25364-001-Rev0 Duke St · 51901.3953.02
20 November 2025 Ref.: 25364-001-Rev0
SCG Consulting Engineers
Attention: Benjamin Hopkins
[email protected]
RE: SLOPE STABILITY ASSESSMENT FOR PROPOSED EXTENSIONS
2/29 DUKE STREET, SUNSHINE BEACH
Dear Benjamin,
1. INTRODUCTION
As requested, Tectonic has undertaken a slope stability assessment for the proposed extension at
2/29 Duke Street, Sunshine Beach. This report presents the results of our slope stability assessment,
together with geotechnical advice for the project. In summary, subject to the implementation of the
recommendations made herein, it is assessed that there should be a Low Risk of slope instability
affecting the proposed development in accordance with the Australian Geomechanics Society Guidelines
for Landslide Risk Management, dated March 2007 (AGS 2007). This level of risk is normally acceptable to
regulators (i.e. Noosa Council [NC]).
1.1 Details of the Site and Development
The subject site is the middle property of an existing three-unit townhouse development, which is
formally described as BUP5098. The total overall site covers an area of about 840 m2 and is situated on
the western corner of the intersection of Duke Street and Ferguson Street. Text Figure 1 below indicates
the site and immediate surrounds. A detailed site description is given in Section 2.
Overall site
2/29 Duke Street
Text Figure 1: Recent aerial image of the site and surrounds (courtesy of NC Intramaps)
Tectonic Geotechnical Pty Ltd
A.B.N. 83 165 727 828
PO Box 899, Buderim, QLD 4556 E [email protected]
P (07) 5478 9016
W tectonicgeo.com.au 1 of 12
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalFull text of the other 16 pages
Page 2
Town planning application drawings were supplied to Tectonic (Ref. Matthew Noffke Architects [MNA],
Project No. J25005, Drawings Nos. CP00 to CP09 [inclusive], Rev. A.3, dated May 2025). The drawings
indicate that the proposed development is to comprise the construction of a two-storey extension, off
the western side of the central townhouse (see Text Figure 2 below). The extension will be structurally
connected to the existing townhouse and supported via new posts to the west. No earthworks are
proposed as part of the development.
Proposed extension
Text Figure 2: Proposed site layout plan, section view and 3D schematic (courtesy of MNA)
20 November 2025
25364-001-Rev0 2 of 12
Page 3
1.2 Method and Scope of Investigation
As part of our slope stability assessment, a desk-top study was carried out comprising a review of
published geological maps, NC overlays, and a ‘soil test’ report prepared by Australian Soil Investigations
(ASI, Ref. Report No. 250539(S), dated 17 November 2025).
A walk-over survey was conducted in order to make an appraisal of the general condition of the site in
regard to topography, drainage, vegetation cover, geology, erosion, and condition of existing structures.
The walk-over survey was carried out by an experienced engineering geologist from Tectonic on
11 November 2025.
The results of the desk-top study and walk-over survey are included in Section 2 below.
1.3 Qualifications of Responsible Engineer
This report has been reviewed by Ashley Davey, an RPEQ with more than 30 years’ experience in
geotechnical engineering, including numerous slope stability projects.
2. DESCRIPTION OF EXISTING CONDITIONS
2.1 Geology and Subsurface Conditions
Available geological information 1 indicates that the site is underlain by Pleistocene age blowout sand
dunes comprising “quartz sand” (Ref. Text Figure 3).
Approx. Site Location
Text Figure 3: Extract from Laguna Bay Surface Geology map
The ASI investigation comprised one borehole (designated as BH1) drilled using hand augering
equipment, and three dynamic cone penetrometer (DCP) tests within the proposed extension footprint.
Subsurface conditions were reported to comprise very loose to loose, silty sand fill to a depth of about
0.3 m below ground level (BGL), then very loose to loose natural sands to depths of between about 1.5 m
and 1.7 m BGL, becoming medium dense to between about 3.3 m and 4 m BGL, with underlying dense
sands extending to the DCP termination depths of 4.5 m BGL.
