Decision Notice - Change to an Existing Approval [As Published] · 132003.220735.7

of 32

Text shows just the words. Original shows the document exactly as it was published.

                                             Officer:            Kerri Coyle
                                             Direct Telephone:   (07) 5449 5223
                                             Response Address:   PO Box 141, Tewantin QLD 4565
                                             Email:              [email protected]
                                             Our Reference:      23245 DA
                                             Your Reference:
19 September 2008

Elysium Noosa Pty Ltd
CARE Conics (Sunshine Coast) Pty Ltd
PO Box 149
WURTULLA QLD 4575



Dear Madam

                       Change to an Existing Approval
                                  Integrated Planning Act 1997

I refer to your request to make a change to an existing approval. On 16 September 2008 Council
decided your requested changes.
Details of the decision with the consolidated conditions are as follows:

1     APPLICATION DETAILS

 Application No:                 23245 DA
 Street address:                 Sunset Drive, Noosa Heads
 Real property description:      Lots 149 – Lot 189 SP 170964, Lot 500 SP 170964, Lot 900 SP
                                 170964 & Lot 901 SP 170964
 Planning Scheme:                The Noosa Plan

2     DECISION DETAILS

Council on 29 April 2004 decided to grant a Preliminary Approval for the Material Change of Use of
Premises and Reconfiguring a Lot for a residential development comprising 94 dwelling houses and
a group housing development of 96 dwelling units subject to conditions.

In relation to representations made to grant a Development Permit for Material Change of Use and
change a number of the Conditions of Approval, Council on 23 June 2004 resolved to:

A. Grant a Development Permit for Material Change of Use for 93 dwelling houses and group
   housing development of 96 dwelling units and a Development Permit for 99 lots including 93
   conventional lots and 6 group title lots.

B. Approve a change to Conditions 2.1 2.2, 2.3, 2.4, 2.7, 2.10, 3.2, 3.7, 4, 8, 10, 12, 15, 18, 19, 24,
   27, 30, 31, 39, 43, 50, 58, 60, 63, 65, 66, 67, 76, 81, 84, 85, 106, 113, 121, 131, 135, 137, 144,
   145, 148, 150 and 155;

C. Delete Conditions 1, 2.9, 2.11, 2.12, 2.13, 25 and 172.4



                                                                                           Page 1 of 32
Full text of the other 31 pages

Page 2

                                                                                  2003/220735


D. Adopt an amendment of the Planning Scheme to reflect the approval by excluding Lots 1 & 2 RP
   904900 from the Rural Pursuits and Future Urban zones and include Lots 1 & 2 RP 904900 in
   the Special Residential zone and Open Space zone in accordance with the approved plan of
   development, after the approvals take effect.

In relation to a request to change the development approval to a group housing development of 189
dwelling units, Council on 16 December 2004 decided to approve the changes with:-

A. The approved plans to comprise those numbered 6994-24D Revision D prepared by PMM
   Group and dated 29 September 2004, allowing for a residential development comprising a group
   housing development of 189 lots.

B. Changes to Conditions 2, 3.4, 3.5, 12, 65, 81, 85, 88, 121, 137, 144, 145, 154, 155

C. Add conditions 1.11, 2.12, 2.13, 172, 173, 174, 175, 176, 177, 178 and 179

In relation to a request to change the development approval, Council on 25 August 2005 decided to:

A. Approve a change to Conditions 2.8.2, 3.4, 3.7

B. Issue a Compiled Decision Notice

In relation to a request to change the development approval, Council on 28 October 2005 decided to:

A. Approve a change to Conditions 6, 7, 139, 146, 154, 156, 157, 158 and 179

B. Delete Condition 49

C. Include one additional Condition (180)

D. Issue a Compiled Decision Notice

In relation to a request to change the development approval, Council on 13 April 2006 decided to
approve the change with:

A. Amendment to Conditions 2, 2.8.2, 2.10, 2.11, 88 & 133

B. Inclusion of additional Conditions 2.14 & 2.15

C. Deletion of Conditions 2.12, 2.13 and 3.3

D. Issue a Compiled Decision Notice

In relation to a request to change the development approval, Council on 7 April 2008 decided to
approve the change with:

A. Amendment to Conditions 2, 2.3, 4, 12, 65, 81, 121, 137, 144, 145 & 155

B. Issue a Decision Notice – Change to an Existing Approval

In relation to a request to change the development approval, Council on 16 September 2008 decided
to approve the change with:

A. Approve to change Conditions 2, 65, 81, 103, 121, 137, 144, 145 & 155

                                                                                   Page 2 of 32

Page 3

                                                                                     2003/220735


B. Include seven additional conditions

C. Issue a Decision Notice – Change to an Existing Approval

3     RELEVANT PERIOD OF APPROVAL

The relevant period for this Development Approval is identified in the Assessment Manager
conditions.

4     ASSESSMENT MANAGER CONDITIONS

Council Conditions
1. Deleted.
2. The Plan of Development, Drawing No 6994-53M Revision M prepared by Conics and dated 12
   September 2008, shall be amended prior to sealing of the plan of survey in accordance with the
   following:-
    2.1.   No development within 100 m of H.A.T. in Weyba Creek, except the approved public
           pathway, any approved detention basins and the corner of lot 19.
    2.2.   No development or fill in the floodplain (ie below Q100), except the approved public
           pathway, tennis court A and its associated filling/landscaping works (planting), and any
           approved detention basins.
    2.3    Include a visual and noise buffer and east-west environmental link adjacent to the future
           road at the northern end of the site (minimum width 20 m). The noise buffer is to comprise
           mounding and acoustic fencing, with landscape treatment to both sides and shall be
           located within the site in accordance with an approved acoustic report, unless otherwise
           approved by Manager, Land Development.
           A provision shall be included under the table titled “Key Development Requirements for
           Precincts” that buildings on lots 1-5, 9, 10 and 13 shall not exceed 1 storey.
    2.4    The Conservation Parkland shall include all the Macadamia integrifolia tree(s) and
           Symplocos haroldii plants.
    2.5    The Private Recreation Parkland around Lake B shall include the stone pitched weir. It
           shall not be included in Public Open Space.
    2.6    The public pathway shall be located to:
           2.6.1   avoid threatened plant species and endangered plant communities, particularly
                   Community 4 as identified in the Flora and Fauna Assessment;
           2.6.2   avoid clearing in Conservation Parkland;
           2.6.3   avoid wet areas, and
           2.6.4   minimize the number of pathways across steep slopes.
    2.7    Swimming pools, recreational facilities and toilet blocks shall not be located below flood
           level, except for part of tennis court A and the public walkway and limited seating, as
           specified in condition 3.7.
    2.8    The buffer between any site lakes or wetlands and the allotments shall be a minimum of
           20 metres width, with the exception of Lake B (existing lake adjacent lots 166, 167 & 168)
           where a lesser buffer will be accepted subject to the following:-
           2.8.1   Stormwater entering Lake B will be fully treated. i.e. there is no intent to use the
                   lake as part of the water quality treatment train.


                                                                                     Page 3 of 32

Page 4

                                                                               2003/220735


      2.8.2   Lots 166 to 168 will be filled on the lake side to achieve a vertical separation a
              minimum of 2 metres high for lots 166 to 167 and 1.7 metres for lot 168 between
              the lake and the lots, and a childproof fence (AS1926.12-1993) within the lot
              separating the lots from the lake edge. There is to be no direct access from the
              lots to the park and lake.
      2.8.3   The southern side of the lake is to have a vertical lake edge wall, approximately 2
              metres high in the lake, to discourage macrophyte growth. This wall is to extend
              to give approximately 20 metres offset from the lots.
      2.8.4   Landscaping around the southern lake edge above the water line will be dense
              and aimed at discouraging access. Landscaping in areas where walkways come
              close to the lake will be designed to discourage access into the lake.

      2.8.5   Lake is to be desilted and de-weeded as part of the works, which will further
              improve its existing quality.

      2.8.6   Monitoring is to be carried out over the coming summer months, to confirm low
              weed and algal growth.

      2.8.7   The EMP will include an education program for residents discouraging feeding of
              birds. The bird population will also be monitored and contingency measures
              derived should the numbers reach the point where nutrient loads to the lake
              become significant.

      2.8.8   The Stormwater Management Plan is to include contingency measures for weed
              control, emergency mixing and aeration for algal control, harvesting of algae and
              aquatic plants and general lake management.

      2.8.9   The pedestrian bridge across the lake is to have safety railing to prevent small
              children falling / climbing into the lake.
2.9   Deleted.
2.10 Building envelopes shall be identified for all dwelling units within the Group Housing
     Development Precinct, including built to boundary walls. The building envelope shall be in
     accordance with the setback requirements contained within the table of Key Development
     Requirements for this Precinct, and shall provide a minimum side setback of 3 metres
     measured for the building facade to one of the boundaries to ensure open space is
     maintained between each of the dwelling units.
      Where no built to boundary walls are identified by the building envelope on the lot,
      buildings shall be setback a minimum of 1.5 metres measured from the building facade.
2.11 All lots shall have a minimum front setback of 3 metres, with garages setback a minimum
     of 4.5 metres, with minor intrusions permitted of eaves, covered entrances and the like.
     Where a lesser setback than 5.4m is proposed to garages:
      2.11.1 Provision shall be given for visitor parking on the driveway with a minimum length
             of 5.4 metres, measured from the garage and a 3.0 metre separation from the
             back of kerb to the rear of a parked vehicle maintained.
      2.11.2 The sightline requirements to the footpath shall be maintained in accordance with
             AS2890.1-2004, for vehicles parked on the proposed driveways.
2.12 Deleted.
2.13 Deleted.


                                                                               Page 4 of 32

Page 5

                                                                                      2003/220735


    2.14 Where the boundary alignment is non linear or irregular such as cul de sacs, the setback
         shall be calculated as an average distance along the length of the building or garage
         alignment.
    2.15 The minimum rear building setback shall be 2 metres, with minor intrusions permitted for
         eaves and the like.
          Buildings shall be setback a minimum of 6 metres from the Conservation Parkland
          boundary, with minor intrusions permitted of eaves and the like.

