b. Oversee installation of all tree protection fencing prior to commencement of any works
onsite (including any clearing).
c. Supervise tree protection within the development site and frontages, prior to, during
and following construction in accordance with AS 4970, Protection of trees on
development sites.
d. Supervise and undertake necessary tree protection for all trees affected by the
development on neighbouring Lots. This includes tree identified in the approved
arborist report as outside project scope within the neighbouring properties east of the
development site. Where trees within neighbouring properties are found to be unsafe
due to works relating to this development approval, the developer is solely responsible
for the removal and replacement of these trees.
e. Oversee approved tree removal in proximity to retained trees.
f. Undertake a risk assessment of all trees on neighbouring properties affected by the
development within striking distance of the development works and site and carry out
hazard removal and amenity pruning in accordance with AS 4373, Pruning of amenity
trees.
*(Refer to Advisory Note)
Fauna Management
37. A qualified person* must be engaged to manage fauna in accordance with a fauna
management plan submitted prior to a prestart meeting. The fauna management plan must
include the following:
g. Ensure works are carried out in accordance the Nature Conservation Act 1992.
h. Undertake pre-clearing inspections including fauna relocation and removal or blocking
of all vacant hollows.
i. Co-ordinate staging and sequence of clearing with fauna protection.
j. Protect and recover fauna during clearing operations.
k. Manage the translocation of animals and recovery procedures in accordance with
relevant legislation.
l. Undertake protection works for mulching of any stockpiled vegetation.
*(Refer to Advisory Note)
Removal of Existing Trees and Vegetation
38. Removal of existing trees and vegetation must be undertaken by a qualified person* and
must include:
m. Stump grinding to below finished surface level.
n. Rectification to the finished surface levels and materials.
o. No damage to other vegetation for retention.
p. Legal disposal of all removed vegetation and debris.
*(Refer to Advisory Note)
FOLLOWING CONSTRUCTION / PRIOR TO COMMENCEMENT OF THE USE
Certification
39. Upon completion of the work a certificate must be issued by an RPEQ certifying that the
works have been constructed in accordance with the Operational Works permit.
Bonds
40. Bonds must:
Page 31 of 36
Document Set ID: 22528171
Version: 11, Version Date: 11/01/2024
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Delegated Report - Code - Planning MCU23 0094, OPW23 0113 & RAL23 0014 [As Published].pdfRelated documentApplication case desk ↗
About this file
- File size
- 3.6 MB (large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take up to a minute.