Skip to the record
Trusted by locals. Built for Noosa.

Original source · versioned page text

Delegated Report - Code - Planning OPW21 0354

of 1

Page text shows just the words. Original shows the document exactly as it was published.

Author	Coordinator Engineering, Mark Lewis
Development Assessment

APPLICATION DETAILS
Application No.	OPW21/0354
Applicant	Anthony Lyndon Rossiter & Anoma Rossiter C/ Brennan Planning Pty Ltd
Proposal	Operational Works - Earthworks
Properly Made Date	8 December 2021
Information Request Date	7 January 2022
Information Response Date	17 February 2022
Decision Due Date	30 March 2022
Report Completed Date	28 March 2022
Report Reviewed By	Diogo Carrico

PROPERTY DETAILS
Property Address	8 Robin Place Lake Macdonald Qld 4563
RP Description	Lot 13 SP 315578
Land Area	15320.000 m²
Existing Use of Land	Vacant (dwelling under construction)

STATUTORY DETAILS
SEQRP Designation	Rural Living Area
Zone	Rural Residential
Precinct	Not Applicable
Local Plan Area	Not Applicable
Overlays	Biodiversity, Bushfire, Extractive Resources, Landslide, Koala habitat
Assessment Type	Code
PROPOSAL
The application seeks approval for Operational Works – Earthworks (construction of a dam).
The locality and proposal plan are included below.

