09/0982 - Op Works - Prescribed Tidal Works - Extensions to Jetty [As Published] · 142009.982
{Sunshine Coast Checklist - Applications Involving L Land
Regional Council Development & Land Use Sections
IDAS APPLICATION
This checklist should be used for any IDAS application. Please check each of the following items before accepting an
application at the counter.
4. - APPLICATION. FORMS
1.1. Form PartA .
1.1.1. Ensure that the form is fully completed and is a current version. A
1.41.2 In the case of an MCU or Op Works below the. high-water mark, owner’s consent is required.
1.1.2.1 If there are multiple owners, the consent of each owner is required.
1.1.2.2 If the owner of the land is a company, either ACN No, Company name clearly indicated by
signatory) or Company Seal required.
4.2 .Form4 Part B-R Supporting Information
1.1.2 Ensure that for each box checked on Form A, the relevant additional Forms B-R are attached.
be 1.1.2.1 Ensure that each of Forms B-R which are attached are fully completed.
(2. DAS: ASSESSMENT. CHECKLIST Rise j t Ae ,
2.1. Ensure that relevant sections have been checked and/or completed with regard to referrals EZ] qe
° 2.2 Ensure correct parts of Form 1 are provided where required (ie most common are Part J for
Clearing Vegetation, Part N for Contaminated land and Part P for Prescribed Tidal Works) ]
3. “ENVIRONMENTALLY RELEVANTAGTIVITIES =,
3.1 Ensure that Part G is completed if EPA referral is required.
3.2 Where EPA is delegated to Council (see * in ERA checklist), ensure that the correct application
fee is pad and recorded op the application. (Refer Environmental Health for fees) ~
4, FORM:2 - ‘CHANGE. ARPROVALS?* 3.00
4.1 Ensure that relevant items have been checked and/or completed including information regarding
applicant details along with owners consent if not current owner of land as shown on Council records.
If over multiple properties on one or more sites, consent of Body Corporate is required.
5. PLANS. ° Se 7 : eta a .
eS 5.1. Ensure that generally at least 6 sets of the Plan of Development 6 for Reconfiguration and Operational Zz
Works) accompany the application. In addition ensure that each set is complete.
§.2 Ensure that 1 of the copies of the Plan of Development is in an A3 or A4 format and is a
unbound.
Co tae
Sa tae Ree |
Dye tke
6. "SUPPOR' iGHNFORMATION
“6.1. Ensure that generally at least 6 copies of any report accompanies the application (5 for Reconfiguration | —
and Operational Works). If the application is accompanied by a covering letter, ensure that it is
capable of reproduction.
6.2 Inthe case of reports, ensure that 1 of the copies is in an A3 or A4 format and is unbound.
6.3 Additionally an electronic version is preferred where possible for ease of electronic record keeping -
7... FEE. . : Dou fsa Sos Tor Bg :
7.1. Ensure that the application fee, as determined from the Council’s adopted scale of fees,
accompanies the application or has been paid.
« Land Use MCU applications; MCU applications including a Lot reconfiguration; Prescribed Tidal Works; Operational
Work if Jetty or if including Landscaping.
« Land Development Lot Reconfiguration applications and Operational Work not including Landscaping
Please DO NOT leave the application at the counter and DO NOT deliver the application to Records.
NSC g.Manduse\administrative processes\application checklist.doc
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalFull text of the other 47 pages
Page 2
DAS REFERRAL AGENCIES TRIGGERS (Most frequent referrals)
Please refer to IDAS Checklist for,complete. fe me
pt A ee}
YES:
Please tic
ve
Ke
rg
‘Department of Main Roads (Concurrence or Advice)
« State Controlled Road
Dept Natural Resources & Water
¢ ~=6Acid sulphate soils (Advice)
« Clearing of native vegetation on freehold land (Concurrence)
Environmental Protection Agency (Concurrence)
* Environmentally Relevant Activity (for non-devolved Council as EPA)
e Contaminated land
* Environmental Management/Contaminated Land Register
» UXO
* Land recently used as a ‘notifiable activity’
* Industrial land changed to sensitive uses (eg school)
e Coastal related development.
e Koala habitat
e Wetlands (Advice only)
Queensland Transport (Concurrence)
° Railway
. Public Passenger Transport
Energex or other responsible entity (Advice)
° Electricity Easements/Substations
Maschinwe Sesfeda
DIP (Concurrence)
. SEQ Regional plan
VARIOUS : «
° Conservation estate (Advice)
R STATE AGENCIES + TRIGGERS
1 a 7
i
s a Rew. eT bet ods eh uhh
Department of Natural Resources and Mines
EPA
For further clarification refer to IDAS Guides prepared by Department of Infrastructure & Planning.
