SUPERSEDED Decision Notice - 010.2006.00000823.001 [As Published] · 132006.823
NOOSA COUNCIL IDAS Development Application Decision Notice 29 of 51
LAND DEVELOPMENT
Construction
General
179. The Developer shall cause the Principal Contractor to attend a pre-start meeting with the Manager – Land
Development prior to commencement of any work on Site. At the pre-start meeting the Principal
Contractor is to submit a copy of the Workplace Health and Safety Plan for the Development to Council
for Council’s records. The Workplace Health and Safety Plan shall comply with the provisions of the
Workplace Health and Safety Regulation 1997. The Principal Contractor and supervising engineer are
responsible for compliance with the Workplace Health and Safety Plan. The Developer shall ensure that
there is compliance with the Workplace Health & Safety Plan.
180. The Developer shall ensure the following steps are undertaken prior to commencement of any works on
Site:
180.1. The Principal Contractor shall give the Council Inspector seven days notice of intention to
commence works.
180.2. The Principal Contractor or any of its subcontractors shall not undertake any works unless each
such contractor has public liability insurance in the sum of $10,000,000 and copies of current
public liability insurance policies are submitted to the Council Inspector.
180.3. The Principal Contractor shall nominate a site representative and give the Council Inspector a
telephone number on which the Inspector can reach the site representative any time 24 hours of
the day.
180.4. The site representative shall arrange to meet on-site with the Council Inspector to be informed of
Council’s requirements for construction of access.
180.5. All traffic signage, including that for safety during construction, shall be in accordance with the
Manual of Uniform Traffic Control Devices and Department of Transport (Main Roads Division)
Roadworks Signing Guide.
181. Construction activities are to be carried out only between 7:00am and 6:00pm Monday to Saturday, with
no construction activities on Sundays and public holidays.
182. Access to the Site for the purposes of construction is to be only between the hours of 7:00 am and 6:00
pm Monday to Saturday, and not on Sundays and public holidays. Queuing of construction vehicles is not
to occur in Viewland Drive prior to 7:00am.
183. Works are to be carried out in accordance with the EMP so as to prevent or minimise:
183.1. dust nuisance to residents in the vicinity;
183.2. transfer of dirt and debris on to existing roads; and
183.3. excessive noise.
184. Attenuation of construction noise is to be provided in accordance with the following measures:
184.1. site layout devised to maximise distances to adjoining residences;
184.2. noisy equipment positioned to make best use of natural attenuation – distance and screening;
184.3. ‘silenced’ machinery to be specified; and
184.4. noise mitigation requirements included in all sub-contract specifications.
185. The Developer shall submit to the Council travel routes for the movement of construction vehicles. Minor
residential roads shall not be used for the movement of construction vehicles. Construction vehicles must
not use Morwong Drive. The Developer is advised that there is a 9 tonne load limit on Park Road and the
Developer shall ensure that its contractors and employees are informed accordingly.
MSOffice c:\docume~1\shesse\locals~1\temp\bcl technologies\easypdf 5\@bcl@d811b33e\@[email protected]
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
SUPERSEDED Decision Notice - 010.2006.00000823.001 [As Published]Related documentApplication case desk ↗
About this file
- File size
- 301 KB (small file)
- File type
No other editions are linked here.