9 August 2006 - permitted the sewer and stormwater lines to discharge to Park Road rather
than to Allambi Rise
27 September 2007 - approved a 50m² extension to the dwelling bringing the total gross
floor area to 198m2.
6 September 2017 – approved retaining wall and unroofed deck. Following Council’s
decision, an appeal was lodged with the Planning and Environment Court on 20 September
2016 by the applicant. The matter was latter resolved between the parties and confirmed
by Judgment of the Planning and Environment Court on 1 November 2011 with the deck
setback 1 metre from the front boundary.
In April 2018 Council officers became aware that works for the lift access walkway had
commenced at the site without a planning approval. The works relate to piling for an underground
tunnel to access a proposed lift shaft. These works are subject to a separate application.
2.2. Site Description
The site contains an existing dwelling nestled amongst the vegetated steeply sloping lot (approx.
30% slope). Vehicle access is from 9 Allambi Rise via an access easement.
2.3. Surrounding Land Uses
Immediately to the north is a detached dwelling accessed from Allambi Rise. Further to the north
with frontage to Park Road are units that are considerably elevated above Park Road and
accessed from an Allambi Rise ‘service’ road.
Immediately to the south is a detached dwelling owned by the applicant. This dwelling has direct
vehicle access to Park Road from a basement garage which is within the Park Road setback
area. Further to the south are detached dwellings, unit blocks and mixed uses fronting Hastings
Street.
To the west across Park Road is Noosa Main Beach and units fronting the beach.
3. STATUTORY PROCESS
The applicant has requested a pre-request response to make a minor change to a development
approval under s78 of the Planning Act 2016. An application for a minor change to a
development approval can only be made in circumstances where a change would constitute a
‘minor change’. The proposed change to the development approval requested by the applicant is
determined to constitute a minor change on the grounds that:
the change would not result in substantially different development as the use remains the
same as that approved and the scale and bulk of the development remains generally
consistent with the current approval. There are no new uses proposed that would create
different or additional impacts; the change does not include prohibited development;
the change would not require the application to be referred to an additional referral agency
or cause a referral agency to have regard to new mattes prescribed by regulation; and
the proposed changes do not vary the level of assessment;
4. ASSESSMENT
The applicable planning instruments that Council must have regard to are:
State Planning Regulatory Provisions;
State Planning Policies; and
2006 Noosa Plan.
The most recent amendment was considered consistent with the higher order State Regulatory
Provisions and Planning Policies. The proposed design modifications will not substantially
change the existing approval and are still consistent with the higher order provisions.
Page 76 of 97
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalVery large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.