2018-08-13 General Committee Agenda
Text sections have not been matched to the original PDF pages. Use the original document to check page numbers.
Page 25 of 48
Noosa Shire Council ATTACHMENT 2
2018/19 Budget Review 1 Capital Submissions
For the period ending 30 June
Project ert ag til Full Year 2018/19 Comment
Budget Actual Proposed
2017/18 Spend Budget
yA CE) TY
Capital Works Total 11,101,590 10,491,828 vA RS 74
Bridges
Cooran Old Noosa Road Bridge Renewal 117,304 12,896] Construction underway with the project to be completed in
2018/19.
Cooroy Mary River Road Bridge Renewal 169,835 184,365|Construction underway with the project to be completed in
2018/19.
Orealla Crescent Overpass 11,961|Design complete and grant funding secured in 2017/18.
Refurbishment Construction to occur in 2018/19.
Total Bridges 518,000/ 308,778) 209.222)
Coastal Canals and Waterways pe
Renewal of revetment wall at O-Boats -976|Project deferred to 2018/19 at BR3. However, planning and
Gympie Tce, Noosaville design spend undertaken in 2017/18 to offset 2018/19 budget.
Total Coastal Canals and Waterways | 1,085] 2,061,976)
Commerical Land & Property I Rs
Peregian Digital Hub - Fitout 55,818 Construction underway with the project to be completed in
2018/19.
Rufous Street Stage 3 Planning and 100,000|Initial budget allocation to progress planning and design of Digital
Design Hub Stage 2 following successful grant application.
Total Commerical Land &Property | 0. 55,818] 224182)
‘Community Facilities |
Noosa Heads Demolition of Lifeguard 2,729 -2,729|Project deferred to 2018/19 at BR3. However, some initial
Service/ SLSQ operations demolition works undertaken in 2017/18 to offset 2018/19
budget.
Tewantin SES Termite Damage 8,300 6,977|Construction underway with the project to be completed in
2018/19.
NAC & NLC Roof Restoration (to Support 72,500 72,500|Project delayed to 2018/19 to provide full assessment of roof
Solar Panels) replacement requirements.
Cooroy SES Shed Alterations 30,000/Emergent works to resolve shed constraints to accommodate
new SES vehicle at Cooroy SES authorised at Capital Works
Executive.
Total Community Facilities 80,800, 4,052}, 106,748)
Corporate Buildings SR QO
Tewantin Administration Building - Master 20,000 20,000|Project delayed to 2018/19.
Planning & detailed design
Tewantin Administration Building - Roof 50,000 50,000|Works yet to commence and will be completed during 2018/19.
Replacement
Tewantin Admin Building Automatic 17,697 17,037|Specialist goods required to complete the works are yet to be
Transfer Switch delivered. Will be completed during 2018/19.
Total Corporate Buildings 87,697) 684] 87,087
Gravel Road Network RS Rs
Hinterland - Upgrade of Gravel Rd 500,000 343,985 Construction underway with the project to be completed in
Sections (Donnelly's Rd) 2018/19.
Total Gravel Road Network 343,985] 156,015)
Holiday Parks pe
Noosa North Shore Beachfront 260,500 Design complete with construction to occur in 2018/19.
Campground Redevelopment
Noosaville Noosa River Holiday Park 601,304 575,917 25,387 |Construction underway with the project to be completed in
Small Amenities Renewal 2018/19.
Total Holiday Parks 861,804) 827,307) 34.497)
Libraries & Galleries Rs Rs
Noosaville Library Refurbishment 906,931 1,124,967 -218,036|Construction underway on multi-year project. Overspend in
Construction 2017/18 as progress is ahead of schedule. Budget to reduce in
2018/19 to ensure total project budget remains within scope.
Total Libraries & Galleries 906,931) 1,124,967) -218,036)]
Parks & Playgrounds Re QO
Cooran Pioneer Park upgrade - Design & 45,000 76,401 -31,401|Design underway on multi-year project. Overspend in 2017/18 as
Construction progress is ahead of schedule. Budget to reduce in 2018/19 to
ensure total project budget remains within scope.
Cooroy Hinterland Priority Playground - 64,683 -29,683|Design underway on multi-year project. Overspend in 2017/18 as
Design & Construction progress is ahead of schedule. Budget to reduce in 2018/19 to
ensure total project budget remains within scope.
Botanic Garden Shade House 50,000 47,336 Project undertaken in 2017/18, with final outstanding invoices to
be paid in 2018/19.
Total Parks & Playgrounds 130,000} 188,420) 58,420)
Pathways & Boardwalks pe
Page 25 of 48See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.