Response to RFI - 25-27 Toolar St · MCU21/0083
Approximate location
of visitor carpark
Figure 2: Proposed location of visitor space on eastern boundary.
Item 3 Information required
3. Provide a stormwater management strategy which demonstrates how the development is
consistent with the Water Quality and Drainage Code of the Noosa Plan of the Noosa Plan. In
particular, the plan must demonstrate how the development is consistent with PO2, PO6, and
PO10 of that code.
Response to Item 3
The applicant’s stormwater management strategy incorporated into the Concept Stormwater
Management Plan in Attachment 1 prepared by SCG. Roof runoff will be collected and directed to
the on site rainwater tank beneath the driveway. Rainwater in the underground tank will be retained
on site for reuse in gardens and other lawful uses within the buildings such as toilet flushing. Once
full, the rainwater tank will overflow to a further detention tank before release into Council’s stormwater
network. Gross pollutant traps will be located inside the site boundaries to capture gross pollutants
prior to discharge to the street. Surface runoff from the driveway will be collected in a grated drain
across the driveway and water directed to the GPT’s before discharge.
Concept Planning and Development Consultants ABN 99 789 542 467 4
[OCR of page images]
Approximate location
of visitor carpark
Figure 2: Proposed location of visitor space on eastern boundary.
Item 3 Information required
3. Provide a stormwater management strategy which demonstrates how the development is
consistent with the Water Quality and Drainage Code of the Noosa Plan of the Noosa Plan. In
particular, the plan must demonstrate how the development is consistent with PO2, PO6, and
PO10 of that code.
Response to Item 3
The applicant’s stormwater management strategy incorporated into the Concept Stormwater
Management Plan in Attachment 1 prepared by SCG. Roof runoff will be collected and directed to
the on site rainwater tank beneath the driveway. Rainwater in the underground tank will be retained
on site for reuse in gardens and other lawful uses within the buildings such as toilet flushing. Once
full, the rainwater tank will overflow to a further detention tank before release into Council’s stormwater
network. Gross pollutant traps will be located inside the site boundaries to capture gross pollutants
prior to discharge to the street. Surface runoff from the driveway will be collected in a grated drain
across the driveway and water directed to the GPT’s before discharge.
Concept Planning and Development Consultants ABN 99 789 542 467 4
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Response to RFI - 25-27 Toolar St.pdfRelated documentApplication case desk ↗
About this file
- File size
- 3.7 MB (large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take up to a minute.