 (7)Development Infrastructure
 By the year 2005, this Planning Scheme is expected to have achieved the following:
 (a)full costs of "hard" infrastructure provided to serve new communities is recovered;
 (b)minimal "out of sequence" development; and
 (c)all new premises being provided with a reticulated or other reliable potable water supply and
 a reticulated or other ecologically sustainable effluent treatment and disposal system.




(7)Development Infrastructure
(a) -(b)
Attached within Appendix 5 Cardno have prepared a Water Supply and Sewerage Report to satisfy
the requirements of the Water Supply and Sewerage Reticulation Code based on an assessment of
the Noosa on Weyba Preliminary Approval Development.


The report made the following conclusions in     regard to the sites suitability for the proposed
development in regard sewerage and water networks.
   .   A sewerage network analysis has been undertaken and determined the development can be
       accommodated with external augmentation to Pump Station NVLOll and the Noosa STP.

       Currently the Noosa STP is scheduled to be upgraded in December 2015. The assessment
       indicates connection to the existing network is possible to the north of the development;
   .   A conventional gravity sewer network is proposed to service the development. Several pump

       stations are   required to convey to the flow to the existing network connection points.
       Alternative servicing strategies such as the use of low pressure sewers have been considered

       for this development. It is envisaged that subsequent development applications may result in
       alternative servicing strategies;
   .   A water network analysis has been undertaken and determined that no augmentation of the

       existing network is required to accommodate the development. Connection to the existing
       network is possible to the north of the development. A network of trunk mains and smaller
       mains is required internally to maintain Unitywater’s DSS within the development

   .   The development is outside the current water supply and sewerage planning headworks

       region and is proposed to connect to the existing water supply and sewerage networks
       currently servicing Noosa.
   .   To provide water supply to the development it is proposed to connect to the Noosa Industrial
       DMA {NIDMA}and serviced via the Tewantin Reservoirs.
   .   Analysis undertaken by MWH on behalf of Unitywater indicated that the current NIDMA
       water supply network has sufficient capacity to accommodate the development.

   .   To service the site, a connection to the existing 600mm diameter trunk main       along Eenie
       Creek Road via a 250 mm diameter main along Walter hay Drive is proposed.
   .   Consideration should be given to a connection to the existing 150 mm reticulation main in
       Lake Entrance Boulevard to avoid dead end mains in the proposed network.
   .   An internal network of 200 mm and 150 mm diameter water mains will be required to service

       each site to maintain Unitywater’s DSS.
   .   The conveyance of sewage from the site is proposed via the internal use of pump stations
       and local reticulation mains. For the purposes of this study a conventional system has been

       identified, as per Unitywater’s DSS.
   .   A   Low pressure   sewerage system     may   be considered   depending   on   topography site
       constraints and capacity at the Noosa STP. It is expected that the design flow with     a   low

       pressure system will be reduced by at least 50%,should this system be adopted.
   .   A total offive pump stations are proposed. Four internal pumps will convey flow to a central

       pump station to the north of the development.




                                                                                                    74

Used in these records

About this file

File size
35.2 MB (very large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Part 2 of 37 Noosa on Weyba Town Planning Assessment Report MCU12_0208.pdf · 35.2 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.