5. Revegetation Specification (continued) 5.5 Jute Matting and Open Weave Coir Mesh
5.2 Site Setout
Biodegradable organic materials shall be used to provide immediate and temporary
External and internal boundaries of all rehabilitation areas are to be surveyed and pegged stabilistaion of steep slopes and watercourses during establishment phases of
prior to any rehabilitation works commencing. revegetation works.
5.3 Sourcing Tubestock Plants Open weave coir mesh (minimum 700 gsm) must be applied to the upper bank of the
The following best practice should be applied to plant selection: overland flow path following any required weed treatment, and prior to planting. Open
weave mesh must extend over the top of the bank but stay outside of the bed of the
Have an established root system, but not be pot bound;
watercourse. Open weave mesh is to be appropriately installed and fixed in place as per
Display signs of active growth;
manufacturer’s specifications.
Free from living insect pests;
Jut matting (minimum 750gsm) must be applied to the steep banks following any required
Be sun hardened; and
weed treatment, and prior to planting, and installed and fixed in place as per
Be of sufficient height and suitable for planting onsite.
manufacturer’s specifications.
Sourcing, purchasing, collections and delivery shall be the responsibility of the
5.6 Tubestock Watering Regime
Contractor. It is the Contractor’s responsibility to make sure that plant stock is suitable to
meet specifications. Planting must not occur unless the soil moisture conditions are adequate and should not
Plants in transit shall be kept moist, protected from the sun and damaging winds and be undertaken during periods of prolonged dry conditions.
shall be securely held in positions such that movement is restricted. At the time of planting, each plant must be watered suitably. Initial watering of plants must
5.4 General Planting Procedure include the addition of organic liquid conditioning product in accordance with
manufacturer’s instructions (e.g., Nutri-Tech Black Gold /Essential Plus 1-0-1).
The following planting procedure should be adhered to:
Ongoing watering of plants is to occur to encourage plant establishment and growth and
Plant species are to be sun-hardened, in a healthy condition and not be root- shall include the following regime:
bound or under-developed;
Two times per week for the first fortnight;
Planting is not to occur when soil moisture is inadequate. All plant specimens are
to be watered well prior to planting; Weekly for the following four weeks; and
Dig holes 20-30 mm deeper than the length of the planting container and twice as Ongoing watering required during dry conditions or rainfall is insufficient for
wide; healthy plant growth to occur.
Fill holes with water if soil is dry;
Plant and backfill with excavated soil and gently press down to remove air
pockets;
Mound excess soil to form small dam wall around tube to hold water; and
Spread mulch around base of plant stock.
Document Set ID: 22990715
22224495
Version: 1, Version Date: 24/04/2024
22/12/2022
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
The download may take up to a minute.