Figure 1 – Locality

Figure 2 – Site Plan

site details
Background
The application is to construct a dam in approximately the middle of the site. The reconfiguration approval that created the site conditioned the building envelope to be located towards the front of the site and the significant vegetation at the rear to be contained within a covenant.
assessment
Instruments for Statutory Assessment
Under the Planning Act 2016 the application must be assessed against each of the following statutory planning instruments to the extent they are relevant to the development:
State Planning Policy;
South East Queensland Regional Plan;
Planning Regulation 2017; and
Noosa Plan 2020.
Noosa Plan 2020
The following codes from the Noosa Plan 2020 are applicable to this development:
Earthworks Code;
Water Quality and Drainage Code
The application has been found to generally comply with all applicable statutory instruments.
The design for the dam has been prepared by RECOR (Consulting Engineers) and the construction of the dam will require the removal of a number of trees that are outside of the covenant area. Council’s Senior Environment Officer has assessed the application and provided conditions for inclusion.
cONSULTATION
Referral Agencies
Internal Council Referrals
The application was forwarded to the following internal Council officers for review and/or comment:
Senior Environment Officer
conclusion & reasons for decision
The proposed development generally complies with the requirements of the planning scheme and does not raise any significant issues that cannot be addressed by reasonable and relevant conditions. The application is therefore recommended for approval.
The report is provided in accordance with Section 63(5) of the Planning Act 2016.
RECOMMENDATION
With regard to Application No OPW21/0354 for Operational Works - Earthworks (Construction of a dam) situated at 8 Robin Place Lake Macdonald Qld 4563 and described as Lot 13 SP 315578, it is recommended the application be approved in accordance with the following details for the Decision Notice:
application details
Application No:	OPW21/0354
Street address:	8 Robin Place Lake Macdonald Qld 4563
Real property description:	Lot 13 SP 315578
Planning Scheme:	Noosa Plan 2020 (25 September 2020)
Decision details
Council decided to issue the following type of approval:
Development Permit for Operational Works – Earthworks (Construction of a dam)
CURRENCY PERIOD of approval
The currency period for this development approval is stated in the conditions below.
assessment manager conditions
APPROVED PLANS
Development undertaken in accordance with this approval must generally comply with the approved plans of development. The approved plans are listed in the following table unless otherwise amended by these conditions.
Plan No.	Rev.	Plan/Document Name	Date
C10	A	Bulk Earthworks Plan prepared by RECOR	31 January 2022
		Proposed Dam Impact to Native Vegetation (email) prepared by North Coast Environmental Services	26 November 2021
CURRENCY PERIOD
The Currency Period for this development approval lapses if the development has not substantially started by 28 March 2024, unless an application to extend the currency period is approved by Council.
SITE SPECIFIC CONDITIONS
Bonds
A site control and/or tree protection bond of $2500 is to be submitted to Council prior to the pre-start meeting. The pre-start meeting will only be held once Council's Construction Engineering Officer has confirmation that the bond monies have been received by Council.
The bond:
will be refunded less any costs incurred by Council in ensuring compliance with these conditions or any additional inspections incurred for substandard work or work undertaken not in accordance with this permit
may be drawn upon by Council in its entirety if the trees or any one tree identified for retention is damaged to the point where the tree cannot be saved (as confirmed by the project arborist and agreed in writing by Council)
will be returned upon practical completion of all the operational works relating to this development.
Bonds must:
meet the requirements of Council’s relevant Planning Scheme Policy for performance and uncompleted works.
be requested for release by writing to Council, when relevant approval requirements have been met.
PRIOR TO COMMENCEMENT OF WORKS
Engineering
Tree protection fencing must be installed under the supervision of the Project Arborist.  (Refer to Retention of Existing Trees Conditions)
A condition report including photographs of the frontage of the site must be completed and submitted to council at the prestart meeting / prior to any works commencing.
Certificates demonstrating currency of public liability insurance and works insurance covering the works must be submitted to Council prior to the prestart meeting.
Council must be contacted at least 5 working days prior to any works commencing to organise a prestart. The contact number to arrange a pre-start meeting is 5329 6500. The pre-start meeting must include the relevant parties for the following aspects of the works:
Civil engineering works;
Arboreal works;
Fauna management works;
Rehabilitation works;
Erosion and sediment control works;
Other relevant parties
A Construction Management Plan must be submitted to Council prior to the pre-start meeting and must specifically address the following:
appropriate traffic signage in accordance with the Manual of Uniform Traffic Control Devices (MUTCD)
provision for safe vehicle and pedestrian access across the frontage of the site both during daily construction and after daily construction has ceased.
Any changes to the details associated with the supervising RPEQ or Principal Contractor during construction, must be notified to council in writing within five business days of the change occurring.
Any conflict between the development and an existing or proposed service must be referred to the relevant service authority for determination prior to commencement of works.
DURING CONSTRUCTION
Engineering
The developer must meet any costs to repair damage to any Council asset during construction, where damage is a result of the development works. Damage to assets must be repaired immediately where it creates a hazard to the community. In circumstances where the damage does not create a hazard to the community, it must be repaired immediately on completion of the works associated with the development.
All works must be supervised by a Registered Professional Engineer of Queensland (RPEQ) who is independent of the Developer and Principal Contractor, and they must certify that all works conform to the Operational Works permit. Where municipal works are involved, such confirmation must be submitted for the respective hold points prior to any site inspection by Council Officers.
All works must be constructed and work procedure undertaken in accordance with:
The approved plans/documents and conditions detailed in this Decision Notice
All relevant Noosa Council Planning Scheme Policies, standard drawings, standard specifications and guidelines
The latest version of the Healthy Waterways document “Water Sensitive Urban Design Technical Design Guidelines for South East Queensland” for all water quality devices to be constructed on site
