Request for Further Information - 010.2007.00002104.001 [As Published] · 142007.2104

of 3

Text shows just the words. Original shows the document exactly as it was published.

        1.6. the current location of street trees away from the road will not provide
             shading to the street. Accordingly, street trees are to be located closer the
             road however setback a minimum of 1 metre from the kerb and channel.

2.      Payment of $12,500 bond in accordance with Condition 16 of MCU approval
        (05/2302).

3.      Payment of Public Open Space, Pathway and Headworks Contributions in
        accordance with Conditions 28, 31 and 45 of MCU approval (05/2302).

4.      Provide evidence of payment of Portable Long Service Leave Levy in accodance
        with Advice Condition 5 of MCU approval (05/2302) where the cost of works
        exceeds $80,000 or alternatively provide a statutory declaration confirming the
        cost of works.

Land Development

5.      Demonstrate how the development meets the following Conditions of the MCU
        approval (05/2302):-

        5.1. Condition No. 20 – requires the driveway to be a maximum width of 4.5
             metres across the Ventura Street road reserve. Please amend all drawings
             to reflect this.

        5.2. Condition No. 33 – Please provide a survey plan indicating the location and
             levels of Council’s sewer line and stormwater drainage lines.

        5.3. Condition No. 34 – Without the survey plan as required by Condition 33, it
             would appear that this condition cannot be complied with. Council suspects
             that the proposed stormwater outlet pipe may clash with Council’s existing
             sewer line.

        5.4. Condition No. 40 - Modifications will be needed for the sewer manhole in
             the proposed driveway, please supply the details of these modifications.

        5.5. Condition No. 48 – Geotechnical Engineers report is require, demonstrating
             if the site is suitable for excavation works to be carried out without damage
             to the adjoining properties and structures on those properties. The report
             shall also address the means of support for embankments during the
             construction of this development.
Please provide four (4) copies of all information that you are providing. In addition, it
would assist Council if you could also provide an electronic copy of your response.
Pursuant to the conditions of the Development Permit for a Material Change of Use
please note that all bonds and contributions are required to be paid prior to the issue of
the Operational Works approval.

Please be aware that under Section 3.2.12 of the Integrated Planning Act, the applicant
is to respond to any information request within 12 months of the request or otherwise,
the application lapses.
Under the provisions of the Integrated Planning Act 1997, you as the applicant, have
three options available in response to this Information Request. You may give the
assessment manager (in this instance Council) and each referral agency (if any):-


     Award Winner - Australian Clean Beach
       Challenge 2004 Litter Prevention

Used in these records

About this file

File size
11 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Request for Further Information - 010.2007.00002104.001 [As Published].pdf · 11 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.