36. No building or other structure shall be constructed or encroach over an easement. Any
building or structure within proximity of an easement or any other public utility’s underground
must have its foundations designed so that no surcharge loads are imposed upon such
underground infrastructure. Foundations must be taken down a minimum of 1 metre below a
line of influence measured 1 metre in the direction of the foundation from the centreline of the
closest underground service and along the natural angle of repose of the foundation soil
type(s).
Plans, and supportive documents, detailing these proposed foundations shall be designed by
a registered practicing Geotechnical Engineer and submitted with the application for a
Development Permit for Operational Works.
Headworks
37. Contributions shall be paid to Council in accordance with Planning Scheme Policies PSP28
and PSP30 on Water Supply Headworks Contributions and Sewerage Headworks
Contributions respectively and at the rates applicable at the time of payment. An estimate
only of the contribution rates as of June 2004 under the current policies is as follows:
Water Supply $3,152
Sewerage $2,289
TOTAL $5,441
All headworks contributions must be paid prior to the issue of a Development Permit for
Operational Works.
Alternatively a trading bank guarantee shall be submitted to Council plus 20%. Should the
headworks contributions not be paid at the due time, Council shall call upon the trading bank
guarantee in full.
In the event that the Development Permit for Material Change of Use of Premises lapses or is
cancelled, the contribution or trading bank guarantee will be returned.
Earthworks
38. Earthworks carried out on site shall not affect the structural integrity of any of the existing
fences that border the development site unless it is intended to replace such fences. In this
regard any fences to be replaced shall be clearly shown on the plans submitted for
Operational Works approval.
Erosion and Sediment Control
39. Any person acting on this permit shall prevent erosion and sediment export from leaving the
site. Site control measures such as silt fencing, controlled gravel access to the site and
controlled disposal of waste, will be necessary.
In this regard plans detailing the methods of controlling erosion and sediment are required to
be submitted to the Council for approval prior to obtaining a Development Permit for
Operational Works.
General
40. Any damage caused to any public utility during the course of construction shall be repaired to
Council’s standards and at no cost to Council.
41. Any alteration of any public utility or other facilities necessitated by the development of the
land or associated construction works external to the site shall be at no cost to Council.
42. The transportation of all materials to and from the site shall be undertaken in a manner such
that no particle matter escapes onto a public road. All vehicles carrying materials either to or
from the site shall be covered to prevent materials including dust being windblown from the
vehicle.
Page 6 of 12
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Decision Notice - Change to an Existing Approval - 010.2005.00000353.003 [As Published]Related documentApplication case desk ↗
About this file
- File size
- 72 KB (small file)
- File type
No other editions are linked here.