Groundwater was not mentioned in the ASI borehole report, with the soils described as ‘moist’. ASI
classified the site as Class P due to poor bearing capacity, however, went on to state that ‘with respect to
potential surface movements through seasonal moisture variations, the site could be considered equivalent
to a Class S site’.
1
1:100,000 Laguna Bay Surface Geology, Sheet 9545, Compilation Map, DNRME, 2018
20 November 2025
25364-001-Rev0 3 of 12
Page 4
2.2 Topography
During the site walk-over, topographic features were noted, and ground slopes were recorded using a
hand-held clinometer. As illustrated in Text Figure 4, the site is located on the easterly facing flank of an
ancient sand dune, which crests about 30 m beyond the western boundary of the site.
The natural slope through the site ranged from up to 15° in the western corner, decreasing to <5° in the
eastern half of the site. The site had been altered by previous cut and fill earthworks during construction
of the existing townhouses. Based on a visual appraisal it appeared that cut and fill earthworks of up to
about 3 m deep and 0.5 m high, respectively, had been undertaken. The major site cut was supported by
a 3 m high internal retaining wall, which helped form the partial basement level of the existing structure.
Additionally, a grouted rock wall up to about 1.2 m height was present to the west of the townhouses,
which retained the upslope cut to the west and formed level lawn/patio areas. The area of the proposed
extension was generally flat.
No obvious signs of irregular features which would indicate global instability were observed across the
allotment.
Subject site
Text Figure 4: Ground surface contours (courtesy of NC interactive mapping)
Site conditions observed at the time of our investigation are shown in Text Figures 5 to 7.
20 November 2025
25364-001-Rev0 4 of 12
Page 5
Text Figure 5: Easterly view of the proposed extension area
Text Figure 6: Southerly view of the proposed extension area
Text Figure 7: Westerly view of site from Duke Street (LHS) and Freguson Street (RHS)
20 November 2025
25364-001-Rev0 5 of 12
Page 6
2.3 Groundwater
No signs of groundwater seepage at the surface (‘springs’) were observed during our walk-over, nor was
groundwater mentioned in the ASI borehole report.
2.4 Surface Drainage
Surface drainage would be expected to follow the ground surface gradients to the east. However, run-
off would be minimal due to the expected sandy nature of the soils as rainfall would normally be
anticipated to infiltrate the ground surface. Nevertheless, as the development will occupy a large part of
the block, significant run-off from hard surfaces will occur. Where directed into swales rather than pipes,
such run-off would be expected to infiltrate into the natural sands relatively rapidly.
2.5 Vegetation
The ground surface across the proposed extension area comprised maintained grass. Some medium
sized trees were present in the western area of the site and were observed as relatively ‘plumb’ which
suggests fairly stable ground.
2.6 Buildings and Other Structures
The existing townhouse comprised a three-level structure, which included a partial basement. Existing
foundation details were not available at the time of writing. A grouted rock retaining wall, which ranged
in height from 0.5 m to 1.2 m, was located to the west of the townhouse units.
As shown in Text Figure 8 below, singular examples of minor cracking were observed in both the
townhouse and the grouted rock wall. The structures were otherwise is fair condition and did not show
any obvious signs of significant distress which could be attributed to global slope instability.
Cracking
Text Figure 8: Hairline cracking in render of townhouse (LHS) and cracking in grouted rock wall (RHS)
20 November 2025
25364-001-Rev0 6 of 12
Page 7
3. ASSESSMENT OF LAND STABILITY
3.1 Existing Conditions
The NC Planning Scheme 2020 includes a landslide hazard overlay map (Ref. extract in Text Figure 9),
which indicates that the site is mapped as having a High landslide hazard.
Subject site
Text Figure 9: Extract from NC landslide hazard overlay mapping
It should be noted that the NC landslide hazard map is a broad-scale indication of the potential landslide
susceptibility and is superseded by this site-specific assessment. No visual signs of global slope
instability were observed across the allotment. No landslide back scarps, groundwater springs, or areas
of naturally ‘hummocky’ ground were observed.
3.2 Stability Assessment
The risk assessment for this project has been carried out following AGS 2007 Practice Note Guidelines for
Landslide Risk Management. Relative levels of risk and their implications are given in Table 1 and the
Qualitative Terminology for Use in Assessing Risk to Property is also attached.