Earthworks
All earthworks must be undertaken in accordance with the provisions of AS 3798 Guidelines on Earthworks for Commercial and Residential Development.
Slope and batters are a maximum grade of:
1 in 6 where in proximity to waterbodies
1 in 4 for grassed areas.
1 in 3 for planted areas
1 in 2 for combined structural engineering and planting solutions.
Stormwater Drainage
Appropriate scour protection must be provided at the outlet of all stormwater drainage including temporary outlets.
Works associated with this permit must not adversely impact on the existing drainage conditions on other properties (eg by blocking or interfering with natural overland flows).
Erosion and Sediment Control
Prescribed Water Contaminants (as defined in Schedule 10 of Environmental Protection Regulation 2019) must not be released from the site or to waters within the site, or be likely to be released should rainfall occur, unless all reasonable and practicable measures are taken to prevent or minimise the release and concentration of contamination.
Sediment and erosion control measures must be in place prior to works commencing. If such measures are not in place or are not satisfactory, “on the spot” fines may be issued. Such fines can be issued if sediments from the site are found to enter or have the potential to enter Council’s stormwater system, natural waterways, any downstream stormwater filtration system or adversely impacting on other properties.  The sediment and erosion control design and measures have NOT been approved, it is the site's Supervising Engineer who is responsible for ensuring that the sediment and erosion control measures have:
Been duly designed by an RPEQ or CPESC and constructed in accordance with "best practise" methods,
Been revised by an RPEQ or CPESC to address the issues raised by changes in the projected construction schedule and/or methods,
Been revised to address predicted rainfall events, and
Achieve the desired environmental outcomes.
Council may request further controls to be installed should the implemented measures be found inefficient.
The erosion and sediment control measures must be designed, installed and maintained in accordance with the supervising engineer instructions and the current best practice standards * (Refer to Advisory Note).
The developer must ensure non-essential exposure of soil is prevented by restricting the extent of disturbance and minimising the duration of soil exposure to adverse weather conditions and effectively turf, cover or stabilise any disturbed area without delay and prior to rainfall occurring.
The developer must ensure sediment does not leave the site or enter onto adjoining properties or Council’s drainage system due to surface runoff or on tyres of vehicles and/or machinery. It is essential to implement appropriate approved erosion and sediment control measures throughout the site during all phases of construction including vehicle shakedown pad/grid (or similar) at the access to the construction site. Where sediments or other contaminants are deposited on a road, they must be removed so as not to enter Council’s drainage system or waterways.
Prior to the completion of the development and commencement of use, all site surfaces must be effectively stabilised using methods which have achieved effective short-term stabilisation and which will continue to achieve effective stabilisation in the medium to long-term. For the purpose of this condition, an effectively stabilised surface is defined as one that does not, or is not likely to result in visible evidence of soil loss caused by sheet, rill or gully erosion or lead to sedimentation, or lead to water contamination.
Retention of Existing Trees and Vegetation
All trees and vegetation identified for retention must be protected in accordance with AS 4970, Protection of trees on development sites.
All works must be carried out in accordance with the conditions and the approved plans within this Decision Notice.
A qualified person * must be engaged for the duration of the works to:
Ensure works are carried out in accordance with the approved documents and conditions.
Oversee installation of all tree protection fencing prior to commencement of any works onsite (including any clearing).
Supervise tree protection within the development site and frontages, prior to, during and following construction in accordance with AS 4970, Protection of trees on development sites.
Oversee approved tree removal in proximity to retained trees.
Undertake a risk assessment of all trees within striking distance of the development works and site and carry out hazard removal and amenity pruning in accordance with AS 4373, Pruning of amenity trees.
*(Refer to Advisory Note)
Vegetation areas for protection must:
Be protected in accordance with the approved Bulk Earthworks Plan.
Be protected with a 1.8m high temporary safety fence or temporary barrier mesh or three-strand wire with pickets at 3m centres.
Have the fence installed prior to the prestart meeting and maintained for the entire period of construction.
Have ‘Exclusion Zone’ (‘No Go’) signage fixed to the fence at 10m centres.
Have no construction material, equipment or personnel entering the exclusion area except to undertake approved rehabilitation activities.
*(Refer to Advisory Note)
The trees identified for retention in the conditions of this approval and the approved Bulk Earthworks Plan listed within this Decision Notice must be maintained in good health for the life of the tree.
Fauna Management
Fauna or fauna habitat relating to minor approved tree removal/clearing works must be managed by a qualified person*.
Removal of Existing Trees and Vegetation
MINOR TO MODERATE VEGETATION REMOVAL
Removal of existing trees and vegetation must be undertaken by a qualified person* and must include:
Rectification to the finished surface levels and materials including native grass seed.
No damage to other vegetation for retention.
Replanting at a ratio of 3:1 replacement trees for each removed tree.
*(Refer to Advisory Note)MAJOR VEGETATION REMOVAL
Rehabilitation after Vegetation Clearing
Rehabilitation works must be supervised, undertaken and certified by qualified persons*.  All works must be completed in accordance with this Decision Notice.
*(Refer to Advisory Notes)
Rehabilitation offset planting must:
Be undertaken immediately following completion of the earthworks that required the clearing.
Be revegetated with a species mix of Eucalyptus grandis, Corymbia intermedia, Lophostemon confertus and Commersonia bartramia or other species approved by Council.
Be located between the dam and the conservation covenant boundary.
Be maintained including but not limited to replacement plants if plant deaths occur, tree guards, weed removal, watering.
*(Refer to Advisory Note)
Rehabilitation outcomes must be submitted to Council 12 months following rehabilitation planting and include photographic and written evidence of success of the rehabilitation offset area ensuring all required trees are alive and healthy.
Damage to Services and Assets
Any damage caused to existing services and assets as a result of the development works must be repaired at no cost to the asset owner at the following times:
