Planning Report - 13 Eumundi-Noosa Road, Noosaville QLD 4566 - Dual Occupany

of 145

Page text read automatically using OCR, there may be inaccuracies

 Performance outcomes                                        Acceptable outcomes                                    Response
 are reinstated and revegetated upon completion
                                                AO5.2                                               Not applicable
 of works.
                                                Stormwater drainage infrastructure is co-located
                                                                                                    The proposed development’s stormwater
                                                with other infrastructure within a combined utility
                                                                                                    drainage infrastructure does not require being co-
                                                corridor where appropriate.
                                                                                                    located with other infrastructure.

                                                             AO5.3                                             Not applicable
                                                             Temporary vehicular crossings of waterways must
                                                                                                               The proposed development does not require a
                                                             be designed and constructed to be consistent with
                                                                                                               temporary vehicular crossing of a waterway.
                                                             the current International Erosion Control
                                                             Association Best Practice Book Series.

 Stormwater quality and protection of receiving waters

 PO6                                                         AO6.1                                                  Not applicable
 Development is located, designed, constructed
                                                             Stormwater runoff discharging into High Ecological The proposed development’s stormwater runoff
 and operated to protect and enhance
                                                             Value waters as a result of development causes no will not discharge into High Ecological Value
 environmental values and water quality of
                                                             increase in gross pollutants, total suspended solids, waters.
 waterways, wetlands, lakes, ground waters and
                                                             total phosphorous or total nitrogen compared to a
 drainage systems.
                                                             pre-development scenario.

                                                             AO6.2                                                  Complies with AO6.2 & AO6.3
                                                             All stormwater runoff is treated to achieve
                                                                                                                    The proposed development’s stormwater runoff
 Editor’s note: Environmental values of waters and           maximum removal of nutrients, gross pollutants
                                                                                                                    will be treated to comply with required standards
 water quality objectives are prescribed in Schedule         and suspended solids as determined by cost to
                                                                                                                    where applicable.
 1 of the Environmental Protection (Water) Policy            efficiency ratios. (e.g. bioretention basins must be
 2009 and are identified on the State Planning               sized to achieve at least 80% reduction in total
 Policy Interactive Mapping System.                          suspended solids, 60% reduction in total
                                                             phosphorous, 45% reduction in total nitrogen and
                                                             90% reduction in gross pollutants >5mm).




Development Application: 13 Eumundi Noosa Road, Noosaville               Noosa Plan 2020: Amendment 1                                          Effective date: 25/09/2020

Log in to download the original (Planning Report - 13 Eumundi-Noosa Road, Noosaville QLD 4566 - Dual Occupany.pdf)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.