213.2.1. Total Nitrogen
213.2.2. Total Phosphorus
213.2.3. Suspended Solids & Turbidity
213.2.4. pH
213.2.5. Salinity
213.2.6. Temperature
213.2.7. Dissolved Oxygen
213.2.8. Trash & gross pollutants
213.2.9. Algal count and identification
213.2.10. Faecal coliforms
213.3. The monitoring shall continue for a period of 5 years from completion of the final stage of
construction.
213.4. For the construction phase for the Resort, at least two per year event and monthly campaign based
water quality monitoring for:
213.4.1. Suspended Solids & Turbidity
213.4.2. Temperature
213.4.3. Salinity
213.4.4. Trash & gross pollutants
213.4.5. Dissolved Oxygen
213.5. In addition to the above, inspections for erosion and deposition, and build up of trash and gross
pollutants should be carried out on a weekly basis during the construction period and corrective
measures implemented.
213.6. An operational phase water quality management plan shall be prepared to address basin
landscape zone and water treatment device water quality maintenance requirements for
stormwater management measures and devices, contingency measures for aquatic plant growth,
loss of vegetation in swales and filter strips, pollution response and algal blooms and should
include a mosquito management strategy.
213.7. Responsibilities are to be clearly delineated.
213.8. Non-compliance with prescribed water quality standards should trigger the implementation of
measures/further testing to rectify.
213.9. Monthly reports on monitoring, incidents, corrective action and plan updates are required to be
submitted to Council. These reports are to be submitted in a form acceptable to the Manager –
Land Development and are to highlight any non-standard results.
213.10. Any stormwater outlet to the creeks on the Site are to be stabilised with appropriate energy
dissipation and local armouring. Regular monitoring of creek erosion is required with appropriate
corrective action specified to ensure a stable creek system. All work to be undertaken to
minimise impacts on the Environmental Values of the creek system.
214. The operational stage components of the stormwater management plan shall be included in the
community management statements for all bodies corporate having control of any part of the Site and
assign responsibilities for compliance in terms of the reasonable satisfaction of the Manager – Land
Development.
MSOffice c:\docume~1\shesse\locals~1\temp\bcl technologies\easypdf 5\@bcl@d811b33e\@[email protected]
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
SUPERSEDED Decision Notice - 010.2006.00000823.001 [As Published]Related documentApplication case desk ↗
About this file
- File size
- 301 KB (small file)
- File type
No other editions are linked here.