PLANNING & ENVIRONMENT COMMITTEE MEETING AGENDA 11 APRIL 2017
Page 44 of 106
PLANNING & ENVIRONMENT COMMITTEE MEETING AGENDA 11 APRIL 2017
Attachment 2
COUNCIL .
Project Control Group Charter
CLIMATE CHANGE ADAPTATION PLAN
Name Climate Change Adaptation Plan (CCAP) Project Control Group (PCG)
Goals The CCAP will:
e Improve Noosa Council and the community’s understanding of current &
future risks from coastal hazards and how they might change through time
as a result of climate change;
e Consult with the community clearly and sensitively throughout key stages
of the project so the community understands the implications and
contributes to the decision making;
e Identify what actions are required to avoid, reduce or adapt to these risks
to people, property, assets and the environment;
e Provide mapping & visual products and deliverables that are useful for a
range of purposes across Council departments and functions and within
the community (e.g. planning scheme, asset management, community
awareness, disaster management and financial planning; and
e Provide direction for a coordinated approach for council and the
community to adapt to climate change and coastal hazards.
Roles & The primary role of the PCG is to provide high level guidance and direction to
Responsibilities the project team on both the processes (including scope) involved in
conducting the background assessment report, assessments, and the content
of the final adaptation plan. This will include ensuring relevant public and
private interests are considered during the project and that inputs meet
nominated deadlines. The PCG is comprised of internal stakeholders only.
PCG members are to respect the confidentiality of draft CCAP findings and
material. The PCG would have oversight of higher level policy related matters.
Timeframes Council has agreed to a project schedule with Local Government Association
of QLD. Principal timeframes are:
e 2017/2018 — Continuous community and stakeholder engagement
e 2017 — Conducting coastal hazard risk, vulnerability and adaptation
assessment
e 2018 — Development of final adaptation plan and implementation plans
Meeting Bi-monthly or as needed according to Project Plans
Frequency
Membership Cr Tony Wellington (Mayor)
Cr (pending)
Cr (pending)
Chief Executive Officer (ex officio)
Director, Planning & Sustainable Environment
Director, Infrastructure Services
Director, Community Services
Director, Corporate Services
Rebecca Britton — Principal Strategic Planner
Meeting Grant Hinner — Program Coordinator Climate Change Adaptation
Coordinator
Page 44 of 106See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalVery large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.