NSC g:\landuse\administrative processes\application checklist.doc
Page 3
Trish Sweeney oe os
From: 0 boat hire [[email protected]] ye
Sent: Wednesday, 5 August 2009 10:32 AM
To: Trish Sweeney
Subject: Re: Prescribed Tidal Works application
Hi Trish,
Thanks for your email and sorry we haven't replied before now as I haven't
been in and didn't see your email until today. Yes it's fine to change the
Lot no. to 160 as I put down the original plan No.151 by mistake. I will t,
also get the signed consent form dropped into you today.
I thought I would also give you a bit of history on boat numbers even though
our approved lease with DNR states our area is for "namely boat hire’.
purposes , and purposes incedental thereto including the mooring of vessels'' *
The jetty pontton extensions. within our leased area"is simply designed for ;
ease of boat mooring and manouvering within | our area.,The boat numbers we
have and will have fluctuate from time to time depending on’ their condition
and timing when they need renewing or changing the style of vessel due to
market demands. We also may moor a couple private directos boats within our
a. .
currently are down to 13. pontton boats and 10-runabouts and frontrunner
style boats plus kayaks. When my partner bought: the business in+ September;
'04 there wére 15 pontoons, 5 runabouts: 4 half cabing 8° cataramans- vand's?
kayaks’ existing for some 15 years prior’ ‘to’ that time. .
eo wife *
cs x
ve
7h
If ‘you require any further details please do not Hesitate to. contact me.
Regards Rod. Baker
cere original Message aa----
From:. "Tris r Sweeney", <Trish. Sweeney@sunshinecoast. qld.gov.au>
To: csenquir'ies@oboathire,. com>.
Sent: Friday, . 1°2009..4:25 PM
Subject : ry Prescott ibed’ Tidal Works application
Hi Rod cor Brad,» 3 an
I have been through your: application and confirmed with DERM that you do not
‘ uire résource entitlement:.as’ the proposal is in. accordance with the
@eec of the lease,and in thé lease area. (which is whdt you said!) “#8
Tt will however, require referral to DERM (previously EPA) and Qld Transport
(Maritime Services) as concurrence agencies but we will advise you. of that : ‘
when the acknowledgment notice is issued. Just a couple of things - you
refer on the application form to Lot 151 CP 908649, however all our records
for 222 Gympie Tce show Lot 160. Are you happy for me to amend the form?
We require’ your consent as lessee to the application (Director/s of Noosa
River Enterprises P/L) so if you could either pop in and sign the forms or
fill in the attached form and return to me that would be great.
Regards,
<<Owner's consent (company) .doc>>
Trish Sweeney | Administration Officer
Planning Assessment - North I Tewantin Office
Sunshine Coast Regional Council
Ph: (07) 5449 5293 | Fax: (07) 5447 1062
FRI GIORGI III IORI CII IOISIIIOOI III IOI III IOI IOI III IO III OI IO IOI I ICICI
kK
To find out more about the Sunshine Coast Council, visit your local council
office at Caloundra, Maroochydore, Nambour: or Tewantin. Or, if you prefer, |
: * : yt &
Page 4
, §2-64 Currie Street, Nambour, a 4560
4
Trish Sweeney
From: Grant Renee [[email protected]}
Sent: Friday, 31 July 2009 3:39 PM
To: Trish Sweeney
Subject: RE: Jetty at Noosa
Confirming this relates to 222 Gympie Terrace Noosaville.
Regards
Renee Grant’: . ‘ 7: .
Senior Land: Officer . * s
State Land Asset Management , . / ae
L&VS, Nambour . :
Ph: 07 5451 2245
‘Fax: 07 5451 2260 4
Email: [email protected]
www. www.derm.qid.gov.au
PO Box 573;Nambour Q'4560
_From: ‘Trish. Sweeney [mailto: ‘Trish. [email protected]]
Sent! Friday, 31 July 2009 2: :34 PM
my
Pears
“To::Grant'Renee™~ * “ /
. Subject: RE: “Jetty a Noda of Loe, ’
“s 6 a dey a ae” ed . tet ’ *
thanké'so mic Rénee; can you please just confirm by return email that this information jelated to 222
Gympie Terrace; Noosaville. Dive og ee ,
“ Have a great weekend! “". . : my .
none Original Message: rr
From: Grant Renee [mailto:Renee. Grant@iderth, qld.gov.au] Ay OF
Sent: Friday, 31 July 2009 2:42 PM . °
To: Trish Sweeney fo, "
Subject: Jetty at Noosa
Hello Trish,
mae
vet ea TMS,
$ ve wi eee
Page 1 of2 =
sk 4
_ 31/07/2009
In regards to our telephone conversation earlier, | am advising that as.long as the improvements
are within. the Lease area and_are in accordance with the purpose of the lease, this department
‘has no requirements provided the works are undertaken in accordance with Sunshine Coast
Regional Council development approvals.
