2018-08-13 General Committee Agenda

of 48

Page text shows just the words. Original shows the document exactly as it was published.

Page text read automatically using OCR, there may be inaccuracies

Text sections have not been matched to the original PDF pages. Use the original document to check page numbers.

Page 25 of 48

Noosa Shire Council                                                                                               ATTACHMENT 2
  2018/19 Budget Review 1 Capital Submissions
  For the period ending 30 June

  Project                                    ert ag til  Full Year     2018/19 Comment
                                              Budget       Actual    Proposed
                                             2017/18        Spend       Budget
                                                          yA  CE)       TY
  Capital Works Total                     11,101,590   10,491,828     vA RS 74
Bridges
 Cooran Old Noosa Road Bridge Renewal                     117,304        12,896] Construction underway with the project to be completed in
                                                                               2018/19.
 Cooroy Mary River Road Bridge Renewal                     169,835     184,365|Construction underway with the project to be completed in
                                                                               2018/19.
 Orealla Crescent Overpass                                               11,961|Design complete and grant funding secured in 2017/18.
  Refurbishment                                                                Construction to occur in 2018/19.
 Total Bridges                               518,000/     308,778)    209.222)
 Coastal Canals and Waterways          pe
  Renewal of revetment wall at O-Boats                                     -976|Project deferred to 2018/19 at BR3. However, planning and
 Gympie Tce, Noosaville                                                        design spend undertaken in 2017/18 to offset 2018/19 budget.
 Total Coastal Canals and Waterways | 1,085]                2,061,976)
 Commerical Land & Property                  I Rs
  Peregian Digital Hub - Fitout                             55,818             Construction underway with the project to be completed in
                                                                               2018/19.
  Rufous Street Stage 3 Planning and                                   100,000|Initial budget allocation to progress planning and design of Digital
 Design                                                                         Hub Stage 2 following successful grant application.
 Total Commerical Land &Property      |             0.     55,818]    224182)
‘Community Facilities                   |
  Noosa Heads Demolition of Lifeguard                        2,729       -2,729|Project deferred to 2018/19 at BR3. However, some initial
 Service/ SLSQ operations                                                      demolition works undertaken in 2017/18 to offset 2018/19
                                                                                budget.
 Tewantin SES Termite Damage                    8,300                     6,977|Construction underway with the project to be completed in
                                                                               2018/19.
  NAC & NLC Roof Restoration (to Support      72,500                     72,500|Project delayed to 2018/19 to provide full assessment of roof
 Solar Panels)                                                                  replacement requirements.
 Cooroy SES Shed Alterations                                             30,000/Emergent works to resolve shed constraints to accommodate
                                                                                new SES vehicle at Cooroy SES authorised at Capital Works
                                                                                Executive.
 Total Community Facilities                   80,800, 4,052},          106,748)
 Corporate Buildings                               SR                          QO
 Tewantin Administration Building - Master    20,000                     20,000|Project delayed to 2018/19.
  Planning & detailed design
 Tewantin Administration Building - Roof      50,000                     50,000|Works yet to commence and will be completed during 2018/19.
  Replacement
 Tewantin Admin Building Automatic             17,697                    17,037|Specialist goods required to complete the works are yet to be
 Transfer Switch                                                               delivered. Will be completed during 2018/19.
 Total Corporate Buildings                    87,697)         684]     87,087
 Gravel Road Network                    RS Rs
  Hinterland - Upgrade of Gravel Rd          500,000     343,985               Construction underway with the project to be completed in
 Sections (Donnelly's Rd)                                                      2018/19.
 Total Gravel Road Network                                343,985]    156,015)
 Holiday Parks                         pe
  Noosa North Shore Beachfront               260,500                            Design complete with construction to occur in 2018/19.
 Campground Redevelopment
  Noosaville Noosa River Holiday Park        601,304      575,917        25,387 |Construction underway with the project to be completed in
 Small Amenities Renewal                                                       2018/19.
 Total Holiday Parks                         861,804)    827,307)      34.497)
 Libraries & Galleries                    Rs Rs
  Noosaville Library Refurbishment          906,931      1,124,967     -218,036|Construction underway on multi-year project. Overspend in
 Construction                                                                  2017/18 as progress is ahead of schedule. Budget to reduce in
                                                                               2018/19 to ensure total project budget remains within scope.

 Total Libraries & Galleries                 906,931)    1,124,967)    -218,036)]
 Parks & Playgrounds                      Re                                   QO
 Cooran Pioneer Park upgrade - Design &       45,000       76,401       -31,401|Design underway on multi-year project. Overspend in 2017/18 as
 Construction                                                                   progress is ahead of schedule. Budget to reduce in 2018/19 to
                                                                               ensure total project budget remains within scope.
 Cooroy Hinterland Priority Playground -                   64,683       -29,683|Design underway on multi-year project. Overspend in 2017/18 as
  Design & Construction                                                         progress is ahead of schedule. Budget to reduce in 2018/19 to
                                                                               ensure total project budget remains within scope.
 Botanic Garden Shade House                   50,000       47,336               Project undertaken in 2017/18, with final outstanding invoices to
                                                                                be paid in 2018/19.
 Total Parks & Playgrounds                   130,000}     188,420)      58,420)
 Pathways & Boardwalks                 pe
                                                                                                                       Page 25 of 48
Log in to download the original file

2018-08-13 General Committee Agenda(PDF, 7MB).pdf · 7.4 MB (large file)

Large file: the download may take up to a minute.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.