          Swimming pools, pergolas, low decks and garden structures shall setback a minimum of 2
          metres from the Conservation Parkland Boundary, with minor intrusions permitted where
          footings do not adversely impact on vegetation within the Conservation Parkland to the
          reasonable satisfaction of the Manager Land Use.
3   The development over the subject land shall comply with the following:
    3.1   All necessary fire protection measures, buffers and devices that are required to protect the
          development from bushfires shall be incorporated within the ‘urban footprint’ and Private
          Open Space.
    3.2   With the exception of Lake A (Detention Basin D) and Detention Basin E and associated
          cut off drain, all necessary stormwater and water quality management and control devices
          associated with the development shall be located within the ‘urban footprint’ or the Private
          Open Space.
    3.3   Deleted.
    3.4   Where roads abut Conservation Parkland, the set back to the edge of road pavement shall
          be in accordance with Drawing No. C5093/05/SK25 Sheet 25 prepared by Tate
          Professional Engineers as received on 18 August 2005 and vegetated to provide a buffer
          to the Conservation Parkland.
    3.5   The minimum width of the Conservation Parkland between Community Group Title Lots
          157, 158, 181, 182 and 183 and the eastern boundary of the property shall be no less than
          10 m at any point.
    3.6   No clearing or removal of native vegetation (other than that specified in the Ecological
          Restoration Plan and the approved plan for the public pathway) shall be undertaken in the
          Conservation Parkland.
    3.7   No development, infrastructure or recreation facilities (eg. Rubbish bins, seats, etc.), shall
          be located in the ‘Conservation Parkland Precinct’, with the exception of the sewerage
          trunk line as shown on Drawing No C5093/05/SK26 prepared by Tate Professional
          Engineers as received on 22 August 2005, approved public pathway and limited seating
          adjacent to the public pathway in the ‘Conservation Parkland Precinct’ where the RL is
          less than 3 metres. Any seating area shall be clearly identified from the vegetated areas
          to prevent adverse impacts.
4   Acoustic buffering shall be undertaken generally in accordance with the Road Traffic Noise
    Assessment Report prepared by Ask Consulting Engineers and dated 25 May 2004 and
    condition 2.3, with all dwellings located on lots 1-5, 9, 10 and 13 to not exceed 1 storey.
    A property note shall be included on the titles of lots 1-5, 9, 10 and 13 noting that construction is
    limited to single storey buildings.
5. Suitable screening shall be provided in proximity to the site’s south eastern corner to prevent golf
   balls being hit into the area.




                                                                                      Page 5 of 32

Page 6

                                                                                     2003/220735


Management Plans

6. The Developer shall prepare various management plans that relate to the design, construction
   and operational phases of the development. These plans are to be prepared by appropriately
   qualified persons and shall be lodged for approval in sequence as outlined in condition 7.
7. The plans are to address specific matters detailed in the Conditions of this approval.
    7.1   The plans to be approved prior to commencement of work on site are:-
              Mosquito, Midge and Cane Toad Management Plan
              Fire Management Plan
    7.2   The plans to be approved prior to the issue of a Development Permit for Operational
          Works are:-
              Environmental Management Plans for Construction Stages
              Ecological Restoration Plan and Specifications
              Landscape Master Plan/Assessment Report
              Lake Design and Management Plan
              Stormwater and Water Quality Management Plan
              Waste Management Plan
              Acid Sulphate Soils Management Plan
    7.3   The plan to be approved within 3 months of commencement of work on site:-
              Environmental Management Plan for Operational Stage
Fees Payable
8. The developer shall pay Council all reasonable costs for the assessment of the management
   plans and also the costs associated with ensuring the development complies with the
   requirements of this approval. These costs shall be limited to a maximum of $25,000 including
   the cost of external consultants should they be required, provided management plans of a
   suitable standard are submitted for assessment.
9. The further approvals required to allow development to occur shall be subject to the fees
   contained in Council’s Fees and Charges Schedule.
Environmental Covenants

10. An environmental covenant as defined by Part 6, Division 4A of the Land Title Act 1994, shall be
    registered in favour of Council on all Community Group titles. The environmental covenants
    shall be for the protection of the site’s environmental values. In particular the covenant(s) shall
    relate to retention of specific vegetation and maintenance of water quality entering the Weyba
    Creek system.
Conservation Parkland
11. The Conservation Parkland shall be dedicated to the Crown at the time of reconfiguration as
    park for conservation and environmental protection purposes.
12. The Conservation Parkland shall include all parts of the Site shown as Conservation Parkland on
    the Plan of Development, Drawing No 6994-53L Revision L prepared by PMM Group and dated
    29 September 2004 and the area required by conditions 2.2 and 2.3.
13. All cleared areas within the Conservation Parkland shall be ecologically restored.

                                                                                     Page 6 of 32

Page 7

                                                                                    2003/220735


14. In order to protect the Conservation Parkland during and after the construction phase, the
    Developer shall construct a permanent fence along all boundaries of the Conservation Parkland
    that abut developed areas (eg. residential areas, roads, the Public Recreation Parkland). The
    fence shall be a minimum of 1.2 m high and ‘fauna-friendly’.
15. The Developer shall provide details about the type and style of fence, construction methods,
    location and type of pedestrian access points, signage to Council specifications, etc. as part of
    the Landscape Master Plan.
16. The Conservation Parkland fence shall be constructed prior to the commencement of any
    construction work on the site.
17. Native trees and vegetation within the Conservation Parkland shall not be felled, removed,
    pruned, lopped, damaged or otherwise adversely affected without written approval from
    Council’s Manager – Environmental Services.
18. No development, infrastructure or recreational facilities (eg. rubbish bins, seats, etc.) shall be
    located in the ‘Conservation Parkland Precinct’, with the exception of the approved public
    pathway and limited seating adjacent to the public pathway in the Conservation Parkland
    Precinct’ where the RL is less than 3 metres. Any seating area shall be clearly identified from
    the vegetated areas to prevent adverse impacts.
19. Those parts of the public pathway located in the Conservation Parkland Precinct above RL 3.0m
    shall be for pedestrian use only. Those parts of the public pathway located in the Conservation
    Parkland Precinct below RL 3.0m shall be designed to accommodate both pedestrians and
    cyclists as well as fire, emergency and maintenance vehicles.
20. Dogs shall be prohibited in the Conservation Parkland.
21. Prior to the Conservation Parkland being dedicated to Council, all the specified ecological
    restoration, weed control, fire control, fencing and pathway work shall be completed to the
    satisfaction of the Manager - Land Use.
Public Pathway
22. The applicant shall provide Council with the following details about the public pathway:
    22.1 location,
    22.2 design,
    22.3 construction,
    22.4 likely future maintenance costs and use levels,
    22.5 likely environmental impacts, and
    22.6 environmental safeguards.
23. All paths, stairs, steps, boardwalks, safety rails and devices, drainage, parking, signs, gates,
    bollards and any other facilities and structures associated with the safe use and management of
    the public pathway and walking track shall be provided by the applicant.
24. The public pathway through the Conservation Parkland Precinct shall be designed, constructed
    and managed in accordance with the requirements of conditions 3.7 and 19.
25. Deleted.
26. Public pathways in the Public Recreation Parkland shall be designed and constructed to
    accommodate both pedestrians and cyclists. Seats, rubbish bins and other recreation facilities
    shall be provided according to Council’s provision standards for recreational parkland.
27. The public pathway shall not be located through, or near, any stands of Symplocos haroldii or
    Macadamia integrifolia. The location of the public pathway in the vicinity of threatened plants
    shall be determined by Council’s Vegetation Management Officer.
                                                                                     Page 7 of 32

Page 8

                                                                                     2003/220735


28. Sufficient parking shall be provided within the residential areas to accommodate the vehicles of
    people using the public pathway or walking track through the Public Esplanade.
Fish Habitat Area
29. Public viewing platforms and walking tracks shall not be constructed on or near Weyba Creek or
    within the Fish Habitat Area.
30. The applicant shall provide signs to Council specifications and any other management devices
    (eg fences) necessary for the protection of the environmental values of the adjacent Esplanade,
    particularly the Fish Habitat Area.
Stone Pitched Weir on Lake B
31. No construction shall occur within 10m of Community 3 or Community 4 as identified in the Flora
    and Fauna Assessment in the Conservation Parkland.
32. The proposed stone weir for Lake B shall be located wholly within the Private Recreation
    Parkland area that encompasses Lake B. It shall not encroach into the Public Recreation
    Parkland or Conservation Parkland.
33. The proposed stone pitched weir for Lake B shall be located, designed, constructed and
    operated so that the adjacent plant communities that are classified as ‘Endangered’ are not
    directly or indirectly affected.
Vegetation Removal, Disposal and Protection in the residential area and Private Recreation
Parkland
34. Vegetation removal, tree felling and lopping shall be undertaken in an environmentally sensitive
    manner to avoid damaging surrounding vegetation, trees and habitat.
35. Prior to felling or lopping all trees are to be checked for wildlife (eg. koalas, cockatoos,
    possums). If wildlife species are present, the tree shall not be felled or lopped until the wildlife
    has left the tree.
36. All cleared vegetation shall be suitably processed or removed from the site by a method
    approved by Council.
37. Environmental weed species cleared from the site shall not be mulched. Vegetation material
    from environmental weed species shall be removed from the site and disposed of in a Council
    approved refuse tip.
38. Burning off is not considered an acceptable means of disposal and is not to take place.
39. During construction, the boundaries of areas of retained and protected vegetation within the
    development area shall be clearly marked for the purpose of preventing access into these areas
    thereby protecting the vegetation and habitat values.
40. All underground services, drainage, footpaths, bike paths, roads and other site works shall be
    located to minimize adverse impacts on retained vegetation, particularly their root systems.
41. Vegetation and individual trees retained in the residential areas and recreation parkland shall be
    healthy and vigorous with an expected life span of at least 50 years. A risk assessment by a
    qualified arborist shall be undertaken on all individual trees and stands of vegetation to be
    retained within the residential areas and recreation parkland. An arborist’s written report shall be
    included in the relevant Operational Works applications.
Weed and Pest Species Control
42. Weed control shall be undertaken in general accordance with the Construction Management
    Plan, dated August 2003, prepared by Tate Professional Engineers.



