Minor Change Existing Approval - MCU17 0568 02 & OPW17 0602 02 (As Published)
3. CURRENCY PERIOD OF APPROVAL
• The relevant period for the Material Change of Use development approval is 6 years starting
the day that this development approval takes effect.
• The relevant period for the Operational Works development approval is 2 years starting the
day that this development approval takes effect.
4. ASSESSMENT MANAGER CONDITIONS
MATERIAL CHANGE OF USE - MCU17/0568
PLANNING
When Conditions must be Complied With
1. Unless otherwise stated, all conditions of this Decision Notice must be complied with prior to
the use commencing, and then compliance maintained at all times while the use continues.
Approved Plans
2. Development authorised by this approval must be undertaken generally in accordance with
the Approved Plans listed in the tables below.
Plan No. Rev. Plan/Document Name Date
2026-27 A Site Plan prepared by building Suncoast green 02/06/2026
Sheet No. 01
of 03
2026-27 A Elevations prepared by building Suncoast green 02/06/2026
Sheet No. 02
of 03
2026-27 A 3D Views prepared by building Suncoast green 02/06/2026
Sheet No. 03
of 03
Nature and Extent of Approved Use
3. Any display and retail sale of goods must remain an ancillary component to the approved
use and must not exceed 20%.
Building Appearance
4. The development must be finished with subdued external building colours.
Building Height
5. The maximum height of the development must not exceed 10 metres above the finished
ground level and the natural ground level.
Performance Bond
6. Security in the form of a cash bond or trading bank guarantee to the sum of $15,000 must
be submitted to Council, to secure performance of all conditions of this approval, prior to the
issue of Building Works. The cash bond or trading bank guarantee will be returned on
performance of the conditions of approval less any costs incurred by Council in respect of
enforcing performance of this permit. Council reserves the right to call upon the bond or
guaranteed sum to effect compliance with conditions.
Street Identification
7. The street address of the development must be clearly visible and discernible from the
primary frontage of the site by the provision of a street number and, where appropriate, the
building name.
Page 2 of 15
Document Set ID: 25022269
Version: 4, Version Date: 30/07/2026