Regards
Renee Grant
Senior Land Officer
State Land Asset Management
L&VS, Nambour
Ph: 07 5451 2245
Fax: 07 5451 2260
Email! [email protected]
«37 fa AH-
Page 5
Meo SR Rate Oe Tye eer Dee egy me RT mma SEE opal
2 BSR Sy PRE Roe Be
Trish Sweeney
From: _ Trish Sweeney
Sent: Friday, 31 July 2009 4:26 PM
To: ‘[email protected]’
Subject: Prescribed Tidal Works application “
Hi Rod or Brad,
| have been through your application and confirmed with DERM that you do not require resource entitlement as the
proposal is in accordance with the purpose of the lease and in the lease area. (which is what you said!)
It will however, require referral to DERM (previously EPA) and Qld Transport (Maritime Services) as concurrence
agencies but we will advise you of that when the acknowledgment notice is issued. Just a couple of things - you refer
on the application form to Lot 151 CP 908649, however all our records for 222 Gympie Tce show Lot 160. Are you
happy for me to amend the form? We require your consent as lessee to the application (Director/s of Noosa River
Enterprises P/L) so if you could either pop in and sigh the forms or fill. in the attached form and. return. tom me that would
be great. . : vn » boa fy :
Regards, : : ro : ,
wner's consent
(company).doc
re ty at rae :
Trish, siveeney \ Administration ‘Officer “OT oe : 2
Planning Assessment North | Tewantin Office -""« ~ Set mo i
Sunshine Coast Regional Council
Ph: (07) 54495293 | Fax: (07) 5447 1062
Page 6
INTEGRATED PLANNING ACT 1997 Part A. Version 3.1, 3 March 2008
(kes
Part A RECEIVED
29 JUL 2009
Common details
OTE: Answer all questions unless directed to go to a particular question. Refer to the end of the form for advice on how to complete this form.
Formy|f{Development Application
approval that may be.
Company/organisation name {if applicable) [Noosa River Enterprises Pty Ltd
Individual applicant/Contact person (if there is more than one applicant, provide additional applicant details on an attachment to this form)
Postal address {222 Gympie Tce, Noosaville QLD 4566
Contact telephone number [07 54497513 Mobile phone number 10418708545
Facsimile number 07 54740991 e-mail address [email protected]
[Details of the premises (Le. the land on which the development is proposed “- refer to the advice at the cnd oF the form) ph 2, cage
1. Identify the premises by completing Table A, or Table B and/or Table C (ensure adequate information is given to identify the premises)
Table A [f the application is for a mobile and temporary Environmentally Relevant Activity (ERA), complete Table A only. Then go to Q2.
| 1
OR
Table B Street address for the premises (tick applicable box/es below and insert 1 property description it in the table. Identify each lol in a separate row.)
() (L] Street address / tot on pian for the premises (Appropriate for most applications including building applications); OF
(ii) ([] Street address Aot on plan for the land adjoining or adjacent to the premises (Appropriate for development in water e.g, jetty,
pontoon et) (ote Loton plan deta may be obtahet from We docurTerts a Rate’ notice, or fom he local goverment)
Gympie Tea, Noosaville
AND/OR
Table C Coordinates and/or a map of the premises (Appropriate for development in remote areas, over part of a fot, in water (e.g. channel dredging in Moreton
Bay) etc.)
ct wt fee : : 8 sma
(1 weses
(F other -
2. Identify if any of the following apply to the premises by completing Tables D, E, or F. (Note: in most instances, the premises will not involve any of
the following characteristics, however some applications may involve one or more of these characteristics - complete only if applicable)
Page 7
INTEGRATED PLANNING ACT 1997 Part A. Version 3.1. 3 March 2008 Table D Compete if the premises are adjacent to or associated with a water body, watercourse or aquifer (e (e.g. river, creek lake, cra) ~ Name of water body; watercourse of aquifer (known). -™ . [1 | Noosa River Table E Complete if the premises are on Strategic Port Land under the Transport Infrastructure Act 1994 S"". ‘Ltn plain description for strategic port land#. so 8 : [1 Table F Complete if the premises are in tidal water : Name of local government for the fal area ( appicable) - |.” .. Narita of port aisthority for the tidal area (fappicatie) .**-" [1 | sunshine Coast Regional Counct 3. Indicate the total area of the premises on which the development) is proposed: (Note: The total area may inctude land both above and below water) . Total area of premises-x2i! fa. 74a. 1,658.00 Odor? [Thectares (Tick applicable unit) [Existing use of the premises _-- . ° : : ] 4. — Current use/s of the premises: (e.g. vacant land, house, townhouses, apartment building. shop, service station, school, sugar cane farming etc.) [+ [cat hire ] 5. Are there any existing easements on the premises? (e.g. for vehicular access, electricity, overland flow, water etc.)7 & No 0 Yes - Ensure the type, location and dimensions of each easement are included in plans, submitted with the application [Proposal details oe " oo 1 6. Brief description of the proposal (e.g. 6 unit apartment building, 30 lot residential subdivision, a bore, aquacutture) To erect two additional pontoon jetties with a walkway ramp within our leased area for the purpose of mooring boats. 