                                                                                      Page 8 of 32

Page 9

                                                                                      2003/220735


43. All Class 2 and Class 3 weeds declared under the Land Protection (Pest and Stock Route
    Management) Act 2002 and Regulations 2003 and all environmental weed species listed in
    Noosa Council’s Pest Management Plan 2002 shall be eradicated, prior to reconfiguration. The
    Manager – Environmental Services will nominate specific weed eradication strategies to be used
    on the site.
44. Prior to entering the site, all construction machinery and vehicles shall be washed down to
    remove soil that may contain weed seeds, soil pathogens and pest species.
45. All nursery stock shall be weed, pest and disease free and certified as such by the supplier. The
    certificates are to be obtained prior to the commencement of any landscaping works on site and
    shall be made available to Council upon request.
46. All mulch produced on site by mulching cleared vegetation and trees shall specifically exclude
    material (particularly seeds) from environmental weed species (eg. lantana, asparagus and
    umbrella trees).
47. Soil disturbance shall be kept to a minimum to avoid weed proliferation.
48. The eradication and control of environmental weeds will be an integral part of both the Ecological
    Restoration Plan and the Landscape Plans. Vegetation used in restoration work and
    landscaping shall exclude environmental weed species.
49. Deleted.
Cultural Heritage
50. In advance of any construction activities commencing, limited archaeological test excavations
    should occur at Site 1 and Site 2 as identified in the approved Archaeological Report to
    investigate the extent and nature of archaeological material (surface and sub-surface) present.
    The minimum excavation unit should be 1 metre by 1 metre. The excavated soil should be
    sieved through 6mm (minimum size) mesh sieves and when considered warranted Indigenous
    archaeological material encountered should be retained for analysis. If not retained for analysis,
    the material should be fully documented on site. When the excavation is completed all
    excavated material that is not retained should be redeposited back into the excavation unit.
51. On the areas of elevated terrain in the southern and central sections of the study area
    mechanical excavations should be undertaken. These excavations should be undertaken with a
    mechanical excavator such as a Toyota 3 Series Bobcat with rubber types and a 1250mm
    scoop. The excavation unit should be around one metre wide and a minimum of two metres
    long. The soil should be scrapped away in 5cm sections and the soil passed through 6mm
    (minimum size) mesh sieves. When considered warranted, Indigenous archaeological material
    encountered should be retained for analysis. If not retained for analysis, the material should be
    fully documented on site. When the excavation is completed all excavated material that is not
    retained should be redeposited back into the excavation unit.
52. The excavations should be undertaken by a qualified archaeologist under a permit (Permit to
    Excavate / Collect Items of the Queensland Estate) issued by the Environmental Protection
    Agency. The excavations should be undertaken with the approval and assistance of the Gubbi
    Gubbi and Undumbi People.
53. At the completion of the excavations, the results should be documented and significance
    assessment and management recommends for each Site and Location provided. A cultural
    heritage management plan should be formulated after the results of the excavations have been
    documented.
54. The recommendations provided by both the Gubbi Gubbi and Undumbi should be taken into
    consideration.
Koalas and Koala Habitat Protection
55. Koalas and their habitat require special protection and particular consideration shall be given to:
                                                                                      Page 9 of 32

Page 10

                                                                                     2003/220735


    55.1 the protection and restoration of koala habitat, habitat linkages and corridors on the site as
         shown on the Wildlife Corridor figure in the Landscape Assessment Report,
    55.2 the protection and restoration of existing and new vegetation to facilitate Koala movement
         throughout the entire site,
    55.3 the protection of Koalas during the construction and operational phases of the
         development, and
    55.4 the planting of additional koala food and habitat tree species during landscaping and
         ecological restoration of the site.
56 All known Koala habitat trees on the site shall be protected, unless specific approval exists for
   their removal or lopping.
57 Rehabilitation/re-establishment of the Koala habitat and habitat links within the site shall be
   given priority in the Ecological Restoration Plan and the Landscape Plans.
58 All swimming pools shall have a rope installed to allow Koalas to exit the pool or be fitted with
   Koala-proof fencing.
Protection of Fauna
59 Fauna protection during construction shall be undertaken in general accordance with the
   Construction Management Plan, dated August 2003, prepared by Tate Professional Engineers.
60 Nesting boxes of a range of sizes shall be installed in nominated trees within areas of the private
   open space. The number, type, size, location and purpose of the nesting boxes is to be
   specified. The manner in which these nesting boxes are to be maintained shall be specified.
   Nesting boxes shall not be located in the Public Open Space areas.
61 Nesting boxes of a range of sizes shall be installed in nominated trees. The number, type, size,
   location and purpose of the nesting boxes is to be specified. The manner in which these nesting
   boxes are to be maintained shall be specified.
62 Buildings, roads and fences shall be sited and constructed to allow movement of fauna through
   and within the site.
63 No domestic pets shall be permitted on the subject land during construction. Thereafter, no
   domestic pets shall be permitted in the Conservation Parkland.
Ecological Restoration Plan and Specifications for the Conservation Parkland
64 An Ecological Restoration Plan and Specifications shall be prepared by a specialist Restoration
   Ecologist, to the reasonable satisfaction of the Council. It shall identify all the areas within the
   Conservation Parkland that require ecological restoration and specify actions and works
   necessary to result in robust, self-sustaining, viable plant communities and habitat.
65 The Ecological Restoration Plan and Specifications shall include all parts of the site shown as
   Conservation Parkland on the Plan of Development Drawing No 6994-53M Revision M prepared
   by Conics and dated 12 September 2008.
66 The following, inter alia, shall be addressed and included in the Plan and Specifications:
    66.1 Formulate structural and floristic models for Communities 1, 2, 3 and 4 as identified in the
         Flora and Fauna Assessment;
    66.2 document the current status of the areas requiring ecological restoration in terms of
         structure, floristics, missing elements, health, vigour, etc.;
    66.3 specify the required works and actions for each area in terms of:
          66.3.1    site preparation (this may include thinning, grass removal, weed removal and
                    control, etc.),

                                                                                    Page 10 of 32

Page 11

                                                                                      2003/220735


          66.3.2    establishment of the missing floristic and structural elements,
          66.3.3    creating opportunities for regeneration from the seed bed, natural recruitment
                    and the establishment of wildlings,
          66.3.4    habitat creation and reinforcement for native fauna and reinforcement of habitat
                    linkages and corridors,
          66.3.5    planting and mulching procedures,
          66.3.6    fertilizing procedures,
          66.3.7    watering procedures,
          66.3.8    protection from wildfire, particularly during the establishment phase,
          66.3.9    erosion and sediment control,
          66.3.10   on-going maintenance,
          66.3.11   environmental safeguards, and
          66.3.12   incorporation of the relevant requirements of all the management plans required
                    by this approval, particularly the Environmental Management Plan.
67 The contract for the Ecological Restoration work shall specify a 4-year maintenance period from
   the date restoration works are completed by the contractor, by which time the ecologically
   restored areas should be self-sustaining. It shall also be weed-free to the satisfaction of the
   Manager, Environmental Services.
68 All the relevant ecological restoration works and actions shall be undertaken by the Developer
   and completed prior to dedication of Conservation Parkland to Council.
Landscape Master Plan
69 Prior to approval for a Development Permit for Operational Works, a Landscape Master Plan
   shall be prepared, to the reasonable satisfaction of Council, for all the residential and recreation
   areas. It shall generally be in accordance with the EDAW Gillespies ‘Landscape Assessment
   Report’ (dated 23 August 2003). However, it shall incorporate all amendments to the Plan of
   Development and address all relevant Conditions of Approval.
70 The Landscape Master Plan shall:
    70.1 specifically exclude areas designated as ‘Conservation Parkland’. (These areas are dealt
         with in the Ecological Restoration Plan), and
    70.2 incorporate all relevant requirements of, and be consistent with, all other Management
         Plans required by this Approval.
71 The Landscape Master Plan shall detail the planting schemes and shall detail, inter alia:
    71.1 areas of natural vegetation to be retained;
    71.2 site preparation;
    71.3 habitat enhancement for native fauna;
    71.4 weed removal and control;
    71.5 species ‘palettes’ and schedules;
    71.6 planting out procedures and horticultural requirements;
    71.7 mulching procedures;
    71.8 fertilising procedures;
    71.9 irrigation and watering procedures;
                                                                                      Page 11 of 32

Page 12

                                                                                     2003/220735


    71.10 erosion and sediment control;
    71.11 on-going maintenance;
    71.12 construction materials and details;
    71.13 environmental safeguards.
72 Landscaped areas shall be integrated floristically and structurally with the surrounding native
   vegetation. To be consistent with the ecologically sustainable design philosophy embodied in
   the Application, at least 85% of all plant species used and at least 85% of the total number of
   plants used in the landscaping shall be indigenous to the site. All other species shall be
   consistent with Council’s Landscaping Guidelines – Planning Scheme Policy PSP1.
73 The Landscape Master Plan shall address, inter alia, the following issues:
    73.1 enhancement of environmental linkages and corridors;
    73.2 enhancement and establishment of fauna habitat, particularly for Koalas and Glossy Black
         Cockatoos;
    73.3 visual screening of buildings and visual integration of the built environment.
74 All detailed landscape plans for individual lots or parts of the developments that are submitted
   for Development Permits for Operational Works shall comply with the Landscape Master Plan.
Fire Management Plan
75 Prior to approval for a Development Permit for Operational Works, a Fire Management Plan
   shall be prepared to the reasonable satisfaction of Council. It shall generally be in accordance
   with the Fire Management Strategy prepared by 4 Site (dated 29 August 2003). However, it
   shall incorporate all amendments to the Plan of Development and address all relevant
   Conditions of Approval.
76 The Fire Management Plan shall also include:
    76.1 landscaping measures to reduce fire risk,
    76.2 the requirement for a building set-back of at least 6 m on all lots adjacent to existing and
         restored native vegetation,
    76.3 a firebreak through the area of floodplain to be revegetated (ecologically restored) located
         along the entire length of the conservation parkland,
    76.4 for all allotments that abut native vegetation, the requirement to provide a garden tap in
         close proximity to the native vegetation for the purposes of reducing bushfire risk unless
         otherwise required by an approved Fire Management Plan, and
    76.5 all relevant requirements of, and be consistent with, all other Management Plans required
         by this Approval.
77 The Fire Management Plan shall demonstrate a high level of environmental care and
   responsibility and be consistent with best practice for developments of this type in similar
   environments.
78 The Fire Management Plan shall meet the provisions of the Queensland Fire and Rescue
   Authority Act 1990 and shall be endorsed by the Queensland Fire & Rescue Authority.
79 The Developer shall provide a bushfire information kit to all Bodies Corporate and all purchasers
   of allotments adjacent to native vegetation. The bushfire information kit shall be submitted to
   Council for approval as part of the Fire Management Plan.
80 The Fire Management Plan is to be implemented by the Developer and future owners of the site
   and is to be referenced in any community management statement(s).

