Confirmation Notice Assessment Manager OPW26 0033 [As Published]

of 3
                                                                    Officer:            Daniel Epps
                                                                    Direct Telephone:   07 53296223
                                                                    Our Reference:      OPW26/0033
                                                                    Your Reference:     19960 – 02/02/2026

                 26 February 2026


                 Surveyor Pty Ltd
                 C/- Tod Consulting Pty Ltd
                 18/113 Poinciana Ave
                 TEWANTIN QLD 4565
                 [email protected]



                 Dear Sir/Madam,
                                                    Confirmation Notice
                                                         Planning Act 2016

                 Council confirms receipt of the application described below, which was properly made on 13
                 February 2026.
                 This Confirmation Notice has been prepared in accordance with the Development Assessment
                 Rules and contains information relevant to the processing and assessment of the application.
                 The following details are confirmed:
                 1.     APPLICATION DETAILS

                  Application No.                 OPW26/0033

                  Street Address:                 30 Pottery St Pomona Qld 4568

                  Real Property Description:      Lot 496 MCH 591

                  Planning Scheme:                Noosa Plan 2020 (26 September 2025)

                  Level of Assessment:            Code

                 2.     TYPE OF DEVELOPMENT PROPOSED

                 The application seeks development approval for:
                 Development Permit for Operational Works - Drainage Works, Earthworks, Roadworks,
                 Stormwater, Clearing Vegetation under planning scheme
                 3.     PUBLIC NOTIFICATION DETAILS

                 Public notification is not required for this application.
                 4.     REFERRAL DETAILS

                 No referral is required.
                 5.     INFORMATION REQUEST

                 Council may decide to make an information request.

                 ABN 97.969.214.121                                                                       PO Box 141
                 noosa.qld.gov.au                                                                  Tewantin QLD 4565
                 [email protected]                                                                  07 5329 6500
                                                                                                             Page 1 of 3
Document Set ID: 24565346
Version: 2, Version Date: 26/02/2026

Log in to download the original (Confirmation Notice Assessment Manager OPW26 0033 [As Published].pdf)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

Full text of the other 2 pages

Page 2

                 6.     OTHER DETAILS

                 You can follow the progress of this application online at www.noosa.qld.gov.au. The “Online
                 Services” page can be accessed via "Quick Links" on the left hand side of the screen. Should
                 you have any further queries in relation to the above, please do not hesitate to contact me on
                 the number above.
                 Yours faithfully,




                 Daniel Epps
                 Senior Development Engineer




                                                                                                       Page 2 of 3
Document Set ID: 24565346
Version: 2, Version Date: 26/02/2026

Page 3

                                                                  Explanatory Note – Public Notification Procedures
                                                                          Planning Act 2016 & Development Assessment Rules



