Delegated Report - Code - Planning OPW24 0103 (As Published) · OPW24/0103

of 14

Text shows just the words. Original shows the document exactly as it was published.

                      b.      be lodged with Council and accompanied by the Bond Administration Fee/s; and
                      c.      be requested for release by writing to Council, when relevant approval requirements
                              have been met
               PRIOR TO COMMENCEMENT OF WORKS
                      Engineering
               5.     All necessary approvals from external service providers (e.g., Unitywater) and external
                      parties on which the development works are proposed have been obtained and a copy
                      supplied to Council.
               6.     A condition report including photographs of the frontage of the site must be completed and
                      submitted to council at the prestart meeting / prior to any works commencing.
                      (*) Refer to Advisory Note
               7.     Certificates demonstrating currency of public liability insurance and works insurance covering
                      the works must be submitted to Council prior to the prestart meeting.
               8.     Council must be contacted at least 5 working days prior to any works commencing to
                      organise a prestart. The contact number to arrange a pre-start meeting is 5329 6500. The
                      pre-start meeting must include the relevant parties for the following aspects of the works:
                      a.      Civil engineering works;
                      b.      Landscape works;
                      c.      Erosion and sediment control works; and
                      d.      Other relevant parties
               9.     A Construction Management Plan must be submitted to Council for agreement prior to the
                      pre-start meeting and must specifically address the following:
                      a.      Traffic management during all aspects of the construct phase including:
                              i.       A Traffic Management Control Plan in accordance with Manual of Uniform Traffic
                                       Control Devices (MUTCD) detailing all temporary signage and traffic control
                                       measures prior to construction;
                              ii.      Maintenance of safe vehicle and pedestrian access across the Douglas Lane and
                                       Duke Street frontages of the site both during daily construction and after daily
                                       construction has ceased;
                              iii.     Proposed fencing to the site during the construction phase of the development;
                              iv.      Adequate parking arrangements for construction workers and deliveries (i.e.,
                                       materials, concrete pump, concrete truck, etc.); and
                              v.       No queuing of trucks is permitted on residential streets, especially prior to
                                       7.00am. Further parked trucks must have engines turned off.
                      b.      Maintenance and protection of water quality and existing drainage lines through the
                              construction site through the implementation of appropriate erosion and sediment
                              control measures;
                      c.      Works programme identifying key components of the works and their respective
                              durations;
                      d.      Establishment of a communication protocol with the general public, adjoining owners,
                              emergency services and local businesses to advise of agreed construction times,
                              impacts on traffic and services and other relevant issues;
                      e.      Include a post out to the local residents and businesses advising of the proposed
                              development, the expected time frames and the site contact details;



                                                                                                         Page 7 of 14

Document Set ID: 23287257
Version: 4, Version Date: 09/10/2024

Used in these records

About this file

File size
1.7 MB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Delegated Report - Code - Planning OPW24 0103 (As Published).pdf · 1.7 MB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.