Table 1: Stability Risk Levels
Risk Level Example Implications (1)
VH Very High Unacceptable without treatment. Extensive detailed investigation and research, planning and implementation
Risk of treatment options essential to reduce risk to Low; may be too expensive and not practical. Work likely to
cost more than value of property.
H High Risk Unacceptable without treatment. Detailed investigation, planning and implementation of treatment options
required to reduce risk to Low. Work would cost a substantial sum in relation to the value of the property.
M Moderate May be tolerated in certain circumstances (subject to regulators’ approval) but requires investigation,
Risk planning and implementation of treatment options to reduce risk to Low. Treatment options to reduce to
Low risk should be implemented as soon as practicable.
L Low Risk Usually acceptable to regulators. Where treatment has been required to reduce the risk to this level, ongoing
maintenance required.
VL Very Low Acceptable. Manage by normal slope maintenance procedures.
Risk
Note: (1) The implications for a particular situation are to be determined by all parties to the risk assessment and may depend
on the nature of the property at risk; these are only given as a general guide.
20 November 2025
25364-001-Rev0 7 of 12
Page 8
Given the geology and topography of this site, it is unlikely that a landslide could affect the proposed
development area. Sand dune slopes are generally close to the ‘limit of equilibrium’ for slope stability
where the surface gradient is about 30° (58%), although often lower (26˚ to 28˚) for very loose sands.
Our measurements indicate that natural gradients ranged up to about 15° at the western extent of the
site, but were <5° through the proposed extension footprint. The limit of equilibrium is the ‘tipping point’
to instability, where the factor of safety (FOS) of the slope is approximately 1.0. The FOS of a slope is the
balance (ratio) between the forces driving instability (e.g. soil weight, groundwater pressure) and the
resisting forces (e.g. soil friction and cohesion).
Sand dune slopes generally remain stable (i.e. FOS greater than 1.0) when they are:
well vegetated (mix of ground cover, shrubs and small trees);
not subjected to concentrated stormwater flows;
not surcharged with additional loads (e.g. fill);
not undercut by excavation or erosion; and
have slope angles less than 26˚.
Direct discharge of stormwater onto dune slopes may cause channel erosion, undermining and
disturbance of vegetation, and development of generally localised instability.
Considering the existing site conditions (Ref. Section 2), and subject to the implementation of
recommendations given below, it is assessed that there should be a Low Risk of global slope instability
affecting the proposed development. Regulators (NC) normally require that a Very Low or Low Risk of
landslide affecting the property must be demonstrated to enable development approval. Summarised in
Table 2 is our qualitative assessment of landslide risk for the development site. A summary of qualitative
terminology for use in assessing risk to property is attached (taken from AGS 2007).
It should be noted that this risk assessment excludes geotechnical risk that may be associated with
settlement due to consolidation of loose sands over time which could affect non-piled structures
(e.g. pavements, landscaping structures).
Table 2: Details of Qualitative Risk Assessment for Property (AGS 2007)
Hazard Likelihood Consequence Assessed Risk Comments
1. Failure Given the gentle to moderate natural gradients through
through very the proposed building area and adjacent ground, it is
loose to loose considered Unlikely that a landslide would develop in
natural sands Unlikely Medium Low these materials, subject to implementation of the
above the recommendations in Section 4. For a potential Medium
foundation impact from such instability the resultant risk would be
depth Low as per AGS 2007.
2. Deep failure The likelihood of a deep failure through the medium
through the dense (or denser) natural sand below the proposed
medium dense foundation depth is assessed as Rare due to the lack of
(or denser) precedence of such movements locally, no signs of
Rare Major Low
sands below existing deep-seated instability and apparent lack of
the foundation groundwater. Although the consequence of such a
depth failure could be Major, the resultant risk is Low as per
AGS 2007.
The potential impacts on slope stability of the development components have been assessed, and the
measures recommended below in Section 4 have been designed to mitigate those impacts.
20 November 2025
25364-001-Rev0 8 of 12
Page 9
4. RECOMMENDATIONS
General recommendations to help maintain the stability of the site are given in the document Some
Guidelines for Hillside Construction, which is attached.
