Damage to Services and Assets
24. Any damage caused to existing services and assets as a result of the development works
must be repaired at no cost to the asset owner at the following times:
a. where the damage would cause a hazard to pedestrian or vehicle safety, immediately;
or
b. where otherwise, upon completion of the works associated with the development.
Any repair work which proposes to alter the alignment or level of existing services and assets
must first be referred to the relevant service authority for approval.
5. REFERRAL AGENCIES
Not applicable.
6. ADVISORY NOTES
The following notes are included for guidance and information purposes only and do not form part
of the assessment manager conditions:
Resubmission of Amended Plans Required
1. The conditions of this Decision Notice require resubmission of plans to Council with
amendments. Please address the amended plan/s to Council’s Development Assessment
Branch with the Reference No. MCU23/0139.
Building and Construction Industry (Portable Long Service Leave) Levy
2. The QLeave levy must be paid prior to the issue of a development permit where it is required.
Council will not be able to issue a Decision Notice without receipt of details that the Levy has
been paid.
Sustainability
3. Council encourages sustainable and energy efficient building design for all development
including the use of sustainable building materials, energy efficient fittings, solar hot water,
photovoltaic systems (including the use of inverter/charges), solar panels, water saving
3. devices and rainwater harvesting.
Co-ordination of Operational Works Assessment
4. Additional application fees apply to Operational Work applications where the different
aspects of the works are lodged separately. Significant savings in application fees will result
if all works are lodged in a single application.
Preparation of a Preliminary Construction Management Plan
5. A preliminary Construction Management Plan must be submitted with the Operational Works
application and must address the following:
a. Traffic management during all phases of construction;
b. Adequate parking arrangements for works and deliveries;
c. appropriate traffic signage in accordance with the Manual of Uniform Traffic Control
Devices (MUTCD); and
d. provision for safe vehicle and pedestrian access across the frontage of the site both
during daily construction and after daily construction has ceased.
Infrastructure Charges
6. All developments and/or changes to existing developments may require payment of
“Infrastructure Charges” (as applicable) in accordance with Council’s “Charges Resolution”
made pursuant to the planning legislation and regulations current at the time of issue. For
further information, please refer to https://www.noosa.qld.gov.au/planning-
development/development-tools-guidelines/infrastructure-charges
Page 9 of 10
Document Set ID: 22856668
Version: 5, Version Date: 21/03/2024
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Delegated Report - Code - Planning MCU23 0139 [As Published].pdfRelated documentApplication case desk ↗
About this file
- File size
- 3.4 MB (large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take up to a minute.