                                                                                    Page 12 of 32

Page 13

                                                                                       2003/220735


Lake Design and Management
81 Lake A and Lake B and their environs shall be designed and managed in accordance with the
   Lake Design and Management Report by 4Site (dated August 2003) and the associated
   supplementary material provided by 4Site on 24 February 2004 and is to be consistent with the
   Plan of Development, Drawing No 6994-53M Revision M prepared by Conics and dated 12
   September 2008, amended as follows:
    81.1 Minimum separation distance from the lake edge to any lot boundary shall be 20m, with
         the exception of Lake B (existing lake adjacent lots 166, 167 & 168) where a lesser buffer
         will be accepted in accordance with Conditions 2.8.1 to 2.8.9.
    81.2 The lake shall be designed and managed to minimise the creation of breeding habitat for
         cane toads.
82 The construction and operation of the stone-pitched weir on Lake B shall not adversely affect the
   adjacent forested areas (Community 3 and Community 4 as identified in the Flora and Fauna
   Assessment).
83 The stone-pitch weir for Lake B shall be included within the Private Open Space area.
84 Discharges from Lake A and Lake B shall be controlled and managed so as not to adversely
   affect downstream vegetation or aquatic ecosystems or cause erosion and shall incorporate
   appropriate flow spreading and energy dissipation devices.
Tennis Court on fill at south end of site
85 Recreational tennis court C shall be designed and constructed so that the finished level is above
   RL 3.1 m and does not impact on the adjacent steep slope or native vegetation. It shall be
   limited to the existing cleared and filled area, provided they have Q100 immunity and it is on the
   hill edge away from the creek. Access to Tennis Court C shall be limited to one pedestrian
   pathway, which is the public pathway.
    Tennis court A shall be constructed at RL 2.0m AHD.
86 Access to the tennis court shall be limited to one pedestrian pathway. The pathway across the
   steep slope shall be designed to have minimal impact on the vegetation and slope stability.
87 The banks of the filled area shall be landscaped to provide visual screening.
88 Toilet facilities are not permitted for Tennis Court C. Toilet facilities proposed for Tennis Court A
   shall be 500mm above the defined Q100 flood level.
Environmental Management Plans
89 Prior to approval for a Development Permit for Operational Works, an Environmental
   Management Plan for:
    89.1 the Construction Stage, and
    89.2 the Operational Stage
    89.3 of the project shall be prepared to the reasonable satisfaction of Council.
90 These Environmental Management Plans shall be prepared and implemented to ensure that the
   impact of the development on the environment is minimised and that the environmental values of
   the site are protected and enhanced. The EMPs are to:
    90.1 comply with AS00014, and
    90.2 demonstrate a high level of environmental care and responsibility and be consistent with
         best practice for developments of this type in similar environments.



                                                                                     Page 13 of 32

Page 14

                                                                                      2003/220735


Construction Environmental Management Plan
91 The Construction Environmental Management Plan shall generally be in accordance with the
   Construction Management Plan prepared by Tate Professional Engineers, dated August 2003.
   However, it shall incorporate all amendments to the Plan of Development and address all
   relevant Conditions of Approval.
92 The Construction Environmental Management Plan shall also:
   92.1 reference all relevant Council Local Laws and Policies (eg. Trade Waste Policy, Local Law
        10 – Vegetation Management, Draft Koala Management Plan, etc.),
   92.2 reference all relevant Legislation (eg. Nature Conservation Act & Regulations, Queensland
        Heritage Act, etc.),
   92.3 include a specific section on vibration nuisance and management,
   92.4 include a specific section on Trade Waste and recycling waste in accordance with
        Council’s Trade Waste Policy,
   92.5 include a specific section on the storage and handling of hazardous wastes,
   92.6 include a specific section on acid sulphate soil management,
   92.7 include a specific section on lake construction and management, and
   92.8 incorporate the specific requirements of Cultural Heritage Management Plan prepared by
        Davies Heritage Consultants.
93 Environmental Procedure EMP-EPO14 shall include reference to, and be consistent with, the
   Ecological Restoration Plan, the Landscape Master Plan and the Lake Design and Management
   Plan. All of these plans will specify:
   93.1 weed control methods and standards, and
   93.2 plant species to be used.
94 The Construction Environmental Management Plan shall apply to all works and activities
   undertaken on any area of the site.
95 The Construction Environmental Management Plan shall incorporate the requirement for
   monthly environmental compliance monitoring reports and annual audit reports to be submitted
   to Council during the construction stages of the development. The format and content of these
   reports shall be in hard copy and digital form, generally in accordance with the following:
   95.1 include tables of the monitoring results (digital form should be in Excel);
   95.2 include individual charts plotting the results for all parameters required in the monitoring;
   95.3 include a brief written discussion of the results and recommend any necessary actions.
Operational Stage Environmental Management Plan
96 An Operational Stage Environmental Management Plan shall be prepared to give guidance to
   the future Bodies Corporate for the community Group Title areas regarding appropriate
   environmental protection and management for the site.
97 The Operational Stage Environmental Management Plan shall address, inter alia,
   97.1 stormwater and water quality management;
   97.2 sediment and erosion control;
   97.3 management of the lake;
   97.4 management of landscaped areas;
   97.5 management of existing native trees and vegetation in residential areas;
                                                                                      Page 14 of 32

Page 15

                                                                                     2003/220735


    97.6 weed and pest control (particularly mosquitoes and cane toads);
    97.7 management of Private Open Space areas;
    97.8 protection of wildlife and their habitat;
    97.9 bushfire prevention and control and include the Bushfire Information kit;
    97.10 management and control of domestic pets,
    97.11 energy efficient living;
    97.12 management and maintenance of water conservation facilities (eg. rainwater tanks).
98 The Operational Stage Environmental Management Plan shall incorporate all amendments to
   the Plan of Development and address all relevant Conditions of Approval. It shall also reference
   all relevant Local Laws and Policies and legislation.
99 The developer and all future owners of the site shall comply with the Operational Stage
   Environmental Management Plan and compliance with it shall be referenced in any community
   management statement for any group title development over the site.
Sediment and Erosion Control Plan
100 Detailed staged Sediment and Erosion Control Plans shall be prepared for the site, to the
    reasonable satisfaction of Council, and in accordance with the Institution of Engineers Australia
    ‘Engineering Guidelines for Queensland Soil and Sediment Control’ (June 1996) and in
    particular using Checklist No. 3 from that document. The Sediment and Erosion Control Plans
    shall cover all development on site (during the construction and operational stages), ecological
    restoration, landscaping and remediation works.
101 The Sediment and Erosion Control Plans shall also apply to all areas of Open Space and shall:
    101.1 identify existing erosion problems, and
    101.2 specify appropriate remedial actions.
102 All necessary erosion and sediment control works and devices shall be provided by the
    Developer.
Stormwater and Water Quality Management Plan
103 Prior to approval for a Development Permit for Operational Works, a Stormwater and Water
    Quality Management Plan for the site shall be prepared to the reasonable satisfaction of Council.
    It shall generally be in accordance with the Stormwater Management Plan prepared by 4 Site
    (dated August 2003) amended in accordance with 4Site’s letter to Council of 6 November 2003
    and their letter of 24 February 2004 and to be consistent with the amended plan of development
    by Conics dated 12 September 2008. However, it shall incorporate all amendments to the Plan
    of Development and address all relevant Conditions in this Approval.
104 The Stormwater and Water Quality Management Plan shall take into account matters specified
    in section 19.4 of the Environmental Protection (Water) Policy 1997.
105 Key water quality objectives to be reflected in the Stormwater and Water Quality Management
    Plan are for the protection of aquatic ecosystems in the lake and wetlands of the site and the
    receiving waters of Weyba Creek.
106 The Stormwater and Water Quality Management Plan shall comply with and address, inter alia,
    the following issues in relation to the construction, establishment and operational stages of the
    development.
    106.1 With the exception of the two approved detention basins located on the floodplain, all
          necessary stormwater treatment and water quality devices associated with the
          development shall be located within the ‘urban footprint’. They shall not be located in
          ‘Conservation Parkland’.
                                                                                     Page 15 of 32

Page 16

                                                                                   2003/220735


106.2 During the construction stage, weekly inspections, monthly water quality monitoring and
      monitoring after significant rainfall events (at least two per year) shall be undertaken for:
      106.2.1    suspended solids and turbidity,
      106.2.2    temperature,
      106.2.3    salinity,
      106.2.4    total nitrogen,
      106.2.5    total phosphorous,
      106.2.6    pH,
      106.2.7    trash and gross pollutants, and
      106.2.8    dissolved oxygen.
106.3 During the establishment and operational stages, water quality monitoring shall be
      undertaken every third month and monitoring after significant rainfall events (at least two
      per year) shall be undertaken for:
      106.3.1    total nitrogen,
      106.3.2    total phosphorous,
      106.3.3    suspended solids and turbidity,
      106.3.4    pH,
      106.3.5    salinity,
      106.3.6    temperature,
      106.3.7    dissolved oxygen,
      106.3.8    trash and gross pollutants,
      106.3.9    algal count and identification, and
      106.3.10 faecal coliforms.
106.4 The Developer shall continue this water quality monitoring for a period of 3 years from
      completion of the final stage of construction. In addition, the Developer shall undertake
      inspections for erosion and deposition, the build-up of trash and gross pollutants, and
      other water pollution. These inspections will be carried out every third month as well as
      after significant rainfall events, for a period of 3 years from completion of the final stage of
      construction.
106.5 An operational stage Water Quality Management Plan shall be prepared to address water
      quality performance targets, water treatment devices, water quality maintenance,
      requirements for stormwater management measures and devices, contingency measures
      for aquatic plant growth, loss of vegetation in swales and filter strips, pollution response
      and algal blooms. It shall also include a mosquito management strategy and a cane toad
      management strategy. The plan shall demonstrate compliance with the prescribed water
      quality objectives. This Water Quality Management Plan shall be incorporated into the
      Operational Stage EMP.
106.6 Responsibilities shall be clearly delineated.
106.7 Non-compliance with prescribed water quality standards will trigger the implementation of
      measures to rectify the problem(s).




