2020-09-14 GC Agenda - Item 7 - Attachment 1 - Noosa River Oyster Ecosystem Restoration Project Annual Report No. 1

of 27

Page text shows just the words. Original shows the document exactly as it was published.

Text sections have not been matched to the original PDF pages. Use the original document to check page numbers.

Total progress against agreed deliverables
Table 1 presents the total progress of the project against the deliverables as outlined in the Alliance and Funding
Agreement Schedule 1.

Table 1: Total progress of the project against the deliverables

 Deliverables                   Measurable          Timeframe     Progress         Total progress to date and notes
                                outcomes
 (A1.1) A Technical Advisory    1 Technical         30 April      Achieved         Terms of Reference (ToR) for the
 Group (TAG) is established     Advisory Group      2020                           TAG finalised
 to provide project             with TOR
 oversight. This will include   established                                        200821 Noosa TAG ToR revised
 a clear terms of reference
 (ToR) and consist of                                                              Inaugural meeting held 13 May
 representatives from key                                                          2020.
 stakeholders (NSC, TNC,
 Kabi Kabi and at least two                                                        200601 TNC Noosa TAG Meeting
 other independent                                                                 1 - Minutes Final
 parties).
                                                                                   Second meeting held 20 August
                                                                                   2020.

                                                                                   200830 TNC Noosa TAG Meeting
                                                                                   2 - Minutes Final

                                                                                   Key representation from the Kabi
                                                                                   Kabi Nation have been invited to
                                                                                   participate in the TAG meetings
                                                                                   and have expressed a keen
                                                                                   interest. To date, they have been
                                                                                   unavailable to participate
                                                                                   directly in the meetings but will
                                                                                   be engaged by appropriate
                                                                                   means.

 (A1.2) Appointment of          1 Project           31 January    Achieved         Craig Bohm appointed by TNC as
 dedicated project manager      Manager             2020                           Marine Coordinator for South
 who is a marine biologist      appointed                                          East Queensland, based in
 with extensive project                                                            Noosa. Position commenced 29
 management experience,                                                            January 2020.
 for the term of the
 Agreement.
 (A1.3) A Project               1 Project           31            Achieved         The project implementation plan
 Implementation Plan            Implementation      December                       was endorsed by Noosa Shire
 detailing at a minimum:        Plan completed      2019                           Council as the ‘Project
 A detailed risk assessment     and endorsed by                                    Management Plan’ at its
 associated with the            Noosa Council                                      Ordinary Meeting held 16 July
 project.                                                                          2020.
 A communications and                                             Achieved
 media plan, outlining



                                                                                                                       8
Log in to download the original file

2020-09-14 GC Agenda - Item 7 - Attachment 1 - Noosa River Oyster Ecosystem Restoration Project Annual Report No. 1(PDF, 927KB).pdf · 949 KB (small file)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.