Bushfire Overlay Code.
Flood hazard overlay code
Overall outcomes
(2)The purpose ofthe Flood hazard overlay code will be achieved through the following overall outcomes:-
(a)development does not occur on land subject to flooding except where:-
(i) the development satisfies one or more ofthe following criteria:-
(A) the development is on land already committed to urban development by an approval
granted prior to the commencement of the planning scheme;
(B)the development is on land identified in a structure plan as an area intended for urban
development;
(C)the development is infill development within an existing developed area;
(D)there is an overriding community need in the public interest for the development; or
(E)the development is for the infrastructure identified on the planning scheme maps; and
(ii) the impacts of flooding on the development can be effectively ameliorated such that there is no
foreseeable risk to life or property;
(b) development protects floodplains and the flood conveyance capacity of waterways;
(c) development in areas at risk from flood and storm tide inundation is compatible with the nature of the
defined flood or storm tide event;
(d) the safety of people is protected and the risk of harm to property and the natural environment from
flood and storm tide inundation is minimised;
Regarding flood impact the proposed development of Noosa on Weyba has been shown through
TUFLOW modelling to:
. have no adverse impacts on flood levels and flows for surrounding properties for local and
regionalflood events;
. reduce the 100 year ARI event the peak flood level around Lake Entrance Boulevard due to
flow attenuation being proposed within the site;
. provide 100 year ARI trafficability for all proposed and upgraded roads;
. provide PMF evacuation routes for all areas of the site; and
.
improve flood access for neighbouring properties.
The flood levels used to set the development levels for the site include the potential impact of climate
change. The proposed filling within the site will reduce available flood storage, although compared to
the available storage in Lake Weyba and the surrounding floodplain, the reduction is minimal. Flood
modelling has shown that the impact of the reduced flood storage is contained within the site. Dense
revegetation of the western drainage channel is considered to be achievable with acceptable flood
impacts for the site and surrounding properties should this be desirable.
The proposed Noosa on Weyba development will have an overall low scale of total impermeable site
coverage. This is beneficial to the development as the effects of flooding will be felt to a much lesser
degree due there being a large amount of area where water can infiltrate into the ground. Noosa on
Weyba will allow for improvements to the existing flooding classification of the site with no
95
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Part 2 of 37 Noosa on Weyba Town Planning Assessment Report MCU12/0208Related documentApplication case desk ↗
About this file
- File size
- 35.2 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.