8 PLANNING & ENVIRONMENT APPEAL NO. 1302 OF 2018 REGARDING
ENFORCEMENT NOTICE - 105 RESORT DRIVE, NOOSA HEADS
DOCUMENT INFORM AT ION
Author Manager Development Assessment, Kerri Coyle
Environment & Sustainable Development Department
Index ECM/ Application / OPW17/0557
Attachments Nil
EXECUTIVE SUMMARY
Not applicable.
RECOMMENDATION
That Council note the report by the Manager Development Assessment to the Planning &
Environment Committee Meeting dated 12 June 2018 regarding Planning & Environment Court
Appeal No. 1302 of 2018 and the proposed settlement.
REPORT
This report is to provide an update to Council on an appeal received against an Enforcement
Notice issued to the developer for clearing vegetation on the road reserve adjacent 105 Resort
Drive, Noosa Heads.
In February this year Council received complaints in relation to clearing of vegetation on the road
reserve adjacent to 105 Resort Drive, Noosa Heads which is currently being developed for
multiple dwelling units.
Inspection of the site by Council officers confirmed that clearing of vegetation had occurred on
the road reserve adjacent 105 Resort Drive contrary to the conditions of the Development Permit
for Operational Works – Earthworks. The species removed from the road reserve included 4
Brush Box and 1 Bribie Island Pine, all reasonably mature native trees. The development
approval requires earthworks to be carried out in accordance with a number of conditions
including specifically relevant conditions 1, 3, 32, 33, 34 and 35 as follows:
1. Development undertaken in accordance with this approval must generally comply with the
approved plans of development. The approved plans are listed in the following table unless
otherwise amended by these conditions.
Plan No. Rev. Plan/Document Name Date
17155/C00 A2 Cover Sheet and Drawing Index prepared by 21 December 2017
Morgan Consulting Engineers
17155/C01 A1 Site Clearing Plan prepared by Morgan Consulting 20 December 2017
Engineers
17155/C02 A1 Bulk Earthworks Plan prepared by Morgan 20 December 2017
Consulting Engineers
17155/C03 A1 Bulk Earthworks Sections prepared by Morgan 20 December 2017
Consulting Engineers
VM05 C Vegetation Management Plan, prepared by 29 November 2017
Anembo
FOR PRECINCT E2 ONLY
Page 92 of 97
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalVery large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.