                                                                                  Page 16 of 32

Page 17

                                                                                      2003/220735


    106.8 During construction and establishment stages, monthly reports on monitoring, incidents,
          corrective action and plan updates shall be submitted to Council. These reports shall be
          submitted in a form acceptable to Council and shall highlight any non-standard results.
          The format and content of these reports shall be in hard copy and digital form, generally in
          accordance with the following:
          106.8.1   including tables of the monitoring results (digital form should be in Excel);
          106.8.2   include individual charts plotting the results for all parameters required in the
                    monitoring (digital form should be in Excel);
          106.8.3   include a brief written discussion of the results and recommend any necessary
                    actions.
Water Quality Devices
107 The Developer shall install water quality control devices generally in accordance with the
    Stormwater and Water Quality Management Plan. Detailed staging plans and specifications,
    based on and generally in accordance with the Plan shall be prepared and submitted (after
    consultation with officers of the Council) with the relevant applications for operational works.
108 Detention Basins D & E shall be constructed and operated in a manner that does not adversely
    affect flood levels elsewhere on the floodplain, cause environmental harm or impact upon the
    adjacent wetland, tidal or intertidal areas.
Drainage Works
109 The Developer shall complete the drainage works progressively in conjunction with development
    of the site and generally in accordance with the approved Stormwater and Water Quality
    Management Plan. Detailed drainage plans and specifications, based on and generally in
    accordance with the approved Drainage Plan, the Construction EMP and these Conditions, shall
    be prepared and submitted (after consultation with officers of the Council) with the relevant
    applications for operational works.
110 All drainage works as required by the Drainage Plan shall be provided by the Developer at its
    own cost.
Acid Sulfate Soils Management Plan
111 Prior to approval for a Development Permit for Operational Work for any component or stage of
    the development, an Acid Sulfate Soils (ASS) Management Plan shall be provided for any
    excavation works undertaken in areas below 5m AHD. The Management Plan shall outline the
    ASS investigations undertaken and the management procedures to be undertaken in that part of
    the site in accordance with State Planning Policy 2/02 ‘Planning and Managing Development
    Involving Acid Sulfate Soils’.
112 The Acid Sulphate Soils Management Plans for each component or stage of the development
    shall generally be in accordance with the Acid Sulphate Soil Investigation Report for the whole
    site, prepared by Soil Surveys (dated July 2003).
113 At the group title components of the site the developer shall provide for refuse collection
    arrangements that are in accordance with an approved Refuse Management Plan. Where there
    are any communal refuse collection points a suitably screened wash down area is required with
    a cold-water tap, hose and drain outlet connected to sewer. The drain outlet is to be designed to
    prevent stormwater entry to the sewerage system.
114 Street litter bins to a design approved by Council, shall be supplied and installed at the
    developers expense at agreed locations.
115 An approved waste management plan must be approved by Council’s Manager of
    Environmental Health prior to the commencement of operational works.
    The existing plan dated 29 August 2003 is deficient in adequate details of:
                                                                                     Page 17 of 32

Page 18

                                                                                       2003/220735


    115.1 collection areas for refuse and recycle bins for the group title areas.
    115.2 bin wash facilities for group title areas.
    115.3 location and servicing of public street letter bins at parks, pool, jetty and other areas of the
          site.
116 Swimming pool or spa pumps are to be contained in an acoustically treated enclosure or located
    in a manner which prevents a noise nuisance beyond the subject land in accordance with the
    nuisance provisions of the Environmental Protection Regulation 1998. On the spot fines apply
    for such offences.
117 Noise emission from air conditioning equipment shall comply with the following requirements:
    117.1 The equipment shall be installed and located in a manner which prevents noise nuisance
          beyond the subject land in accordance with the nuisance provisions of the Environmental
          Protection Regulation 1998 and Council’s Local Law No. 12 - Control of Nuisances.
          Infringement Notices (on-the-spot fines) may apply for offences.
    117.2 Submission of written certification from a suitably qualified person confirming that the noise
          levels comply when measured at the nearest residential boundary. This is required
          immediately after installation of the equipment and prior to any occupation of the building,
          and in a format approved by Council.
    117.3 A person must not use equipment on any day if it makes or causes noise to be made –
          117.3.1    Before 7am or after 10pm: More than the lower of either –
                   40 d(B)A
                   3 d(B)A above the background noise level
          117.3.2    From 7am to 7pm: More than the lower of either –
                   50 d(B)A
                   5 d(B)A above the background noise level
          117.3.3    From 7pm to 10pm: More than 3 d(B)A above the background noise level.
118 As the proposal is to be located in close proximity to residential areas, a Noise Exposure
    Forecast/Plan from an acoustic consultant shall be submitted with respect to possible noise
    emissions during construction. This Forecast/Plan must include the following:-
    118.1 The measures to be taken under the plan to minimise the adverse effects of the operations
          on the environmental values;
    118.2 Persons responsible for carrying out each of the measures;
    118.3 Maximum, Leq, L10, L90 and background levels for the operations;
    118.4 Noise monitoring to be undertaken for the operations;
    118.5 Processes for dispute resolution that the applicant must follow to deal with complaints
          received about the impact of the noise from the operations;
    118.6 How compliance with the Environmental Protection Regulation 1998 for noise emissions is
          to be achieved.
119 Adequate control measure must be implemented by the Body Corporate to control noise and
    lighting emissions from the tennis courts
Land Development
General
120 For the purpose of these conditions, the following definitions apply: -
                                                                                      Page 18 of 32

Page 19

                                                                                     2003/220735


    120.1 A Plan of Survey means the plan for the reconfiguration of a lot required to be endorsed
          by Council pursuant to S3.7.1 of the Integrated Planning Act 1997.
    120.2 A Registered Professional Civil Engineer means an engineer who is registered with the
          board of Professional Engineers of Queensland..
    120.3 Carparking area means a parking area as defined in the Schedule to the Shire of Noosa
          Planning Scheme inclusive of manoeuvring areas and access from the roadway.
    120.4 The person acting on this permit means any person or company who undertakes
          development pursuant to this permit.
    120.5 AS 2890.1 – 1993 means Australian Standard for Off Street Carparking - AS 2890.1-1993.
    120.6 Principal Contractor means the person nominated by the Applicant and approved by the
          Manager - Land Development at a pre-start meeting as being responsible for the major
          component of works associated with a Development Permit for Operational Works of any
          works on the site.
121 The lot reconfiguration shall be in accordance with Drawing No 6994-53M Revision M prepared
    by Conics and dated 12 September 2008 as modified herein.
122 Pursuant to Section 3.5.21(6) of the Integrated Planning Act 1997, the currency period is four (4)
    years from the day this permit takes effect during which time all conditions must have been
    complied with, operational works completed, and the Plan of Survey lodged with the Council for
    endorsement.
123 In conjunction with the lodgement of the Plan of Survey for Council endorsement, legal
    documentation shall be presented to Council and shall be submitted in the correct form with the
    fees prescribed in Council's adopted fee schedule.
124 Pursuant to Section 3.7.3(b) of the Integrated Planning Act, all outstanding rates and charges
    due and payable to Noosa Council in respect of the lots being reconfigured shall be paid prior to
    endorsement of the Plan of Survey for each stage.
125 An underground electricity service shall be provided to each lot if not already provided.
    In this regard, an approved ENERGEX Electrical Design Consultant shall work in conjunction
    with Council’s Manager - Works Support to prepare detailed designs of the electrical proposal.
    The detailed deigns shall then be submitted to ENERGEX for approval and a copy of their
    approval submitted to Council in conjunction with a “Certificate of Electricity Supply for Proposed
    Subdivisions” (prepared by an approved ENERGEX Electrical Design Consultant) prior to
    Council endorsing the Plan of Survey.
    Any agreement with ENERGEX or an approved ENERGEX Electrical Design Consultant shall be
    wholly at the applicant’s expense and shall not entail a financial encumbrance on future
    purchasers of the proposed lots.
    Street lighting and pathway lighting throughout the subdivision shall have a high energy efficient
    rating to the reasonable satisfaction of Council and shall generally be provided in accordance
    with the principles of Council’s Engineering Design Standards, section 11.3.3.
126 The requirements for TELECOMMUNICATION services shall be satisfied in relation to the
    provision of new telephone services to the proposed lots. In this regard written confirmation
    from an approved telecommunication agency shall be submitted to the Council prior to Council
    endorsing the Plan of Survey.
127 Prior to undertaking any excavation, the person acting on this permit shall contact public utility
    service providers to ascertain the location of their underground services.



                                                                                    Page 19 of 32

Page 20

                                                                                    2003/220735


128 The person acting on this permit shall apply and obtain for all other necessary permits including
    crane permits, road opening permits, hoarding permits, footpath occupation permits and/or any
    other approvals required under any other Act.
129 Prior to commencement of work relating to a Development Permit for Operational Works, the
    Applicant shall sign a written undertaking to be responsible for the full cost of repairs to road
    pavement, footpath, kerb and gutter, or other Council property damaged as a result of
    construction of the proposed development.
    If any person acting under this permit damages any Council property or facilities (such as
    underground drainage, water supply and sewerage) , through any cause whatsoever in the
    course of, directly or indirectly carrying out development, that person shall forthwith notify the
    Manager - Land Development and shall forthwith rectify that damage at its cost and to the
    satisfaction of the Manager - Land Development. Alternatively, the Applicant may request the
    Council to carry out the rectification works.

