
AO7.4 Complies with AO7.4
Any damage to footpaths, street plantings,
The proposed development will ensure that any
natural vegetation, kerb and channel, bridges or
damage will be minimised and repaired or
roadways at the removal site, the new site or
reinstated to at least pre-existing conditions.
between the sites is repaired or reinstated to at
least pre-existing conditions.
PO8 AO8.1 Complies with AO8.1
Waste materials are removed from the site to Waste materials are removed from the site.
The proposed development will ensure that waste
avoid causing unhealthy conditions including:
materials are removed from the site.
1. potential fire hazard;
AO8.2 Not applicable
2. ponding of water; and
If a development permit has not been issued for
The proposed development is for residential uses.
3. breeding of vermin. the future use of the site:
1. hard surfaced areas including
concrete slabs are removed or
covered with a minimum of 300
millimetres of soil; and
2. disturbed areas are revegetated.
Development Application: 13 Eumundi-Noosa Road, Noosaville Noosa Plan 2020: Amendment 1 Effective date: 25/09/2020