28. Fire hydrants are to be provided on the development site in accordance with Council
Engineering Design Standards and in accordance with Queensland Fire Service
Standards. The provision of fire hydrants and any required booster pump shall be in
accordance with the Building Code of Australia, and consultation may also be needed
with Queensland Fire Services to ensure suitable fire fighting infrastructure is provided.
To this end any necessary fire hydrants shall be clearly shown on the plans submitted
for Building Works approval and if a booster pump is deemed necessary, the plans shall
indicate where the fire truck is to be accommodated in order to provide boosting to the
water supply.
Erosion and Sediment Control
29. Any person acting on this permit shall prevent erosion and sediment export from leaving
the site. Site control measures such as silt fencing, controlled gravel access to the site
and controlled disposal of waste, will be necessary.
Contributions Towards Council Infrastructure
30. Monetary contributions shall be paid to Sunshine Coast Regional Council towards the
cost of providing and/or upgrading various infrastructure at the rates applicable at the
time of payment. An estimate only of the contribution amounts under the current
Council policies and requirements is outlined in the table below:
Contribution Required For: Amount:
PSP12 – Public Open Space Contributions (Park) $17,873
PSP16 – Sewerage Headworks Contributions $18,353
PSP17 – Water Supply Headworks Contributions $31,609
PSP20 – Pathway Trunk Network Contributions $5,443
TOTAL Contribution Amount = $73,278
Please note, that these amounts are all subject to variations in the Consumer Price
Index, All Groups Brisbane from March 2009 until the date of payment.
All contributions must be paid prior to Council’s endorsement of the plan of survey.
In the event that the Development Permit for Material Change of Use of Premises lapses
or is cancelled, any paid contributions and/or the trading bank guarantee will be
returned.
General
31. Any damage caused to any public utility during the course of construction shall be
repaired to Council’s standards and at no cost to Council.
32. Any alteration of any public utility or other facilities necessitated by the development of
the land or associated construction works external to the site shall be at no cost to
Council.
33. The transportation of all materials to and from the site shall be undertaken in a manner
such that no particle matter escapes onto a public road. All vehicles carrying materials
either to or from the site shall be covered to prevent materials including dust being
windblown from the vehicle.
Refuse
34. Paved waste storage areas shall be provided on site for all wheelie bins.
35. The existing wheelie bin cleaning contract shall be continued, or alternatively, an on-site
bin washing facility connected to the sewer shall be provided.
FM1512s/1-07/04/2010 Page 5 of 9
Print Date: 24 April 2019, 10:39 AM
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
App H - Existing Approvals.pdfRelated documentApplication case desk ↗
About this file
- File size
- 1.6 MB (small file)
- File type
No other editions are linked here.