            INTRODUCTION                                                             (a) if both part 2 and part 4 are relevant to the application as a
                                                                                         result of the changed application, the day after part 3 has
            The purpose of this Explanatory Note is to provide guidance to               ended;
            applicants on the public notification requirements under Section
            53 of the Planning Act 2016 (the Act) and under the                      (b) otherwise, the day after the day notice is given under
            Development Assessment Rules (the Rules). The Act and the                    section 26.2(a) or 26.2(c).
            Rules, set out the requirements for the giving of public notice.         WHAT IS PUBLIC NOTICE
            These guidelines quote much of the material contained within             The following is extracted from Part 4 of the Rules.
            the Act and the Rules.
                                                                                     17.      Public notice requirements
            If there is doubt about a particular public notification aspect, the
            applicant should refer to the Act and the Rules or have the public       17.1. The applicant, or the assessment manager acting under
            notice procedures undertaken by a consultant who is familiar             section 53(10) of the Act, must give public notice by—
            with the public notice requirements.                                     (a) publishing a notice at least once in a newspaper circulating
            Whilst every care has been taken in preparation of this                      generally in the locality of the premises the subject of the
            explanatory note, ultimately it is the applicant's responsibility to         application; and
            ensure that the procedures are correctly followed. Council will          (b) placing notice on the premises the subject of the application
            not accept any responsibility for incorrect giving of public notice.         that must remain on the premises for the period of time up
            OVERVIEW OF PUBLIC NOTIFICATION PROCEDURES                                   to and including the stated day; and
            (PUBLIC NOTICE)                                                          (c) giving notice to the adjoining owners of all lots adjoining the
            There are three distinct tasks to be undertaken when carrying                premises the subject of the application.
            out public notice:                                                       17.2. The applicant must give notice to the assessment
            1. Publishing a notice in a local newspaper.                             manager of the intended start date of public notification.
            2. Placing a notice or notices on the premises.                          17.3. Schedule 3 prescribes the way in which public notice
            3. Giving notice to adjoining owners.                                    must be given.
            After the notification period has ended, the applicant must give         17.4. All public notice requirements under section 17.1 and
            the assessment manager notice of compliance with the public              17.2 must be undertaken within the period prescribed under
            notice requirements.                                                     section 16.
            One key aspect to note is that an application automatically              18.      Notice of compliance
            lapses if public notification does not start within 20 business          18.1. If the applicant gives public notice, it must, within 10
            days of the completion of the relevant preceding part.                   days from the day after the last day on which a submission may
            Furthermore, the application also automatically lapses if                be made, or a further period agreed between the applicant and
            applicant does not give the assessment manager the notice of             the assessment manager, give the assessment manager notice
            compliance with the public notice requirements within 10                 of compliance with the public notice requirements.
            business days from the day after the last day on which a
            submission may be made.                                                  PUBLIC NOTIFICATION PERIOD
            WHEN NOTIFICATION PART STARTS                                            Section 53 of the Act states the required public notification
                                                                                     period. The following is an extract from Section 53.
            Part 4 of the Rules states when the public notification part starts.     53(4)    The notice must state that—
            The following is an extract from Part 4.
                                                                                     (a) a person may make a submission about the application to
            16. When this part starts                                                    the assessment manager; and
            16.1. If there are no referral agencies for the application and          (b) any submission must be made by a stated day that is at
            part 3 does not apply because:                                               least—
            (a) the applicant has advised that it does not wish to receive an              (i) for an application that includes a variation request—30
                information request and it is not an application mentioned in                  business days after the notice is given; or
                section 11.3; or
                                                                                           (ii) for an application of a type prescribed by regulation—
            (b) the assessment manager states in the confirmation notice                        the period, of more than 15 business days after the
                that it does not intend to make an information request;                         notice is given, prescribed for the application; or
                public notification must start within 20 days of the day after
                the confirmation notice is given to the applicant.                         (iii) for any other application—15 business days after the
                                                                                                 notice is given.
            16.2. If—
                                                                                     53(5) However, if the development assessment rules require
            (a) the applicant has advised that it does not wish to receive an        the notice to be given in more than 1 way, the period mentioned
                information request; and                                             in subsection (4)(b) starts on the day after the day when the last
            (b) it is not an application mentioned in section 11.3; and              notice is given.
            (c) there are referral agencies;                                         Please ensure that all public notices that are published in the
                    public notification must start within 20 days after the day      newspaper, placed on the land, and given to adjoining land
                    the last referral assessment period for any referral             owners clearly state that:
                    agency has started.                                              (a) written submissions may be made electronically; and
            16.3. If sections 16.1 and 16.2 do not apply, public notification        (b) electronic submissions         are     to    be     sent     to
            must start within 20 days of the day after part 3 has ended.                 [email protected]
            16.4. For a changed application, where public notification is            (c) all submissions, including individual submitter's particulars,
            required to be undertaken again from its beginning, public                   will be published on Council's website (Online Services) and
            notification must commence within 20 days—                                   therefore will be accessible to internet search engines




                                                                                                                                        Page 3 of 3
Document Set ID: 24565346
Version: 2, Version Date: 26/02/2026

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.