4. ASSESSMENT MANAGER CONDITIONS
APPROVED PLANS
Plans and Documents
1. Development undertaken in accordance with this approval must generally comply with the
approved plans of development. The approved plans are listed in the following table unless
otherwise amended by these conditions.
Plan No. Rev. Plan/Document Name Date
TRP062026 00 Tree Survey & Retention Plan [Cover page], 1 June 2026
prepared by Equilibrium Ecology
TRP062026 00 Tree Survey & Retention Plan [Page 1], 1 June 2026
prepared by Equilibrium Ecology
TRP062026 00 Tree Survey & Retention Plan [Page 2], 1 June 2026
prepared by Equilibrium Ecology
2. Development undertaken in accordance with this approval must generally comply with the
approved plans of development. The approved plans are listed in the following table unless
otherwise amended by these conditions.
CURRENCY PERIOD
3. The Currency Period for this development approval lapses if the development has not
substantially started by 25 September 2028, unless an application to extend the currency
period is approved by Council.
PRIOR TO THE COMMENCMENT OF WORKS
4. Prior to requesting a prestart meeting:
a. Tree protection fencing must be installed under the supervision of the qualified person*.
(Refer to Retention of Existing Trees conditions).
b. Pre-clearance surveys and habitat assessment required by this Decision Notice must
be undertaken (Refer to Fauna Management conditions).
5. A prestart meeting must be organised with Council’s delegate by calling 5329 6500 (giving
at least five business days’ notice). The prestart meeting must be attended by the responsible
persons for:
a. Arboreal (tree) works
b. Fauna management works
DURING CONSTRUCTION
General
6. All works must be constructed and work procedure undertaken in accordance with:
a. The approved plans/documents and conditions detailed in this Decision Notice.
b. The relevant conditions of the higher order Reconfiguration of Lot approval viz.
RAL26/0016 to which this approval relates, except where in accordance with this
Decision Notice.
c. All relevant Council Planning Scheme Policies, standard drawings, standard
specifications and guidelines.
d. The latest version of Water Sensitive Urban Design Technical Design Guidelines for
South East Queensland (Healthy Waterways) for all water quality devices to be
constructed on site.
Page 7 of 11
Document Set ID: 25190157
Version: 4, Version Date: 24/09/2026
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
The download may take up to a minute.