NOOSA COUNCIL IDAS Development Application Decision Notice                                                       14 of 51


Water
51.     Sand, silt, mud, paint, cement, concrete, builders waste or rubbish shall not be permitted to enter or be
        placed where it could reasonably be expected to move into a roadside gutter, stormwater drain or a water
        course.

52.     The Developer is advised that in accordance with the Environmental Protection Act 1994 all waste water
        from any excavations or de-watering activities must be treated to remove suspended solids (<50mg/L)
        and maintain the pH within an acceptable range of 6.5-8.5 to ensure contaminants are not released. The
        appropriate monitoring of any waste water discharges shall be undertaken by the Developer.
Protection of Visual and Aesthetic Values
53.     The Landscape Management Report, the Site Rehabilitation Plan, the Environmental Management Plan
        and the Construction Management Plan shall specify the manner in which the visual and aesthetic values
        of the site and the adjoining National Park will be protected and enhanced and the manner in which
        buildings, roads and pathways will be visually screened and visually integrated into the landscape..

54.     Only minor pruning will be permitted of existing tree branches protruding beyond the 10m setback line
        under the supervision of the site arborist. The degree of pruning required will be submitted for approval in
        conjunction with an application for operational works.

55.     No earthworks (fill or cut or earth-spill) shall occur within the 10m intermittent creek setback line.

56.     Retaining walls are to be designed and constructed to provide bridging footing structures as necessary to
        avoid root damage to retained trees.

57.     Upper level pool and lookout earthworks are to be minimal in scale and extent and localised to the
        footprint of the immediate construction. The pool is to be a maximum of 12m long by 4 in size.
        Earthworks are to be temporarily screened from Hastings Street utilising black or dark green shade cloth
        or equivalent material until construction work in this area is fully stabilised. Disturbed soil in this area is to
        be fully stabilised within 10 business days of initial disturbance with either a temporary or permanent
        treatment.

58.     The fence colour of the upper level pool located to the east of Building B shall be non reflective and
        charcoal/ woodland grey in colour. The retaining wall for the pool is to be clad in dark coloured rock, with
        native plantings located in front of it to provide screening.

59.     No shade structures or gazebo shall be erected at the lookout or upper level pool behind Building B. Only
        black, dark brown or navy blue coloured umbrellas shall be used in the vicinity of this pool.

60.     Trees to be removed shall be in accordance with the approved plans.

61.     Disturbance of the upper eastern area of the site to construct the boulder gabion walls shall minimise the
        disturbance to existing native trees and their roots wherever possible. Suitable techniques will be utilised
        to minimise disturbance and damage to this area. Rocks utilised will be grey in colour, with non-reflective
        wire cages.
Environmental Management Plan
Preparation
62.     An environmental management plan (EMP) for the Site shall be prepared and implemented by persons
        holding appropriate environmental and construction engineering qualifications and proven expertise in the
        preparation and implementation of EMPs, to ensure that the impact on the environment of the carrying out
        of the Development is minimised, the Environmental Values of the Site are protected and enhanced and
        the Development is ecologically sustainable.

63.     The EMP shall document in detail how compliance with the Conditions is to be achieved.

64.     The EMP shall demonstrate a high level of environmental care and responsibility and be consistent with
        best practice for developments of this type in similar environments.

65.     The EMP shall detail the Developer’s environmental policy and the proposed environmental management
        system for the Site.

66.     The EMP shall specify to the reasonable satisfaction of the Manager – Land Use:




MSOffice c:\docume~1\shesse\locals~1\temp\bcl technologies\easypdf 5\@bcl@d811b33e\@[email protected]

Used in these records

About this file

File size
301 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

SUPERSEDED Decision Notice - 010.2006.00000823.001 [As Published].pdf · 301 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.