4.1 Site Layout and Development Limitations
Should any revisions be made to the proposed extent of the development, as described in Section 1.1,
Tectonic must review these revisions prior to construction to assess if there are any impacts on slope
stability.
To achieve a Low Risk of instability, the following is recommended:
The proposed development should not exert additional load on the existing structures or footing
system, unless assessed and approved by a structural RPEQ, who must also confirm the existing
footings and structural members have sufficient capacity to carry any additional loads imposed by
the extensions.
All footings must found below the zone of influence of the existing structures (including retaining
walls).
Design and construction of footings shall be undertaken in accordance with Section 4.3.
All retaining walls exceeding 1 m high and/or subject to surcharge loads must be engineer designed
and certified by an RPEQ. The design must include an assessment of global and internal stability.
Formal drainage should be constructed to ensure all stormwater is directed away from the existing
and proposed structures.
4.2 Earthworks
It is anticipated that substantial earthworks will not be required for the construction of the extensions.
Localised excavations may be required for footings and service trenches. Additional fill must not be
placed on the site during construction unless assessed and approved by Tectonic prior to
commencement.
Any organic rich topsoil must be stripped from construction areas.
Excavations in the soils encountered in the ASI borehole should be achievable using conventional
earthmoving equipment (e.g. excavators with toothed buckets or augers).
Any excavations required adjacent to existing structures will need to be specifically designed to ensure
that the structures are not undermined. This may necessitate the use of shoring and/or underpinning,
which must be designed and certified by a structural RPEQ.
The above recommendations do not supersede any existing safety regulations or legislation applicable to
excavations (e.g. limits on personnel entry into trenches).
4.3 Footing Design
A suitably qualified and experienced structural RPEQ must be consulted to ensure the existing footings
and structural elements of the residence have sufficient capacity to support any additional loads imposed
by the proposed extensions. It is recommended that footing exposures and/or building records searches
be undertaken prior to construction. Alternatively, the proposed extensions could be designed to be
structurally isolated from the existing structures.
20 November 2025
25364-001-Rev0 9 of 12
Page 10
No design loadings were available at the time of reporting. Footings for the proposed extensions must
penetrate through any fill materials and unsuitable natural soils (i.e. very loose to loose sands) to found
at least 0.5 m into medium dense (or denser) sands. Based on the current borehole & DCP information,
footing depths in the order of about 2 m to 2.5 m BGL (below the existing ground levels) are expected.
Based on the proposed development plans, negligible earthworks will be required, and as such footings
will therefore need to be piled.
Given the site access constraints, screw piles using a mini rig could be a suitable option. Piles founded at
least 0.5 m into the medium dense (or denser) sands may be designed using an allowable end bearing
pressure (ABP) of 300 kPa. Footing design should also account for potential soil reactivity.
Due to the likely presence of loose sands, together with the close proximity to surrounding infrastructure,
open bored piers or driven piles are not considered to be appropriate for this site. Steel reinforced
concrete bored piles could be feasible; however, the use of sacrificial liners (e.g. ‘formatube’) would be
required to prevent the caving of upper loose sands.
The advice of a specialist piling contractor must be sought regarding feasibility, design and installation of
the piling system for this site, including an assessment of potential vibration effects on nearby structures,
and monitoring requirements.
If steel screw piles are adopted, it will be important to ensure close supervision of installation, as piling
may not encounter sufficient drilling resistance (from torque measurement) in sands at the suggested
founding depth and piles could extend to much greater depth than necessary.
It is therefore recommended that site-specific load testing be conducted on screw piles, if adopted, at a
minimum. Where tension or compression capacity developed in the footings is critical for the future
structure (e.g. resistance to uplift forces from high winds), then cyclic load tests (including measurement
of deflections under tension and compression cycles) should also be undertaken prior to construction.
Kentledge for static testing, or simulated cyclic loads, should prove the piles to a minimum of two times
the expected working load within tolerable deflections.
All footings should found such that they are not adversely affected by (or affect) any adjacent
excavations, trenches or retaining walls that are not designed to support building loads. Footings should
found at least below a plane extending 1 m horizontally from the base of trenches/excavations/retaining
walls, then rising up at 1V:1H, as illustrated in Text Figure 10.
