Original source · versioned page text
Planning Report - 13 Eumundi-Noosa Road, Noosaville QLD 4566 - Dual Occupany
Performance outcomes Acceptable outcomes Response
PO10 AO10 Complies with AO10
Development prevents increased bed and bank The development is designed to: The proposed development will provide suitable
erosion and sedimentation in receiving waterways measures to prevent bed and bank erosion.
1. limit the peak 1 year ARI event
by avoiding changes in low rate, peak flow run-off
discharge within the
and flow duration.
receiving waterway to the pre-
development peak 1 year discharge;
2. maximise pervious areas by using
pervious alternatives for otherwise
impervious areas wherever possible;
3. provide for capture and reuse of
stormwater for non-potable purposes
for gardening, toilet flushing, laundry
and hot water supply uses;
4. incorporate appropriate detention
features; and
5. incorporate natural channel design
principles
Editor’s note: The Sustainable Building Design
Code includes requirements for stormwater capture
and reuse.
PO11 AO11.1 Not applicable
Water sensitive urban design principles are The design and construction of a natural channel or The proposed development does not involve the
applied to achieve multifunctional design of natural channel rehabilitation works are in design and construction of a natural channel or
accordance with the Natural Channel Design natural channel rehabilitation works.
Development Application: 13 Eumundi Noosa Road, Noosaville Noosa Plan 2020: Amendment 1 Effective date: 25/09/2020
Preview the original
The page text is free to read. Previews and downloads of original files need an account.
Log in to previewSearchable page text hides email addresses. Original files are unchanged and may show email addresses.