    Any damage to a water main shall be rectified by Council. Any damage to a sewer main shall be
    undertaken by either Council or a Council approved contractor.

    In all cases, Council reserves the right to carry out rectification works in an emergency and
    where no reasonable attempt has been made to complete the rectification works as part of the
    development.

    All costs incurred by Council in any rectification works shall be repaid to Council prior to the
    endorsement of the Plan of Survey.

Minimum Habitable Floor Levels
130 All buildings proposed on site (and areas utilised for carparking purposes associated with the
    buildings) shall be constructed to comply with Council’s Minimum Floor Height requirements as
    defined in Council’s Planning Scheme and on Council’s Scheme Maps at the time of issue of the
    Building Permit.
    In this regard and as an indication only – the site should have a Minimum Floor Height of RL 2.5
    (AHD). These levels however are subject to change and verification shall be made to Council’s
    Land Development Section prior to obtaining a Development Permit for Building Works.

Vehicle Access
131 Vehicle access shall be provided to and within the site generally as shown on drawing number
    C5093/03/L4a Preliminary Street Network Plan dated 12/08/03 by Tate Professional Engineers.
    Access arrangements will be amended if required when the amended Plan of Development is
    accepted by Council.
132 The access to Lot 100 is to be located 30 metres from the holding line of the roundabout at Road
    R1-R3 intersection.
133 A vehicular access driveway shall be designed and constructed from the street frontage of the
    site for each lot in accordance with the following:
    133.1 A minimum width of 3 metres and a maximum width of 4.5 metres outside the property and
          6 metres inside the property.
    133.2 Consideration given to nearby traffic calming devices and provide sufficient separation to
          road intersections, in accordance with Austroads Part 5, Intersections at Grade.
    133.3 Council’s design standards and to grades that prevent vehicles from scraping and/or
          bottoming. Should any driveways be constructed to grades that do not comply with
          AS2890.1-2004, Council will require that the driveway be removed and reconstructed to
          levels that do comply.
                                                                                   Page 20 of 32

Page 21

                                                                                   2003/220735


          The Community Management Statement shall include the requirement for vehicles to be
          parked so that they do not protrude more than 5.4 metres from the garage doors and do
          not protrude within 3 metres of the back of kerb.

Carparking
134 On Street parking spaces shall be located on the opposite side of the road to that of the swale
    drains. In the case R6 where the swale drain is located on the same side of the road to the
    indented parking, a piped system shall be provided.
135 Carparking shall be provided within the site as shown on drawing number C5093/03/L4a
    Preliminary Street Network Plan dated 12/08/03 by Tate Professional Engineers, except as
    modified herein.
136 The carparking area shall be designed to comply with the provisions of AS 2890.1-1993 for user
    class 3.
Roads
137 Road shall be constructed in accordance with the widths set out in Council’s Engineering
    Standards with the exception of Road R3 which may be constructed to a width of 8 metres kerb
    to kerb. Road reserve widths shall be in accordance with Drawing No 6994-53M Revision M
    prepared by Conics and dated 12 September 2008.
138 Roads widths within the Group Housing areas will be set prior to the issue of a development
    permit for these areas.
Roadworks Contributions
139 A roadworks contribution of $2,711.45 per additional lot for each stage towards the Coastal
    Major Road Network shall be paid to the Council prior to endorsement of the Plan of Survey for
    the stage. This amount will be subject to variations in the Price Index, All Groups Brisbane from
    September 2003 until the date of payment.
Frontage Works
140 Footpath improvements such as topsoiling, grassing, and tree planting are required to all street
    frontages in accordance with Planning Scheme Policy PSP1 Landscaping Guidelines. Grass
    shall be couch, free of weeds.
141 A new 1.5 metre wide concrete path shall be constructed along the length of R1, R2 (from Lot 1
    to Lot 21) and R3 in accordance with Council’s design standards. Care shall be taken to protect
    any significant vegetation or any underground services.
142 A pram ramp shall be installed at the intersection of R2 and R3 and at the intersection of R3
    and R8 in accordance with Council’s Standard Drawing 9006.
143 The paths and pram ramp shall be designed and constructed to ensure pedestrian safety using
    non-slip materials and to produce an evenly graded surface finish.
Pathway Construction
144 A 2.0 metre wide concrete shared pathway shall be constructed along the Weyba Creek
    frontage of the site as shown on plan Drawing No 6994-53M Revision M prepared by Conics and
    dated 12 September 2008 shall connect to the Eenie Creek Road reserve bikepath/pathway at
    the proposed bicycle gate.
145 1.5 metres wide concrete pathway shall be constructed along the rest of the pathway network
    indicted on Drawing No 6994-53M Revision M prepared by Conics and dated 12 September
    2008, with the exception of the section negotiating the escarpment which will be decided upon at
    operational works stage.


                                                                                  Page 21 of 32

Page 22

                                                                                      2003/220735


Pathway Contributions
146     A pathway contribution of $235.75 per additional lot for each stage towards external major
      pathways, in accordance with Planning Scheme Policy PSP41 Coastal Major Pathway
      Contributions, shall be paid to the Council prior to endorsement of the Plan of Survey for the
      stage. This amount will be subject to variations in the Price Index, All Groups Brisbane from
      September 2003 until the date of payment.
Sewer Mains
147 The site shall be connected to Council’s existing sewerage reticulation systems and be
    constructed in accordance with Council’s standards and requirements at no cost to Council.
148 The sewerage network will be generally in accordance with Tate Professional Engineers
    Drawing No. C5093/03/L6a Preliminary Water and Sewer Layout Plan dated 12/08/03.
149 A Sewer Master Plan is required to be submitted for approval in conjunction with the application
    for a development permit.
Town Water Supply
150 The water supply network will be generally in accordance with Tate Professional Engineers
    Drawing No. C5093/03/L6a Preliminary Water and Sewer Layout Plan dated 12/08/03.
151 A Water Supply Master Plan is required to be submitted for approval in conjunction with the
    application for a development permit.
152 The site shall be connected to Council’s existing town water supply and be constructed in
    accordance with Council’s standards and requirements at no cost to Council.
153 Each water connection to the water reticulation system shall extend to the property boundary
    and be metered. All fees for the supply of water meters shall be paid to the Council.
154.Registered easements shall be created over all proposed Council water mains within the
    property. The easements shall generally be parallel to and centred over the water main and be
    equivalent in width to twice the depth to invert level of the water main at the deepest point within
    the allotment (measured from the finished surface) and be no less than 3.0 metres wide. In this
    regard, plans submitted for Operational Works approval shall accurately show the location of the
    easements.

      Where a Council water main coincides with an internal road reserve, the road reserve is to be
      dedicated as a water supply easement to provide maintenance access.

      In addition to this, the Applicant’s solicitor shall give Council’s solicitor an appropriate
      undertaking in writing that the Title Deed and the easement documents will be lodged at the
      Land Titles Office and any additional Titles Office forms or requisitions requiring the consent of
      Council will be attended to promptly.

      A duly executed copy of the easements shall be submitted to Council for perusal prior to the use
      commencing. Any changes required by Council’s solicitor must be corrected immediately.

Service Easements
155. The access easement for maintenance of Council’s trunk main adjacent to Eenie Creek Road
    along the proposed access to 12 and 13, as indicated on Drawing No 6994-53M Revision M
    prepared by Conics and dated 12 September 2008, shall be an all weather access track
    (including across the open space) to be constructed by the applicant at no cost to Council.




                                                                                     Page 22 of 32

Page 23

                                                                                      2003/220735


 156. A registered easement shall be created over all proposed Council sewer mains within private
      property. The easements shall generally be parallel to, and centred over, the sewer main and
      be equivalent in width to twice the depth of invert level of the sewer at the deepest point within
      the allotment (measured from the finished surface) and be no less than 3.0 metres wide.
       Where Council sewer mains coincide with internal road reserves, the road reserve is to be
       dedicated as a sewerage easement to provide maintenance access.

       Should the developer utilise private sewers inside individual allotments (ie not in Common
       Property), provision shall be made to facilitate maintenance access. In this regard a width
       equivalent to twice the depth to invert level of the private sewer at the deepest point within the
       allotment (measured from the finished surface) or a minimum of 2.0 metres shall be provided.
       Private easements that would alert all potential owners, shall be created over the maintenance
       access areas for all private sewers if used. Maintenance responsibilities and building set-back
       requirements for any private sewers shall also be clearly designated in the Body Corporate’s
       Community Management Scheme.

       In this regard, where private sewers are utilised, plans submitted for Operational Works
       approval shall be amended to accurately show the location of the Council easements and
       private easements.

       In addition to this, the Applicant’s solicitor shall give Council’s solicitor an appropriate
       undertaking in writing that the Title Deed and the easement documents will be lodged at the
       Land Titles Office and any additional Titles Office forms or requisitions requiring the consent of
       Council will be attended to promptly.

       A duly executed copy of the easements shall be submitted to Council for perusal prior to the
       use commencing. Any changes required by Council’s solicitor must be corrected immediately.
 157. No building or other structure including fountains, retaining walls, etc. (excluding fences) shall
      be constructed or encroach over a Council easement or private sewer access. Any building or
      structure within proximity of an easement, private sewer access, or any other public utility’s
      underground must have its foundations designed so that no surcharge loads are imposed
      upon such underground infrastructure. Foundations must be taken down a minimum of 1
      metre below a line of influence measured 1 metre in the direction of the foundation from the
      centreline of the closest underground service and along the natural angle of repose of the
      foundation soil type(s).
       Plans and supporting documents, detailing these proposed foundations shall be designed by a
       registered practising Geotechnical Engineer and submitted with the application for a
       Development Permit for Material Change of Use for the dwelling houses.