Where footings are located within a horizontal distance of 1.5H (H being the batter height) of any cut or
fill batter crest, these footings must be founded at a depth level with the toe of the batter.
Text Figure 10: Zone of influence diagrams – footings to be founded below these lines
If bored piles are adopted, it is recommended that footings be inspected by an RPEQ prior to placement
of steel reinforcement and pouring of concrete to confirm allowable bearing pressures and cleanliness of
excavations.
20 November 2025
25364-001-Rev0 10 of 12
Page 11
If any soil conditions encountered during construction are found to differ from those discussed in this
report, ASI and Tectonic should be notified immediately, and an inspection carried out to determine if
changes to footing design are required.
4.4 Retaining Structures
Retaining structures must be founded as per the recommendations in Section 4.3 above. Retaining
structures greater than 1 m high, or those required to support surcharge loads or sloping backfill, will
require engineer design and certification of construction. Retaining wall design should be carried out in
accordance with AS4678-2002 Earth retaining structures.
The parameters outlined in Table 3 may be adopted for retaining wall design. The values in Table 3
assume that the walls are fully drained, and no allowance is included for hydrostatic pressures,
construction loading, up-slope footing loadings, the effects of sloping ground and backfill compaction
stresses. Any temporary shoring required to support excavations during construction may also be
designed using the parameters in Table 3.
Table 3: Retaining Structure Design Parameters
Lateral earth pressure coefficients
Unit weight Friction angle Ø Ka Ko Kp
Retained material
(kN/m3) (°) (Cantilever wall) (Non-yielding
wall)
Loose Sands 17 28 0.36 0.53 2.77
Medium Dense (or 18 33 0.29 0.46 3.39
Denser) Sands
Future Fill * * * * *
Note: * depends on fill material type and level of compaction
At a minimum, retaining structures must be founded as per the recommendations in Section 4.3 above
with the footings also designed to account for lateral loads imposed by the retaining wall. Detailed
design must include an assessment of internal and global stability, together with required bearing
capacity and founding depth, by the retaining wall design engineer.
4.5 Drainage
Given the sandy nature of the site, rainfall is generally expected to rapidly infiltrate any unsealed surfaces.
If necessary, diversion drainage should be constructed to divert seepage and/or runoff away from the
building area to prevent saturation and erosion.
Permanent site drainage must be installed to ensure that stormwater runoff is directed away from
proposed building walls, footings and retaining walls (e.g. positive gradients and/or channel drains).
Future building and landscaping must be carried out to maintain good drainage.
Subsurface drainage must be installed behind any retaining walls (e.g. slotted ‘aggi’ pipe wrapped in
filter ‘sock’ placed in gravel backfill). Depending on matters such as the extent of drainage installed and
site-specific groundwater conditions, the designer must make an assessment of hydrostatic pressure to
be accounted for in the design of the retaining structure.
20 November 2025
25364-001-Rev0 11 of 12
Page 12
All excess stormwater collected around the building (including overflow from rainwater tanks, etc.) must be directed by pipes or lined channels into the existing drainage system, which presumably directs waters to the street. 5. CONCLUSION It is assessed that there would be a Low Risk to the proposed extension from slope instability subject to implementation of the recommendations given in this report. 6. LIMITATIONS This assessment relates only to the proposed works described within Section 1.1. Your attention is drawn to the document Limitations, which is attached to this letter report. Please contact the undersigned should you wish to discuss any of the above matters. Yours faithfully, Tectonic Geotechnical Pty Ltd Oliver De Silva BAppSc PMEG Ashley Davey BEng (Geological) RPEQ 8159 Engineering Geologist Director/Principal Geotechnical Engineer Attachments: A. Qualitative Terminology for Use in Assessing Risk to Property B. Some Guidelines for Hillside Construction C. Limitations 20 November 2025 25364-001-Rev0 12 of 12
Page 13
PRACTICE NOTE GUIDELINES FOR LANDSLIDE RISK MANAGEMENT 2007
APPENDIX C: LANDSLIDE RISK ASSESSMENT
QUALITATIVE TERMINOLOGY FOR USE IN ASSESSING RISK TO PROPERTY
QUALITATIVE MEASURES OF LIKELIHOOD
Approximate Annual Probability
Implied Indicative Landslide
Description Descriptor Level
Indicative Notional Recurrence Interval
Value Boundary
10-1 5x10-2
10 years The event is expected to occur over the design life. ALMOST CERTAIN A
20 years The event will probably occur under adverse conditions over the
-2
10 100 years
design life.
