Development Application - Part 1 of 2 - Covering Letter, IDAS Forms 1 & 6 and Checklist 1 & 4 · OPW11/0399

of 22

Text shows just the words. Original shows the document exactly as it was published.

1.6          Is any of the proposed operational work listed in schedule 12 of the Sustainable Planning Regulation
             2009 and does it exceed the specified threshold?


Z No
                •       This application requires assessment by the Department of Transport and Main Roads as a
q Yes
                         concurrence agency

Section reference:
•       Sustainable Planning Regulation 2009, schedule 7, table 3, item 14

1.7          Is any of the proposed operational work listed in schedule 13 of the Sustainable Planning Regulation
             2009 and does it exceed the specified threshold?

      No
                         This application requires assessment by the Department of Transport and Main Roads as a
q Yes
                         concurrence agency

Section reference:
•            Sustainable Planning Regulation 2009, schedule 7, table 3, item 15


1.8          Is any part of the premises in an interim koala habitat protection area identified under the South East
             Queensland Koala state planning regulatory provisions (SEQ Koala SPRP)?

® No

q Yes                    It is recommended that you complete part 5 of this checklist.


1.9          Is any of the proposed operational work associated with reconfiguring a lot and the reconfiguration is
             also assessable?


® No
q Yes                    It is recommended that you complete part 6 of this checklist.


1.10         Does the Vegetation Management Act 1999 apply to any of the proposed operational work for the
             clearing of native vegetation?

® No

q Yes                    It is recommended that you complete part 7 of this checklist.


1.11         Is any of the proposed operational work for any thing constructed or installed that allows, under the
             Water Act 2000, for taking or interfering with water from a watercourse, lake or spring (other than
             using a water truck to pump water; and other than under the Water Act 2000, section 20(2), (3) or (5),
             or from a dam constructed on a watercourse or lake?

® No
q Yes
      No.^               It is recommended that you complete part 8 (starting from question 8.8) of this checklist.
                         It is recommended that you complete part 8 (starting from question 8. 1) of this checklist.


1.12         Is any of the proposed operational work tidal work, other than excluded work defined under the
             Sustainable Planning Regulation 2009?

® No
q Yes            •       It is recommended that you complete part 9 of this checklist.




                                                                                            Operational works . IDAS checklist 4
                                                                                                    Ver:tiion 1 0 December 2009

Used in these records

About this file

File size
4.3 MB (large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Development Application - Part 1 of 2 - Covering Letter, IDAS Forms 1 & 6 and Checklist 1 & 4.pdf · 4.3 MB (large file)

The download may take up to a minute.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.