where the damage would cause a hazard to pedestrian or vehicle safety, immediately; or
where otherwise, upon completion of the works associated with the development.
Any repair work which proposes to alter the alignment or level of existing services and assets must first be referred to the relevant service authority for approval.
FOLLOWING CONSTRUCTION
Certification
Upon completion of the work a certificate must be issued by an RPEQ certifying that the works have been constructed in accordance with the Operational Works permit.
Upon completion of the work a certificate must be issued from the site Arborist that states that all requirements nominated in the Arborist report referenced within this Decision Notice have been completed.
A final inspection and approval of the new dam and completed reinstatement works by Council’s Inspector is required. Please contact Council on 5329 6500 to arrange for the inspection.
referral agencies
Not applicable.
Advisory notes
The following notes are included for guidance and information purposes only and do not form part of the assessment manager conditions:
General Advisory Notes
As the dam is a private structure, the owner bears full responsibly for the standard of its construction, maintenance and any liabilities associated with its construction. It is recommended that professional advice be sought for the construction of the dam.
Council has undertaken an audit check of the Operational Works drawings in relations to the proposed works.  A detailed check of the calculations and drawings has not been undertaken, as they have been certified by a RPEQ. The RPEQ bears full responsibility for all aspects of the engineering design.  Council reserves the right to require further amendments and/or additions at a later date should design errors become apparent.
Council reserves the right to call up any performance bond held or levy charges against the property, should emergency works be required to be undertaken by Council to make the site safe due to inactivity on the development site for extended periods of time.
Should any changes or modifications to the approved plans be required as a result of construction constraints, a “Request to change an existing approval” under the Planning Act 2016 must be made. Amended plans clearly indicating the changes must be lodged with this application along with the appropriate fees.
Prestart, On and Off Maintenance Inspections Request
Contact Council on 5329 6500 to arrange a prestart or an inspection giving a minimum of 5 business days notice of preferred inspection time.
If Council officers are required to undertake additional inspections of the same works, a reinspection fee will be applicable in accordance with Council’s Fees and Charges register applicable at the time.
A minimum maintenance period of 12 months will apply to all municipal works and thereafter until such time as the works are performing in accordance with the approved design unless noted otherwise
Environmental Advisory Notes
The Environmental Protection Act 1994 states that a person must not carry out any activity that causes, or is likely to cause, environmental harm unless the person takes all reasonable and practicable measures to prevent or minimise the harm. Environmental harm includes environmental nuisance. In this regard persons and entities, involved in the civil, earthworks, construction and landscaping phases of this development are to adhere to their ‘general environmental duty’ to minimise the risk of causing environmental harm.
Erosion and Sediment Control
Accepted best practice standards include International Erosion Control Association Australasia Best Practice Erosion and Sediment Control
Qualified Person, for the purpose of erosion and sediment control is a Certified Professional in Erosion and Sediment Control (CPESC) or suitably experienced Registered Professional Engineer of Queensland (RPEQ).
As a general rule, a site is determined to have achieved effective short-term stabilisation if at the time of the final inspection:
Methods of stabilisation are:
appropriate for slopes and slope lengths; and
are consistent with best practice environmental management practices such as in the Manual for Erosion and Sediment Control or the IECA Manual; and
Stormwater runoff from the site is not currently, and is not likely to result in visible evidence of sedimentation or erosion, or lead to water contamination.
Landscaping
Tree Protection Bond:
may be drawn upon by Council if:
the requirements detailed within the approved plans have not been met are not implemented and,
any trees identified for retention are damaged to the point where they cannot be saved (as confirmed by the site Arborist and agreed in writing by Council).
Retention of Existing Trees
The existing trees on adjoining properties must be retained and protected during construction wherever achievable. To avoid doubt, this advisory note is not intended to exclude the operation of Chapter 3 of the Neighbourhood Dispute Resolution Act 2011 following construction of the development which is the subject of this development approval.
Removal of Existing Trees and Vegetation
Stockpiling mulch to the appropriate volume and separation is required for fire mitigation as well as optimum weed seed sterilisation.
Qualified Person
Qualified Person, for the purpose of:
Undertaking rehabilitation construction and establishment works is considered to be a person with five years current experience in revegetation and regeneration.
Managing Fauna protection is considered to be a certified Fauna Spotter Catcher.
Undertaking, supervising tree works and preparing arboriculture certification, is considered to be a person with a minimum three years current experience in tree protection, hazard identification/mitigation and Specifying Trees – a guide to assessment of tree quality (NATSPEC) assessment and either:
International Society of Arboriculture (ISA) certification; or
A Diploma of Arboriculture.
property notes
Not applicable.
VARIATION approval details
Not applicable.
further development permits required
Not applicable.
submissions
Not applicable.
RIGHTS OF APPEAL
You are entitled to appeal against this decision. A copy of the relevant appeal provisions from the Planning Act 2016 is attached.
During the appeal period, you as the applicant may suspend your appeal period and make written representations to Council about the conditions contained within the development approval. If Council agrees or agrees in part with the representations, a negotiated decision notice will be issued. Only one negotiated decision notice may be given.
OTHER DETAILS
If you wish to obtain more information about the decision, electronic copies are available on line at www.noosa.qld.gov.au or at Council Offices.

[word/footer1.xml]
Page 11 of 11

[word/header1.xml]
3

[word/header2.xml]
DEVELOPMENT ASSESSMENT DELEGATED REPORT

[Attachment: image2.jpeg (image text)]
 

 

OP WORKS
'SSUE

 

  

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 
Log in to download the original file

Delegated Report - Code - Planning OPW21 0354.docx · 359 KB (small file)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.