Operational Waste Management Plan
142 Noosa Drive, Noosa Heads
4 Primary Waste Streams and Quantity Calculations
SC6.10 PSP9 Waste Management of the Noosa Plan 2020 outlines the minimum service levels for visitor
accommodation as:
‘One 240 litre waste storage bin per 4 cabins or caravan sites per week and one 240 litre recycling bin per 4 camp
sites per fortnight (Bulk bins can also be used for waste storage, provided the capacity of the bin equates to 60
litres per cabin or caravan site per week).’
It is understood that it is the preference of RACV to provide communal bulk bins rather than individual bins for
each cabin to ensure consistency with the existing part of the eco-resort immediately north of the site. Table 1
shows the estimated general and recyclable wastes generated from the proposed development based on the
minimum service levels outlined above.
Table 1 Waste generation calculations and bin requirements
Site Use Estimated Estimated Calculated Calculated General Recyclable
General Waste Recyclable General Recyclable Waste Bin Waste Bin
Rate Waste Rate Waste Rate Waste Rate Requirements Requirements
Eco- 60L/cabin/week 60L/cabin/week 900 L/week 900 L/week One (1) x One (1) x
cabins 1.1m3 bulk bin 1.1m3 bulk bin
(15 collected collected
cabins) weekly1 weekly1
4.1 Bin Storage Area Design & Collection Requirements
The designated bin storage area at the site shall be used to store the required general and recyclable waste bulk
bins and shall be located adjacently south-east of the proposed carpark entrance (Figure 2).
It is recommended that the bin storage area has the following features as per the requirements of SC6.10 PSP9
Waste Management of the Noosa Plan 2020:
• Is a sufficient size to accommodate the required number and type of bins outlined below in Table 2 to
allow for the bins to sit next to each other and not behind each other.
• Is constructed on an impervious area.
• Is suitably screened from public places and neighbouring properties.
• Includes adequate lighting to allow the usage of the storage area after dark.
• Includes a cold-water tap and hose for washing of the bulk bins within the bunded storage area and
drains to an outlet connected to sewer via a bucket trap. The drain outlet shall be designed to prevent
stormwater entry to the sewerage system.
The bulk bins (which shall have rubber wheels) shall be relocated to the Sanctuary Drive kerbside by Resort Staff
for servicing. The bulk bins shall be presented as shown in Photograph 1 to ensure consistency with the current
practice at the existing part of the eco-resort as the existing and proposed eco-resort will be serviced
concurrently.
1
Additional collections will be scheduled during peak holiday periods as required.
JOB NUMBER J002662 STATUS Final VERSION 2 DATE 2/12/2025 10
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Reference Document Emergency Management Plan & Reponse Procedures Feb 2026 OPW25-0206.pdfRelated documentApplication case desk ↗
About this file
- File size
- 6.6 MB (large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take up to a minute.