7. Does the poposal include new buildings or operational work (including any services) on the premises? ih} No oO Yes - Ensure the nature, location and dimensions of the proposed works are included in plans, submitted with the application (Resource entitlement (if applicable) - futher information 's provided in the advice section at the end of the forin er eee ) 8. Does the application involve taking or interfering with a State resource and therefore require a resource entitlement? (e.g. the application involves State land (leased and freehold), declared Fish Habitat areas, taking quarry material, taking or interfering with water under the Water Act 2000, etc.) No - Got0Q9 0 Yes - Complete Table G - provide details for each evidence required on a separate row, if applicable. Evidence of resource allocation or entitlement must be submitted with the application. You do not need to answer Q9 - go to the next section. iOwner'’ '§ CONSENt (if applicable) further information is provided in the advice section at the end of the form... s = “ | 9. Complete Table H for applications involving a material change of use; reconfiguration of a lot; work on land below high-water mark and not within a canal as defined under the Coastal Protection and Management Act 1995; or work on rail corridor and defined under the Transport infrastructure Act 1994 « provide details for each owner on a separate row, of on an attachment to this form if applicable. ': Premises Owner's name’s |.- — .: Details of the premises owned * #2” and postal address" __ (street address or lot on plan description) Noosa River Enterprises P/L 222 Gympi ‘ . " pie Tce, Noosaville QLD 4566 1 222 Gympie Tce, Noosaville 151 OLD 4866 Lot 151 on RP908649 * Owner's signature cannot be provided on the form if you intend to submit the application electronically. Owner's consent must be provided to the assessment manager on an attachment containing appropriate written documentation of the owner's consent. If the owner is a company, $127 of the Corporations Act 2001 (Cwealth) details how a company may sign as owner. Templates for the provision of owner's consent are available on the IPA website . Table H a fAttachments | and supporting information (Complete Table I - USe a Separate row for each type of attachinent or information, including information required “* funder this Part} Please ensure af documentation submitted with this form, iackucing other Parts of Form 7, of owner's consent, etc, ard securely attached to this Part of the Form. Y= Desenption of attachinent of information = -[' * - Tile (applic sbi Table | | (og Part of Form 1, anette ce plicable ‘ pion, ry: (0g, Gero! auton Joes Seaton Repo cote [1 [Pian of pntoon jetty extentions
Page 8
INTEGRATED PLANNING ACT 1997 Part A. Version 3.1. 3 March 2008
Portable Long Service Leave (PLSL) tevy (Appicable for certain buticing and construction work vahied over $80,000 only) j
10. The Portable Long Service Leave Levy (PLSL) is not applicable to this application if any of the following apply: ( Tick box i applicable)
(J) the application seeks a preliminary approval only,
(C the application is not for building and construction work under the Building and Construction Industry (Portable Long Service
Leave) Act 1991, section 3AA (e.g. the application is only for a change of use, or for the following types of work carried out solely for
farming purposes: land clearing, site preparation, earthworks, fences, fodder harvesting, clearing of encroaching vegetation, clearing of
regrowth, thinning vegetation or controlling weeds or pests);
[X] all costs, that relate to the work both directly and indirectly, are less than $80,000, inclusive of GST; or
(C1 the work is being carried out under an owner-builder permit issued under the Queensland Building Services Authority Act 1997 -
Complete and submit a OLeave Notification and Payment Form (no payment required if owner-builder permit number staled). [he receipted form must be
sighted by the assessment manager before a development permit can be given.
41. Is payment of a PLSL levy applicable to this application? (Refer to Q10 and the Advice below for more information)?
[XI No - Endorpata
(1) Yes - Answer 12 below
OFFICE USE ONLY (For use by the Assessment Manager / Private Certifier) (Optional)
rts] 2-3 74] sonia] zal n [RR] OS Knap] we | 07/982
L aa NOTIFICATION OF ENGAGEMENT OF PRIVATECERTIFIER 2 os: |
To: Council. | have been engaged as the private certifier for the building work referred to in this application.
QLEAVE NOTIFICATION AND PAYMENT (for completion by assessment manager or private certifier if applicable)
Desaipionof te work “| Leave Project Number "| Amount paid (8){ “ Date paid "| Om Slatted by:Name of cffcer who sighted the
. . . ec pet” | anager! ee
4
Privacy Statement
The information collected on Form 1 will be used by the Department of infrastructure and Planning (DIP) in accordance with the processing and assessment of your Application,
Your personal details will not be disclosed for a purpose outside of the IDAS process, except where required by tegisiation (including the Freedom of information Act 1992) or as
required by Parliament. This information may be stored in a DIP database. The information collected will be retained as required by the Public Records Act 2002.
Advice for completing Part A
General advice
° Part A of IDAS Development Application Form 1 must be completed and accompany all development applications. The applicant is responsible
for answering all questions fully and correctly, untess following a response there is a statement to go directly to another question. The
Assessment Manger may refuse to receive an appiication that is not properly made.