Headworks
 158. Contributions shall be paid to Council in accordance with Planning Scheme Policies PSP28
      and PSP30 on Water Supply Headworks Contributions and Sewerage Headworks
      Contributions respectively and at the rates applicable at the time of payment. An estimate only
      of the contribution rates as of September 2003 under the current policies is as follows:
         Water Supply       $4,076
         Sewerage           $1,441
         TOTAL              $5,517 per additional lot

       All headworks contributions must be paid prior to endorsement of the Plan of Survey for each
       stage.



                                                                                      Page 23 of 32

Page 24

                                                                                         2003/220735


      Alternatively a trading bank guarantee shall be submitted to Council plus 20%. Should the
      headworks contributions not be paid at the due time, Council shall call upon the trading bank
      guarantee in full.

      In the event that the Development Permit for Material Change of Use of Premises lapses or is
      cancelled, the contribution or trading bank guarantee will be returned.

Acid Sulfate Soils Report
159. The development shall be carried out in accordance with the Acid Sulfate Soils Report
     prepared by Soil Surveys Engineering Pty Ltd titled, Acid Sulfate Soils Investigation, Weyba
     Ranch and dated July 2003.
Earthworks
160. Filling works required on site shall be carried out in accordance with Section 3.8 of Council’s
     Engineering Design Standards Manual and so as not to cause the ponding of water on any
     adjoining lands or the blockage of, or interference with, any natural watercourses.
      This will require the design and construction of drainage pipes within the development site that
      cater for drainage within the adjoining sites and in this regard a Development Permit for
      Operational Works shall be obtained.
161. Where a change in the levels of the site outside of an existing or proposed road reserve is
     approved, the site shall be filled or cut so that each lot drains towards a road frontage unless a
     proposed drainage system will collect stormwater from off each lot and discharge the
     stormwater to an adequate Council stormwater drainage system.
      Such works undertaken on the site shall be carried out in accordance with Section 3.8 of
      Council's "Engineering Design Standards" Manual so as not to cause any ponding of water on
      any adjoining land, or the blockage of, or interference with any natural watercourses.
162. A registered practicing Geotechnical Engineer shall test the existing ground conditions for
     suitability of placing additional fill, prior to such fill being placed.
      Filling works shall be restricted to the subject site itself, and the finished fill levels are to taper
      to the existing levels prior to the rear boundary of the property. Batters shall be at a maximum
      grade of 1:4 unless retained by a wall.

      Any existing fill or natural materials on the site or with the extent of approved works external to
      the site which do not satisfy the Manager - Land Development's or a Geotechnical Engineer's
      requirements shall be removed and replaced with suitable material.
163. Fill shall be compacted to 95% relative dry density as per Main Roads Department Test No.
     Q8A. A registered practicing Geotechnical Engineer shall supervise all the placement of fill and
     shall certify that all lots have been compacted to the required standard.
      Any existing fill on the site that does not comply with Council’s requirements shall be removed
      at the direction of the Manager - Land Development prior to additional filling works
      commencing.
164. Following completion of the filling works and prior to endorsement of the Plan of Survey, the
     registered practicing Geotechnical Engineer supervising the works shall submit compaction
     tests across the entire filled areas and a site classification report for each lot subject to filling.
     The extent of fill and each lot site classification shall be shown on a metes and bounds survey
     plan.
165. An appropriate property notation shall be placed on Council's rates records to advise
     prospective purchasers of lots that have been filled that special foundations requirements will
     apply.

                                                                                         Page 24 of 32

Page 25

                                                                                   2003/220735


166. Earthworks carried out on site shall not affect the structural integrity of any of the existing
     fences that border the development site unless it is intended to replace such fences. In this
     regard any fences to be replaced shall be clearly shown on the plans submitted for Operational
     Works approval.
167. The dams to be retained shall be reshaped in order to ensure safety standards for egress after
     accidental entry apply.
Erosion and Sediment Control
168. Any person acting on this permit shall prevent erosion and sediment export from leaving the
     site. Site control measures such as silt fencing, controlled gravel access to the site and
     controlled disposal of waste, will be necessary.
      In this regard plans detailing the methods of controlling erosion and sediment are required to
      be submitted to the Council for approval prior to obtaining a Development Permit for
      Operational Works.

General
169. Any damage caused to any public utility during the course of construction shall be repaired to
     Council’s standards and at no cost to Council.
170. Any alteration of any public utility or other facilities necessitated by the development of the
     land or associated construction works external to the site shall be at no cost to Council.
171. The transportation of all materials to and from the site shall be undertaken in a manner such
     that no particle matter escapes onto a public road. All vehicles carrying materials either to or
     from the site shall be covered to prevent materials including dust being windblown from the
     vehicle.
Additional Conditions

Public Access
172. The applicant shall grant all necessary easements in gross for the purposes of access over
     those internal roads necessary to provide direct access for the public from Noosa Springs
     Drive to the Conservation & Recreation Parklands.
173. The development shall be ungated to permit public access to the Conservation & Recreation
     Parklands at all times.
Lot 902
174. Lot 902 shall be ecologically restored as a koala corridor, with a small landscape entry
     statement compatible with the natural character of the locality permitted to the reasonable
     satisfaction of the Manager, Land Use.
Town Water Supply
175. The water supply network shall provide a minimum 150mm diameter loop main with a
     minimum of two separate connections to the existing main within the Noosa Springs
     Development. The locations of the connections and configuration of the loop main shall be to
     the standards and requirements of Noosa Council.
176. All internal reticulation mains servicing individual “group title lots” shall be designated as
     Council mains.
177. Each individual “group tile lot” is to be provided with a metered water connection to the
     standards and requirements of Noosa Shire Council.
178. A separate single metered water service and reticulation system is to be provided for all Body
     Corporate flows.
                                                                                  Page 25 of 32

Page 26

                                                                                       2003/220735


    Sewer
    179. All sewerage pump stations, reticulation mains and sewer rising mains shall be designated as
         Council assets except for the sections of sewer contained within private allotments which will
         be private sewers maintained by the body corporate.
    Additional Condition 28/10/05

    180. Security in the form of a cash bond or trading bank guarantee to the sum of $250,000 must be
         submitted, to secure performance of all conditions of this approval, prior to any works
         commencing on site. The cash bond or trading bank guarantee will be returned on
         performance of the conditions of approval less any costs incurred by Council in respect of
         enforcing performance of this permit.
    Additional Conditions 16/09/08
    181. The community club house as shown on the Plan of Development Drawing No 6994-53M
         Revision M prepared by Conics and dated 12 September 2008 shall be operated as ancillary
         recreational facilities to the Group Housing Development and shall be for the use of residents
         and their guests only. The facility is not permitted for use by the general public.
    182. The area surrounding the community club house shall be landscaped in accordance with
         Council’s Policy on Landscaping Guidelines. A properly prepared landscape plan shall be
         submitted to Council prior to the issue of Building Works and be to the satisfaction of the CEO.
         Such landscaping is to be completed prior to the premises being occupied and maintained at
         all times thereafter.
    183. No functions or amplified music shall be carried out from the community club house, unless
         otherwise approved by the body corporate.
    184. Lighting associated with the community club house shall be hooded to ensure that excessive
         light spillage does not occur beyond the private open space precinct.
    185. Swimming pools shall be fully fenced in accordance with AS1926.1.
    186. Prior to the issue of Building Works, the following shall be updated to the reasonable
         satisfaction of the CEO:-
            i.    Construction Environmental Management Plan;
          ii.     Sediment and Erosion Control Plan; and
          iii.    Stormwater and Water Quality Management Plan.
          All works shall be carried out in accordance with the above plans
    187. The Operational Stage Environmental Management Plan shall be updated to the reasonable
         satisfaction of the CEO prior to the commencement of the use. All works shall be carried out
         in accordance with this plan.

5         REFERRAL AGENCY CONDITIONS

    The referral agencies applicable to this application are:

     Referral Trigger            Referral Status     Referral Agency      Referral Address

     Contaminated land           Concurrence         Environmental        GPO Box 2771
                                 Agency              Protection Agency    BRISBANE QLD 4001

    A copy of any referral agency conditions is attached.



                                                                                      Page 26 of 32

Page 27

                                                                                        2003/220735


6      APPROVED PLANS/DOCUMENTS

The approved plans and / or documents for this development approval are listed in the following
table:
 Plan / Document No.       Rev.     Plan / Document Name                         Date
 6994-53M                  M        Plan of Development (Master Plan incl.       12 September 2008
                                    Setbacks) – Conics (Sunshine Coast)
                                    Pty Ltd

7      ADVISORY NOTES
The following Advisory Notes are for information purposes only and do not form conditions of
approval:
1.   A Registered Professional Engineer of Queensland shall certify engineering drawings and
     specifications for all engineering works, which shall be submitted in conjunction with an
     application for a Development Permit for Operational Works.
Aboriginal Cultural Heritage Act 2003
There may be a requirement to establish a Cultural Heritage Management Plan and/or obtain
approvals pursuant to the Aboriginal Cultural Heritage Act 2003.
The ACH Act establishes a cultural heritage duty of care which provides that: “A person who carries
out an activity must take all reasonable and practicable measures to ensure the activity does not
harm Aboriginal cultural heritage”. It is an offence to fail to comply with the duty of care. Substantial
monetary penalties may apply to individuals or corporations breaching this duty of care. Injunctions
may also be issued by the Land and Resources Tribunal, and the Minister administering the Act can
also issue stop orders for an activity that is harming or is likely to harm Aboriginal cultural heritage or
the cultural heritage value of Aboriginal cultural heritage.
You should contact the Cultural Heritage Co-ordination Unit on 07 3238 3838 to discuss any
obligations under the ACH Act.

