Other Change Decision Notice - Council Meeting Decision 132005 638 04 (As Published)

of 72

Page text shows just the words. Original shows the document exactly as it was published.

Page text read automatically using OCR, there may be inaccuracies

                        and always maintained at the waste management facility site office.
                37.     Certification must be submitted to Council from a qualified person* which certifies that
                        the development has been undertaken and constructed in accordance with the bushfire
                        management conditions of this Decision Notice.
                        *(Refer to Advisory Note)
                38.     A review and certification of the Bushfire Management Plan is required every 5 years to
                        ensure its currency and must be submitted to Council from a qualified person*.
                        *(Refer to Advisory Note)
                        Environmental covenant
                39.     A vegetation protection covenant must be registered against the title/s of the property
                        over the area identified as the 1.8ha Proposed Offset Planting Area as shown on the
                        Approved Plans pursuant to Section 97A of the Land Title Act 1994. The covenant
                        document and a survey plan must be submitted to Council for endorsement prior to
                        lodgement with the relevant titles authority for registration of title. The covenant
                        document must:
                        a.      incorporate the requirements of this Decision Notice
                        b.      include Noosa Council as Covenantee reference Queensland Land Title Registry
                                Standard Terms Document No. 715597513.
                40.     The vegetation protection covenant document must be registered with the titles office
                        before the commencement of the use of the expanded Resource Recovery Area.
                ENGINEERING
                        Earthworks and Retaining Walls
                41.     All fill and associated batters must be contained entirely within the approved use area
                        and must be designed and certified by a suitably qualified person.
                        Acid Sulfate Soils
                42.     An Acid Sulfate Soils Investigation Report must be prepared to mitigate the risk of acid
                        sulfate soils on the adjacent bushland /wetland areas.
                        All requirements and recommendations of the Acid Sulfate Soils Investigation Report
                        must be certified by a suitably qualified person*.
                        *(Refer to Advisory Note)
                STORMWATER
                43.     Prior to the construction of the pad area for the expansion of the Resource Recovery
                        Area (RRA) and the relocation of the HES basin, provide an updated SWMP, which is
                        based on the Covey’s Stormwater Management Plan (M25-0042Rpt, Issue A) dated
                        February 2025 and which addresses the following:
                        a.      Specify the final HES basin detail from the range of options presented in the report,
                                including consideration of whether a Type-B HES basin may present a lower-risk
                                option compared to the flap-gated arrangement proposed to prevent back-flows
                                into the Type-A arrangement as currently proposed;
                        b.      Include all details for the sizing and proposed levels of the HES basin within the
                                body of the report, based on recent detailed survey at the point of discharge and
                                downstream; and
                        c.      Include construction-phase erosion and sediment control plans which document
                                how the transition from the current HES basin location to the ultimate location
                                (including filling for the RRA pad) will be achieved.




                                                                                                           Page 6 of 72
Document Set ID: 24377726
Version: 13, Version Date: 23/12/2025
Log in to download the original file

Other Change Decision Notice - Council Meeting Decision 132005 638 04 (As Published).pdf · 7.5 MB (large file)

The download may take up to a minute.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.