* The IDAS Assessment Checkist must also be completed for all development applications, other than those requiring assessment against the
Building Act 1975 only, i.e. those applications requiring the compietion of Parts A and B only.
Applicant details
j° If the appiicant is a company or organisation, a contact person must be nominated. The applicant's signature is not required to be provided
under the IPA.
Page 9
oe a “a.
Page 10
INTEGRATED PLANNING ACT 1997
Part P. Version 2.1. 3 March 2008
Name of RPEQ of equivatent * | John Norden and Associates
RPEQ No. or equivalent
Contact matling address: ~ _|Office 16 Tewantin Plaza, Moorindil St, Tewantin Q 4565
(Contact telephone number ~ 154497137
Contact facsimile number eo 154497172
Reference riumber of all plans fo which this is cortcaton ees
Mandatory information «
5. Confirm the following mandatory information accompanies this application.
Plaris and written documentation Pa 1 Soe an
(i) The location and Givonelore fe popoaed Wal wick Risdon hes abuting the proposed |
work and the tidal and on which the work is proposed to be located [x] Confirmed | over the counter
(ji) All other structures on the waterfront and within 20 metres of the proposed works [X] Confirmed over the counter
(il) __ The current location of Lowest Astronomical Tide (LAT), Highest Astronomical Tide (HAT) and
Mean High Water Springs (MHWS) (Confirmed —_| over the counter
(iv) The slope angies of the beds and banks of the tidal area (1 Confirmed
(v) Details of the proposed work in accordance with the IDAS code for prescribed tidal work in the
Coastal Protection and Management Regulation 2003, schedule 4A (e.g. physical appearance, lighting, Confirmed over the counter
signage, earthworks, public access, infastructure, structural components, engineering design standards)
(vl) The finished levets of the proposed works [EX] Confirmed over the counter
(C1 Confirmed
(vii) — Oetalls of the largest vessel, if any, to be moored at the structure
[EX] Net applicable
(vi) Evidence that the proposed work will not prejudice the access rights of adjoining property CL Confirmed
owners DX] Not applicable
OFFICE USE ONLY
Date Received Reference Numbers LC ti‘“‘CSCSCSY EPA cost code | 433061
Advice for completing Part P
L
L
L
General advice
Part A must also be completed for all IDAS development applications.
1 The applicant is responsible for answering all questions fufly and correctly, untess following a response there is a statement to go directly to another
question.
nh When paying fees to the Environmental Protection Agency by electronic funds transfer (EFT) use the process from the information sheet Electronically
paying fees to the Environmental Protection Agency (EPA) and attach the form Electronic Funds Transfer (EFT) payment notification to the application.
1. For further information about completing this form go to:
IDAS Guide 24 {Prescribed tidal work}
Eooaccess wepsite
Qi
A development permit authorises development to occur, while a preliminary approval is a step in the approval process and does not authorise
development to occur.
Qa
A Registered Professional Engineer of Queensland (RPEQ), or the interstate equivatent, may certify that the proposed work complies with the
design and safety provisions of the IDAS code for prescribed tidal work in the Coastal Protection and Management Regulation 2003, schedule
4A. The provision of the certification may reduce the applicable fee for assessment of the work by the jocal goverment.
Page 11
Company Owner’s consent to the making of
an IDAS development application
I, Bradley Edward Gray (insert Seegin
Director, AND
I, Rodney Paul Baker (insert name in full),
both directors {insert Company position in full — i.e.
another director, or a company secretary — strike out above name and company position if not applicable, i.e.
for a proprietary company that has a sole director who is also the sole company secretary, only that director
needs to complete the owner’s consent),
of Noosa River Enterprises P/L. (insert name of company)
owner of premises identified as follows
222 Gympie Tce, Noosaville Qld 4566 (insert street address; lot on plan
description; or coordinates of the premises the subject of the application)
consent to the making of a development application under the Integrated Planning Act 1997 by
Brad Gray (insert name of applicant)
on the premises described above for the purposes of
Pontoon jetty extensions and dredging (insert details of the proposed
development, eg a change of use for 3 storey apartment building))
K EF fe? (signature of Directors)
i tor)
Signed on the B74 dayof 4U6u57._, 2009.
(signature of Director/ Company Secretary)
Signed onthe _§ 7/* day of A ug UST ; 2009.
Company seal (if usea)
U_ 05/08/2009 c:\documents and settings\user\my documents\council and risk etc\owner's consent (company).doc
-+
Page 12
INTEGRATED PLANNING ACT 1997 Part P, Version 2.1, 3 March 2008
{ti i dppicabie sei) .