8      PROPERTY NOTES
Not applicable

9      PRELIMINARY APPROVAL OVERRIDING SCHEME
Not applicable




                                                                                        Page 27 of 32

Page 28

                                                                                     2003/220735


10    FURTHER DEVELOPMENT PERMITS REQUIRED

 Type of Development Permit required          Subject of the required Development Permit
 Development Permit for Lot                   Creation of 189 Group Housing Lots
 Reconfiguration

 Development Permit for Operational           Landscaping, Access and/or Carparking, Site Civil
 Works                                        Works, Roadworks, Stormwater Drainage, Frontage
                                              Works, Sewer Reticulation (Including New Mains,
                                              Relocations, Diversions, Pump Stations and Rising
                                              Mains), Water Reticulation, Site Filling, Excavation of
                                              Materials to Fill Another Site.

 Development Permit for Building Works        189 Dwellings & Ancillary Facilities

11    SELF ASSESSABLE CODES
Not applicable

12    SUBMISSIONS
There were twelve (12) properly made submissions about the application.

13    REASONS / GROUNDS FOR APPROVAL DESPITE CONFLICT WITH SCHEME

Not applicable

14    RIGHTS OF APPEAL
You are entitled to appeal against this decision. A copy of the relevant appeal provisions from the
Integrated Planning Act 1997 is attached.

15    OTHER DETAILS
Should you wish to obtain more information about Council’s decision electronic copies are available
on line at www.sunshinecoast.qld.gov.au, or at Council Offices.

DECISION NOTICE HISTORY
 Original Decision Notice 29/04/04
 Negotiated Decision Notice with amendment
   to Conditions 2.1 2.2, 2.3, 2.4, 2.7, 2,10, 3.2,
   3.7, 4, 8, 10, 12, 15, 18, 19, 24, 27, 30, 31,
   39, 43, 50, 58, 60, 63, 65, 66, 67, 76, 81, 84,
   85, 106, 113, 121, 131, 135, 137, 144, 145,
   148, 150 and 155 and deletion of Conditions
   1, 2.9, 2.11, 2.12, 2.13, 25 and 172.4.
 Council changed the development approval to
   a group housing development of 189 dwelling
   units and amended Conditions 2, 3.4, 3.5, 12,
   65, 81, 85, 88, 121, 137, 144, 145, 154, 155
   and additional Conditions 172, 173, 174, 175,
   176, 177, 178 and 179 on 16 December 2004
 Minor Change to the approval with
   amendment to Conditions 2.8.2, 3.4 and 3.7
   on 25 August 2005.

                                                                                     Page 28 of 32

Page 29

                                                   2003/220735


 Minor Change to the approval with
   amendment to Conditions 6, 7, 139, 146, 154,
   156, 157, 158 and 179, deletion of condition
   49 and inclusion of one additional Condition
   on 28 October 2005.
 Minor Change to the approval with
   amendment to Conditions 2, 2.8.2, 2.10, 2.11,
   88 & 133, Inclusion of additional conditions
   2.14 & 2.15 and deletion of Conditions 2.12,
   2.13 and 3.3 on 13 April 2006.
 Change to the approval with amendment to
   Conditions 2.3 & 4 on 7 April 2008.
 Change to the development approval with
   amendment to Conditions 2, 65, 81, 103, 121,
   137, 144, 145 & 155 and inclusion of seven
   additional conditions.
Yours faithfully,



Kerri Coyle
MANAGER – LAND USE




                                                   Page 29 of 32

Page 30

                                                                          2003/220735



                                    Referral  Agency       Conditions                       -
                                    Environmental Protection Act
                                    INTEGRATED PLANNING ACT 1997 & 1998 REGULATION



1.   At all times while the use continues and the subject land is on the Environmental
     Management Register (EMR) the applicant must comply with the approved Site
     Management Plan (SMP) and Remediation Action Plan (RAP) for Lot 2 on RP904900 issued
     under the Environmental Protection Act 1994 by the Environmental Protection Agency
     (Contaminated Land Unit).




                                                                         Page 30 of 32

Page 31

                                                                                                2003/220735



                                                    Appeal Rights
                                                    INTEGRATED PLANNING ACT 1997 & 1998 REGULATION




The following is an extract from the Integrated                       (5) If an application is processed under section
Planning Act (Chapter 4).                                       6.1.28(2), appeal rights for submitters for the
                                                                application are available only for the aspects of the
Division 8 - Appeals to court relating to
                                                                development that would have required public
development applications
                                                                notification under the repealed Act.
Appeals by applicants
                                                                      (6) If an application involves assessment against a
4.1.27.(1) An applicant for a development application           concurrence agency code, appeal rights for
may appeal to the court against any of the following-           submitters for the application are not available against
(a) the refusal, or the refusal in part, of a development       the part of the approval that represents the
    application;                                                concurrence agency’s response for the code.
(b) a matter stated in a development approval,                  Appeals by advice agency submitters
    including any condition applying to the                     4.1.29.(1) An advice agency may, within the limits of
    development, and the identification of a code               its jurisdiction, appeal to the court about the giving of
                          1
    under section 3.1.6;                                        a development approval for a development
(c) the decision to give a preliminary approval when a          application if-
    development permit was applied for;                         (a) the development application involves impact
(d) the length of a currency period;                                  assessment; and
(e) a deemed refusal.                                           (b) the advice agency told the applicant and the
    (2) An appeal under subsection (1)(a) to (d) must                 assessment manager to treat its response to the
be started within 20 business days (the “applicant’s                  application as a submission for an appeal.
appeal period”) after the day the decision notice or                  (2) The appeal must be started within 20 business
negotiated decision notice is given to the applicant.           days after the day the decision notice or negotiated
    (3) An appeal under subsection (1)(e) may be                decision notice is given to the advice agency as a
started at any time after the last day a decision on the        submitter.
matter should have been made.                                   Appeals for matters arising after approval given
Appeals by submitters                                           (co-respondents)
4.1.28.(1) A submitter for a development application            4.1.30.(1) For a development approval given for a
may appeal to the court about-                                  development application, a person to whom any of the
                                                                following notices have been given may appeal to the
(a) the giving of a development approval, including             court against the decision in the notice-
    any conditions (or lack of conditions) or other
    provisions of the approval; or                              (a) a notice giving a decision on a request for
                                                                      extension of the currency period for an approval;
(b) the length of a currency period for the approval.
                                                                (b) a notice giving a decision on a request to make a
    (2) The appeal must be started within 20 business                 minor change to an approval.
days (the “submitters appeal period”) after the day
the decision notice or negotiated decision notice is                  (2) The appeal must be started within 20 business
given to the submitter.                                         days after the day the notice of the decision is given
                                                                to the person.
    (3) If a person withdraws a submission before the
application is decided, the person may not appeal the                 (3) Subsection (1)(a) does not apply if the
decision.                                                       approval resulted from a development application
                                                                (superseded planning scheme) that was assessed as
    (4) If an application involves both impact                  if it were an application under a superseded planning
assessment and code assessment, appeal rights for               scheme.
submitters are available only for the part of the
application involving impact assessment.                              (4) Also, a person who has made a request
                                                                mentioned in subsection (1) may appeal to the court
                                                                against a deemed refusal of the request.
                                                                      (5) An appeal under subsection (4) may be started
                                                                at any time after the last day the decision on the
1
    Section 3.1.6 (Preliminary approval may override local      matter should have been made.
    planning instrument)
                                                                                               Page 31 of 32

Page 32

                                                                                           2003/220735


Division 9 - Appeals to court about other matters          Appeals by applicants
Appeals for matters arising after approval given           4.2.9(1) An applicant for a development application
(no co-respondents)                                        may appeal to the Building and Development Tribunal
4.1.31.(1) A person to whom any of the following           against any of the following-
notices have been given may appeal to the court            (a) the refusal, or the refusal in part, of a development
against the decision in the notice-                            application;
(a) a notice giving a decision on a request to change      (b) a matter stated in a development approval,
    or cancel a condition of a development approval.           including any condition applying to the
                                   2
(b) a notice under section 6.1.44 giving a decision to         development, and the identification of a code
                                                                                     3
    change or cancel a condition of a development              under section 3.1.6;
    approval.                                              (c) the decision to give a preliminary approval when a
    (2) The appeal must be started within 20 business          development permit was applied for;
        days after the day the notice of the decision is   (d) the length of a period mentioned in section 3.5.21
        given to the person.                                   currency period;
    (3) Also, a person who has made a request              (e) a deemed refusal.
        mentioned in subsection (1)(a) may appeal to           (2) An appeal under subsection (1)(a) to (d) must
        the court against a deemed refusal of the          be started within 20 business days (the “applicant’s
        request.                                           appeal period”) after the day the decision notice or
    (4) An appeal under subsection (3) may be started      negotiated decision notice is given to the applicant.
        at any time after the last day the decision on         (3) An appeal under subsection (1)(e) may be
        the matter should have been made.                  started at any time after the last day a decision on the
Appeals against decisions to change approval               matter should have been made.
conditions under the repealed Act                          The Registrar for the Building and Development
4.1.33A.(1) A person who is dissatisfied with a            Tribunal may be contacted at the website
decision made on an application to change the              http://www.localgovernment.qld.gov.au/
conditions attached to an approval given under
section 2.19(3)or section 4.4 of the repealed Act may
appeal to the court against-
(a) the decision; or
(b) a deemed refusal of the application.
    (2) An appeal under subsection (1)(a) must be
started within 20 business days after the day notice of
the decision is to be given to the person.
    (3) An appeal under subsection (1)(b) may be
started at any time after the last day a decision on the
matter should have been made.
Appeals against local laws
4.1.33B.(1) An applicant who is dissatisfied with a
decision of a local government or the conditions
applied under a local law about the use of premises or
the erection of a building or other structure permitted
by the planning scheme may appeal to the court
against the decision or the conditions applied.
    (2) The appeal must be started within 20 business
days after the day notice of the decision is given to
the applicant.
For Building Works Only
Rights of appeal conferred by Section 4.2.9 of the
Integrated Planning Act 1997 as follows:
Division 3 – Appeals to tribunals relating to
development applications


2
     Section 6.1.44 (Conditions may be changed or
                                                           3
    cancelled by assessment manager or concurrence             Section 3.1.6 (Preliminary approval may override local
    agency in certain circumstances)                           planning instrument)
                                                                                          Page 32 of 32

Used in these records

About this file

File size
130 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Decision Notice - Change to an Existing Approval [As Published].pdf · 130 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.