LIKELY B
-3
-3 5x10 200 years
10 1000 years The event could occur under adverse conditions over the design life. POSSIBLE C
5x10-4 2000 years
The event might occur under very adverse circumstances over the
10-4 10,000 years
design life.
UNLIKELY D
-5 5x10-5 20,000 years
10 The event is conceivable but only under exceptional circumstances
100,000 years RARE E
over the design life.
-6 5x10-6 200,000 years
10 1,000,000 years The event is inconceivable or fanciful over the design life. BARELY CREDIBLE F
Note: (1) The table should be used from left to right; use Approximate Annual Probability or Description to assign Descriptor, not vice versa.
QUALITATIVE MEASURES OF CONSEQUENCES TO PROPERTY
Approximate Cost of Damage
Description Descriptor Level
Indicative Notional
Value Boundary
Structure(s) completely destroyed and/or large scale damage requiring major engineering works for
200% CATASTROPHIC 1
stabilisation. Could cause at least one adjacent property major consequence damage.
100%
Extensive damage to most of structure, and/or extending beyond site boundaries requiring significant
60% MAJOR 2
stabilisation works. Could cause at least one adjacent property medium consequence damage.
40%
Moderate damage to some of structure, and/or significant part of site requiring large stabilisation works.
20% MEDIUM 3
Could cause at least one adjacent property minor consequence damage.
10%
5% 1% Limited damage to part of structure, and/or part of site requiring some reinstatement stabilisation works. MINOR 4
Little damage. (Note for high probability event (Almost Certain), this category may be subdivided at a
0.5% INSIGNIFICANT 5
notional boundary of 0.1%. See Risk Matrix.)
Notes: (2) The Approximate Cost of Damage is expressed as a percentage of market value, being the cost of the improved value of the unaffected property which includes the land plus the
unaffected structures.
(3) The Approximate Cost is to be an estimate of the direct cost of the damage, such as the cost of reinstatement of the damaged portion of the property (land plus structures), stabilisation
works required to render the site to tolerable risk level for the landslide which has occurred and professional design fees, and consequential costs such as legal fees, temporary
accommodation. It does not include additional stabilisation works to address other landslides which may affect the property.
(4) The table should be used from left to right; use Approximate Cost of Damage or Description to assign Descriptor, not vice versa
Australian Geomechanics Vol 42 No 1 March 2007
68039 Landslide Risk Management Issued 10/7/07
Page 14
PRACTICE NOTE GUIDELINES FOR LANDSLIDE RISK MANAGEMENT 2007
APPENDIX C: – QUALITATIVE TERMINOLOGY FOR USE IN ASSESSING RISK TO PROPERTY (CONTINUED)
QUALITATIVE RISK ANALYSIS MATRIX – LEVEL OF RISK TO PROPERTY
LIKELIHOOD CONSEQUENCES TO PROPERTY (With Indicative Approximate Cost of Damage)
Indicative Value of 1: CATASTROPHIC 2: MAJOR 3: MEDIUM 4: MINOR 5:
Approximate Annual 200% 60% 20% 5% INSIGNIFICANT
Probability 0.5%
A – ALMOST CERTAIN 10-1 VH VH VH H M or L (5)
-2
B - LIKELY 10 VH VH H M L
C - POSSIBLE 10-3 VH H M M VL
D - UNLIKELY 10-4 H M L L VL
-5
E - RARE 10 M L L VL VL
-6
F - BARELY CREDIBLE 10 L VL VL VL VL
Notes: (5) For Cell A5, may be subdivided such that a consequence of less than 0.1% is Low Risk.
(6) When considering a risk assessment it must be clearly stated whether it is for existing conditions or with risk control measures which may not be implemented at the current
time.