(i Private use
j Jetty, pier or wharf .
x jetty pier or wha &} Non-private use
. . (Private use
me) Boat ramp or spillway [1 Non-private use
CJ Private use
ss Mooring pi Develo: it Permit
& (i jooring pile Non-private use O pmeni
Private use imi
Cl Ww) Deck or boardwalk DPrvate [_] Prefiminary approval
(Non-private use
(Private use
Pontoon
OW m (O Non-private use
C1 Private use
i Revetment, sea wail or retaining wall .
Ow 9 (Non private use
oO (vii) Other (e.g. abutment, basin, bridge, breakwater, dam.
dock, dockyard, embankment, groyne, pipeline or other }[_] Private use
underground service etc.) - Provide details below
(INon-private use
2. Is the application within a cul-de-sac, a bend in a waterway or other location where the side boundaries of the lot connected to the
work and neighbouring lots are not at right angles to the waterway?
& No
Oo Yes - Submit, with the application, photos of any constructed neighbouring structures, or information about approved but unconstructed
neighbouring structures.
{Adjoining property access and evidence.of support, oe a Ba tes
3. Is the application supported by evidence that the proposed work will not prejudice the access Tights of adjoining property owners?
—XJNo =] Yes - Compiete Q3(a)
Certification
4, Has a Registered Professional Engineer of Queensland (RPEQ) or interstate equivalent certified that the works comply with the design
and safety provisions of the State IDAS code for Prescribed Tidal Works contained in the Coastal Protection and Management
Regulation 2003?
a )
IX) Yes - Provide detaiis below
Page 13
IDAS Assessment Checklist, Version 22
Answering the following questions will assist you in determining which sections of the checktist must be completed for your application. If
unsure, phone or visit your local government or log onto the DIP website www.dip.gid.gov.au for help _
For all IDAS development applications (vce thase for building work requiring assessment against the 8uilding Act 1975 only} ~ complete Section 1.of this
checklist wa a
Does the application. seek approval to make a material change of use of the premises? (1 Yes |] No
ifyes - complete Section, 26f fhis checklist. , ty .
Does the application ‘seek ‘approval to reconfigure a lot? ‘ . ~~ |E] Yes | No
ifyes - complete Section 3 of this checklist and Part F of IDAS Application Form 1." If the premises are completely within a single local
government area assessment is by the focal | government.
, Does the application seek approvat to carry out operational work? : , . Ves (J No
e@ if yes.- complete Section 4 of this checklist, : 2
Does the application seek approval to carry out duilding work requiring assessment against the Fisheries Act 1994? C1 Yes {J No
if yes - complete Section 5 of this checklist.
Have you received a referral agency response under section 3.3.2.0f the IPA, in relation to this development (1 Yes
application? :
ifyes - complete Section 6 of this checklist.
Does the application seek approval to carry out building work requiring assessment against a local government (1 Yes |.
planning scheme? .
>
if yes - complete Form { Part E of IDAS Application Form 1, Assessment is by the local government. *
Does the application seek approval to carry out building work requiring assessment against the Building Act 19757 C1 Yes
ff yes - goto Appendix 1 of this checktist for advice on buiiding referrals. Complete Part 8 of DAS Apptication Form 1. Assessment is by a
building certifier.
Do you wish the application to be assessed against superseded planning scheme? CL] Yes
Hf yes - complete Form 1 Attachment 1.
Is the application for development completely or partly on Cairns or Mackay airport {and under the Airport Assets C] Yes
(Restructuring and Disposal} Act 2008?
ifyes ~Assessment is by the Department of infrastructure and Planning. Complete Form 1 Part D of IDAS Application Form 1 if the application
is for a material change of use. and Part E if for building or operational work. Also, the application must be referred to the focal government as
Advice Agency.
Page 1
Page 14
INTEGRATED PLANNING ACT 1997 IDAS Assessment Checklist, Version 22
SECTION 1 Section 1 must be completed for all applications that require completion of the IDAS Assessment Checklist.
HERITAGE
141A
Is apy part of the proposal intended to be carried out on a Queensland heritage place under the Queensland Heritage Act 1992?
No-Gotoar.18 ([] Yes ‘
If yes, has an exemption certificate for the proposal’ been issued under the Queensland Heritage Act 1992?
(Yes DNo
If no, is the proposed work liturgical development under Queens/and Heritage Act 1992, section 78?
Yes CINo .
If no, is the work being carried out by the State?
Ol Yes oO No - (Complete Form 1, Part C1) This application requires assessment by the Environmental Protection Agency {EPA).
if EPA is not the Assessment Manager for the application, the EPA has jurisdiction as Concurrence Agency.
1, Schr loble 2 Rem 18
IPA, schedule 8, part
He 3, than 2: IP Regu
1.18
Does the proposal involve development intended to be carried out on a place entered in a local heritage register under part 11 of the
Queensland Heritage Act 1992, other than if place is on Cairns or Mackay airport fand?
[I No - Goto a1.2 OYes
If yes, does the following apply?
