SUPERSEDED - Decision Notice OPW26 0033 (As Published)
ii. maintenance of safe vehicle and pedestrian access across the frontage of the
site both during daily construction and after daily construction has ceased;
iii. proposed fencing to the site during the construction phase of the development;
iv. adequate parking arrangements for construction workers and deliveries; and
v. no queuing of trucks is permitted on residential streets;
b. maintenance and protection of water quality and existing drainage lines through the
construction site through the implementation of appropriate erosion and sediment
control measures;
c. works programme identifying key components of the works and their respective
durations;
d. establishment of a communication protocol with the general public, adjoining owners,
emergency services and local businesses to advise of agreed construction times,
impacts on traffic and services and other relevant issues;
e. include a post out to the local residents and businesses advising of the proposed
development, the expected time frames and the site contact details;
f. include signage in prominent locations on the boundaries of the site advising of the
proposed development, the expected time frames and the site contact details;
g. identification of complaint management procedures including:
i. contact details for the on-site manager; and
ii. dispute resolution procedures.
h. details on the location of external fill/dump sites/sources, the haulage route, type of
vehicle to be utilised during filling operations and frequency of usage.
Any damage to the existing road system as a result of haulage operations shall be fully
repaired at the applicant’s expense.
11. All necessary approvals from external service providers (e.g., Unitywater) and external
parties on which the development works are proposed have been obtained and a copy
supplied to Council.
12. Any changes to the details associated with the supervising RPEQ or Principal Contractor
during construction, must be notified to council in writing within five business days of the
change occurring.
13. Any conflict between the development and an existing or proposed service must be referred
to the relevant service authority for determination prior to commencement of works.
VEGETATION PROTECTION
Retention of Existing Trees and Vegetation
14. All trees and vegetation identified for retention must be protected in accordance with
AS 4970, Protection of trees on development sites.
15. A qualified person (*) must be engaged for the duration of the works to:
a. Oversee installation of all tree protection fencing prior to commencement of any works
onsite (including any clearing).
b. Supervise tree protection within the development site and frontages, prior to, during
and following construction in accordance with AS4970, Protection of trees on
development sites.
c. Oversee approved tree removal in proximity to retained trees.
d. Undertake a risk assessment of all trees within striking distance of the development
works and site and carry out hazard removal and amenity pruning in accordance with
AS 4373, Pruning of amenity trees.
Page 5 of 21
Document Set ID: 25057225
Version: 2, Version Date: 14/08/2026
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original (SUPERSEDED - Decision Notice OPW26 0033 (As Published).pdf)
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.