RISK LEVEL IMPLICATIONS
Risk Level Example Implications (7)
Unacceptable without treatment. Extensive detailed investigation and research, planning and implementation of treatment
VH VERY HIGH RISK options essential to reduce risk to Low; may be too expensive and not practical. Work likely to cost more than value of the
property.
Unacceptable without treatment. Detailed investigation, planning and implementation of treatment options required to reduce
H HIGH RISK
risk to Low. Work would cost a substantial sum in relation to the value of the property.
May be tolerated in certain circumstances (subject to regulator’s approval) but requires investigation, planning and
M MODERATE RISK implementation of treatment options to reduce the risk to Low. Treatment options to reduce to Low risk should be
implemented as soon as practicable.
Usually acceptable to regulators. Where treatment has been required to reduce the risk to this level, ongoing maintenance is
L LOW RISK
required.
Acceptable. Manage by normal slope maintenance procedures.
VL VERY LOW RISK
Note: (7) The implications for a particular situation are to be determined by all parties to the risk assessment and may depend on the nature of the property at risk; these are only
given as a general guide.
Australian Geomechanics Vol 42 No 1 March 2007
68039 Landslide Risk Management Issued 10/7/07
Page 15
PRACTICE NOTE GUIDELINES FOR LANDSLIDE RISK MANAGEMENT 2007
APPENDIX G - SOME GUIDELINES FOR HILLSIDE CONSTRUCTION
GOOD ENGINEERING PRACTICE POOR ENGINEERING PRACTICE
ADVICE
GEOTECHNICAL Obtain advice from a qualified, experienced geotechnical practitioner at early Prepare detailed plan and start site works before
ASSESSMENT stage of planning and before site works. geotechnical advice.
PLANNING
SITE PLANNING Having obtained geotechnical advice, plan the development with the risk Plan development without regard for the Risk.
arising from the identified hazards and consequences in mind.
DESIGN AND CONSTRUCTION
Use flexible structures which incorporate properly designed brickwork, timber Floor plans which require extensive cutting and
or steel frames, timber or panel cladding. filling.
HOUSE DESIGN
Consider use of split levels. Movement intolerant structures.
Use decks for recreational areas where appropriate.
SITE CLEARING Retain natural vegetation wherever practicable. Indiscriminately clear the site.
ACCESS & Satisfy requirements below for cuts, fills, retaining walls and drainage. Excavate and fill for site access before
DRIVEWAYS Council specifications for grades may need to be modified. geotechnical advice.
Driveways and parking areas may need to be fully supported on piers.
EARTHWORKS Retain natural contours wherever possible. Indiscriminatory bulk earthworks.
Minimise depth. Large scale cuts and benching.
CUTS Support with engineered retaining walls or batter to appropriate slope. Unsupported cuts.
Provide drainage measures and erosion control. Ignore drainage requirements
Minimise height. Loose or poorly compacted fill, which if it fails,
Strip vegetation and topsoil and key into natural slopes prior to filling. may flow a considerable distance including
Use clean fill materials and compact to engineering standards. onto property below.
FILLS Batter to appropriate slope or support with engineered retaining wall. Block natural drainage lines.
Provide surface drainage and appropriate subsurface drainage. Fill over existing vegetation and topsoil.
Include stumps, trees, vegetation, topsoil,
boulders, building rubble etc in fill.
ROCK OUTCROPS Remove or stabilise boulders which may have unacceptable risk. Disturb or undercut detached blocks or
& BOULDERS Support rock faces where necessary. boulders.
Engineer design to resist applied soil and water forces. Construct a structurally inadequate wall such as
Found on rock where practicable. sandstone flagging, brick or unreinforced
RETAINING
Provide subsurface drainage within wall backfill and surface drainage on slope blockwork.
WALLS
above. Lack of subsurface drains and weepholes.
Construct wall as soon as possible after cut/fill operation.
Found within rock where practicable. Found on topsoil, loose fill, detached boulders
Use rows of piers or strip footings oriented up and down slope. or undercut cliffs.
FOOTINGS
Design for lateral creep pressures if necessary.
Backfill footing excavations to exclude ingress of surface water.
Engineer designed.
Support on piers to rock where practicable.