(i) development for public housing, as defined by the integrated Planning Act 1997 (IPA), chapter 5, Oo No [] Yes @
pari6
(ii) development carried out by the state on land designated for community infrastructure under the [-]No (Yes
IPA, chapter 2, part 6
(ii) development that is exempt from assessment against a planning scheme under the IPA, schedule []No [L] Yes
If no to all of (i) — (ii) above - (Complete Form 1, Part C2) This application requires assassment by the relevant local government as Concurrence
Agency,
IPA, schaduile 8, sit 1 lable § tem 2A. IP Rogutation, schedule 1, part &. table 5, em 2: Augart Aunete (Reviruclurina and Ossposays Act 2006, ¢ 54,
“REMOVING QUARRY MATERIAL; WILD-RIVERAREA-- ---- Fees ot oe - . de
1.2 | Does’the proposal involve removing quarry material from a watercourse or lake as defined under the Water Act 2000?
No-Gotoar3 (Yes
I yes, is an allocation notice required under the Water Act 2000?
No C1 Yes
if yes, is any part of the removal of quarry material intended to be located in a declared wild river area under the Wild
~Rivers Act 2005? :
| No — (Complete Form 1, Part Kx) This application requires assessment by the Department of Natural Resources and Water (NRW). if NRW is not
the Assessment Manager for the application. the agency has jurisdiction as Concurrence Agency.
{J Yes - Unless the application is consistant with any properly development plan eppiying {0 the land, the Assessment Manager must reluse to receive #.
(Complete Form 1, Part Kr). f NRW is nat the Assessment Manager for the application, the agency has jurisdiction as Concurrence Agency.
Subject to the declaration for the relevant wild river area, assessment is also required for the purposes of the Wild Rivers Act 2005,
teeny fable 2. itany 47, a) Seti table 5 trai 2 (ws fata A ), section GACY
1} In this IBAS Assessment Checklist, the term proposal refers to he proposed use, work or lot reconfiguration the subject of the application.
Page 2
Page 15
»
a
INTEGRATED PLANNING ACT 1997
ENVIRONMENTALLY RELEVANT ACTIVITY; WILD RIVER AREA” *
13
Dees the proposal involve an environmentally relevant activity (ERA), other than a mining activity or a petroleum axivily?
No-Gotoa.4 (Yes
If yes, is any part of any ERA intended to be located in a wild river area declared under the Wild Rivers Act 2005?
(No
If no, is there a code of environmental compliance under the Environmental Protection Regulation 2008 for every aspect of each
proposed ERA?
O No - (Complete Form 1, Part G) This application requires assessment by the Administering Authorily. If the Administering Authority is not the
Assessment Manager for the application, the agency has jurisdiction as Concurrence Agency. Go lo Q1.4
(7 Yes - Goto 14
DYes * .
li yes, is any extraction ERA intended to be located in waters?
£1 Yes
If yes, wil the application be accompanied by an allocation notice for that ERA, as defined urider the Environmental
* Protection Act 1994, section 73AA(9}?
oO Yes - Unless the application is consistent with any property development plan applying to the land, and the epplication is accompanied by an
allocation notice, the Assessment Manager must refuse to receive it. (Complete Form 1, Part G). This application requires assessment by the
Administering Authority for the purposes of both the Environmental Protection Act 1994 and, subject to the declaration for the relevant wild river area,
the Wild Rivers Act 2005, If the eministering Authority is not ihe Assessment Manager for the application, the agency has jurisdiction as Concurrence
Agent
C1 No- An application for the ERA will be taken to be'not properly made and the Assessment Manager must refuse fo receive it, «
_ FINo ‘ : rep tte vos tea
If no, is any part ofa any ERA intended to be located i in, a high preservation area? :
Les ‘ > ole .
If yes, is each proposed ERA one oof the following? : te
(i) a sewage ERA CI No!L] Yes.
(ii) awater treatment ERA : (No! C] Yes ;
(ii) a dredging ERA C1 No! [1 Yes |
(iv) an extraction ERA carried out outside waters and the activity is a borrow pit of not oO No: Oo Yes :
. more ‘than 10;000m3 for -
ie Specified works under the Wild Rivers Act 2005; or
ws“ residential complexes, as defined under the Environmental Protection Act 1994 . am
(vy) a a écreening ERA. carried out outside waters and the activity is for - : CI Noj £1 Yes |
>, Specified works under the Wild Rivers Act 2005; or. . ° :
. + "for residential complexes, as defined under the Environmental Protection Act 1994 i
(vi) a crude oil or petroleum product storage ERA and the activity is - ONo| Yes |
« for résidential complexes, as defined under the Environmental Protection Act 1994; & . : :
« carried out outside a designated urban area, as defined under the Wild Rivers Act:
‘
wk
2005 *
(vii) An exempt environmentally relevant activity, as defined under Environmental Protection {[]No!(1 Yes:
Act 1994, in a designated urban area, as defined under the Wild Rivers Act 2005 : ft
If yes to any one of (i) - (vii) above - Uniess the application is consistent with any property development plan applying fo the land, and,
the application is accompanied by an allcation notice, the Assessment! Manager must refuse fo receive it. (Complete Form 1, Part G).
