Page 29 of 106
PLANNING & ENVIRONMENT COMMITTEE MEETING AGENDA 11 APRIL 2017
ATTACHMENT 1
120% LGAQ Annual Conference
Wo 4 LD Gold Coast Convention & Exhibition Centre
2684-2690 Gold Coast Highway, Broadbeach
ORDER 18 - 20 October 2016
W Ej #icaq2016
PLANNING AND DEVELOPMENT
Submitting council / organisation
Noosa Shire Council
Date of council / organisation resolution LGAQ Policy Executive district
18 August 2016 District 2 — South East
: , 27 - Planning Powers - Local Government Infrastructure Plans - Amend,
eee cael Simplify and Remove Unnecessary and Irrelevant Statutory Requirements
Motion That the Local Government Association of Queensland lobby the State Government to
amend the Statutory Guidelines with respect to Local Government Infrastructure Plans
(LGIPs) in order to remove the unnecessary cost, resource and time burdens
reimposed on local governments, with this to be achieved by:
a) removing obsolete requirements for itemised detailed costing of existing assets
plus determination of network catchment demand allocations that are irrelevant
under the current adopted infrastructure charges regime (these former “PIP &
ICS” requirements were necessary only for determining charge rates and were
thus discarded in the 2011 legislative amendments on introduction of adopted
charges);
b) removing the requirement for third party reviews of draft LGIPs by an appointed
reviewer (note that this matter was raised under motion 28 at the 118th LGAQ
Conference to no effect); and
c) simplifying all LGIP review and approval processes to accord with a single
process as currently described for an “interim local government infrastructure plan
amendment’ - this being identical for “making and amending a planning scheme
policy”.
27(a) MOVER: Cr T. Wellington (Noosa)
SECONDER: Cr F. Wilkie (Noosa) CARRIED
27(b) MOVER: Cr T. Wellington (Noosa)
SECONDER: Cr F. Wilkie (Noosa) CARRIED
27(c) MOVER: Cr T. Wellington (Noosa)
SECONDER: Cr F. Wilkie (Noosa) CARRIED
23|Page
AJIT Kags ap Yow Yow Wiew &f & fh mm. te We 1b B
1s HOW i)
Page 29 of 106See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalVery large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.