SWIMMING POOLS Provide with under-drainage and gravity drain outlet where practicable.
Design for high soil pressures which may develop on uphill side whilst there
may be little or no lateral support on downhill side.
DRAINAGE
Provide at tops of cut and fill slopes. Discharge at top of fills and cuts.
Discharge to street drainage or natural water courses. Allow water to pond on bench areas.
SURFACE Provide general falls to prevent blockage by siltation and incorporate silt traps.
Line to minimise infiltration and make flexible where possible.
Special structures to dissipate energy at changes of slope and/or direction.
Provide filter around subsurface drain. Discharge roof runoff into absorption trenches.
Provide drain behind retaining walls.
SUBSURFACE
Use flexible pipelines with access for maintenance.
Prevent inflow of surface water.
Usually requires pump-out or mains sewer systems; absorption trenches may Discharge sullage directly onto and into slopes.
SEPTIC &
be possible in some areas if risk is acceptable. Use absorption trenches without consideration
SULLAGE
Storage tanks should be water-tight and adequately founded. of landslide risk.
EROSION Control erosion as this may lead to instability. Failure to observe earthworks and drainage
CONTROL & Revegetate cleared area. recommendations when landscaping.
LANDSCAPING
DRAWINGS AND SITE VISITS DURING CONSTRUCTION
DRAWINGS Building Application drawings should be viewed by geotechnical consultant
SITE VISITS Site Visits by consultant may be appropriate during construction/
INSPECTION AND MAINTENANCE BY OWNER
OWNER’S Clean drainage systems; repair broken joints in drains and leaks in supply
RESPONSIBILITY pipes.
Where structural distress is evident see advice.
If seepage observed, determine causes or seek advice on consequences.
Australian Geomechanics Vol 42 No 1 March 2007 113
Page 16
PRACTICE NOTE GUIDELINES FOR LANDSLIDE RISK MANAGEMENT 2007 114 Australian Geomechanics Vol 42 No 1 March 2007
Page 17
Limitations This document has been prepared for the purpose outlined in Tectonic’s proposal and no responsibility is accepted for the use of this document, in whole or in part, for any other purpose. The scope of Tectonic’s Services are as described in Tectonic’s proposal, and are subject to restrictions and limitations. Tectonic did not perform a complete assessment of all possible conditions or circumstances that may exist at the site referenced in the report. If a service is not expressly indicated, do not assume it has been provided. If a matter is not addressed, do not assume that any determination has been made by Tectonic in regards to it. Conditions may exist which were undetectable given that economic and time constraints limit the practical extent of geotechnical investigation. Variations in conditions may occur between investigation locations, and there may be special conditions pertaining to the site which have not been revealed by the investigation and which have not therefore been taken into account in the document. Where variations exist on site, additional studies and actions may be required. Tectonic’s opinions are based upon information that existed at the time that the work was performed. The passage of time, man-made or natural events, may alter the site conditions. It is understood that the Services undertaken allowed Tectonic to form an opinion of the actual conditions of the site at the time the site was visited and cannot be used to assess the effect of any subsequent changes in the quality of the site, or its surroundings, or any laws or regulations. Any assessments made in the preparation of this document are based on the conditions indicated from published sources and the findings of the investigation described. Actual subsurface conditions may differ from those indicated in the document (e.g. between boreholes or test pits). No warranty is included, either express or implied, that the actual conditions will conform exactly to the assessments contained in this document. Where data supplied by the client or other external sources, including previous site investigation data, have been used, it has been assumed that the information is correct unless otherwise stated. No responsibility is accepted by Tectonic for incomplete or inaccurate data supplied by others. This document is provided for the sole use by the Client and its professional advisers. No responsibility whatsoever for the contents of this document will be accepted to any person other than the Client. Any use which a third party makes of this document, or any reliance on or decisions to be made based on it, is the responsibility of such third parties. Tectonic accepts no responsibility for damages, if any, suffered by any third party as a result of decisions made or actions based on this document. Limitations August 2024 | Rev2
Used in these records
25364-001-Rev0 Duke St.pdfRelated documentApplication case desk ↗
About this file
- File size
- 4.1 MB (large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take up to a minute.