application requires assessment by the Administering Authority for the purposes of the Environmental Protection Act 1994. If the. alee,
Administering Authority is not the Assessment Manager for the application, the agency has jurisdiction as Concurrence Agency. Subject to™
any limitations in the declaration for the wild river area and the Wild Rivers code, assessment is also required for the purposes of. the Wild
Rivers Act 2005. In particular. a sewage ERA, a water treatment ERA and an ‘exempt environmentally relevant activity‘ do not require
assessment for the purposes of the Wild Rivers Act 2005 if the ERA is proposed in a designated urban area.
If no to all of (3) - (vii) above - An application for the ERA/s will be taken to bé nol properly made and the Assessment Manager must.
refuse to recoive it,
C] No. - Answer the following question on the next page
Page 3
Page 16
INTEGRATED PLANNING ACT 1997
IDAS Assessment Checklist, Version 22
ENVIRONMENTALLY RELEVANT ACTIVITY; WILD RIVER AREA (continued)
Ifo, is any ERA an extraction ERA intended to be located outside waters?
oO No — Unless the application is consistent with any property development plan applying to the land, and the application is accompanied by
an allocation notice, the Assassment Manager must refuse to receive it. (Complete Form 1, Part G). This application requires
assessment by the Administering Authority for the purposes of both the Environmental Protection Act 1994 and the Wild Rivers Act
20085. if the Administering Authority is not the Assessment Manager for the application, the agency has jurisdiction as Concurrence
Agency.
(J Yes
Ifyes, does the ERA meet the following? A
{i) the activity is located inside a flood management area and a borrow pit of not (No!L Yes
more than 10,000m°for -
¢ — specified works under the Wild Rivers Act 2005; or
+ _ residential complexes, as defined under the Environmental Protection Act 1994
(ii) the activity is located outside a flood management area . (No [] Yes
If yes to either (i) or (ii) above - Uniess the application is consistent with any property development plan applying to the land, and
the application is accompanied by en allocation notice, the Assessment Manager must refuse to receive it. (Complete Form 1,
Part G). This application requires assessment by the Administering Authority for the purposes of both the Environmental
Protection Act 1994 and, subject to the declaration for the relevant wild river area, the Wild Rivers Act 2005, If the Administering
Authority is not the Assessment Manager for the application, the agency has jurisdiction as Concurrence Agency.
If no to both (i) and (ii) above - An appiication for the ERA wil! be taken to be no! properly made and the Assessment menager must
refuse to receive it.
IPA schedule 8, part |. tabla 2, dem 1; IPA, schedule 2, part 1. taiie 5, dems 3 and ¢: 1P Regulation. scheuite 2, iabie 2. hams { and 23, Environunedtai Protection Act 1996, szelan 7RAA twild
ver area}, Wid Kivers Aci 2008. section 424; relevant wild over daclaratony Wid Rivers Code,
WITHIN THE LIMITS OF A PORT
14 Ilsa
Yy part of the premises within the limits of a port under the Transport infrastructure Act 1994?
No. Gotoa.5 *{] Yes
If yes, is that part of the premises below high waler mark?
No
~ (Yes - ifanswers to questions in other sections of this checklist indicate that the proposed development is assessable under IPA; schéduile
8 - Answer (a) to (c) below. This application requires assessment by the Port Authority for the land., if you answer no to (a), (b) and
(c) below, the Port Authority for the Port has jurisdiction as Advice Agency.
(a) [s any part of the proposal within 200m of a shipping channel or an entry and exit shipping corridor for the Port?
> >
No LJ YeS — The Port Authority for the Port has jurisdiction as Concurrence Agency.
(b) Is any part of the proposal within 1,000m of a swing basin, a commercial fishing wharf, a mooring, anchorage or spoil grounds?
C1No (11 Yes - The Port Authority or the Port has jurisdiction as Concurrence Agency.
(c) Is any part of the proposal within 1,000m-of a planned port facility identified ina land use plan?
(No (1 Yes - The Pon Authority for the Port has jurisdiction as Concurrence Agency.
# Regulation, schindiiie 2 tabla 2, dems 1 and 16.
DECLARED FISH HABITAT AREA
1,5 | Oogs any part of the premises adjoin a declared fish habitat area under the Fisheries Act 1994?
No - Goto 01.6
Yes - if answers to questions in other sections of this checklist indicate that the proposed development is assessable under IPA, schedule 8,
this application requires assessment by the Department of Primary Industries and Fisheries (DPI&F). If DPI&F is not the Assessment
Manager for the application, the agency has jurisdiction as Advice Agency.
26.
JF Regulation, sclexide 2, fata 2. th
Page 4
Page 17
INTEGRATED PLANNING ACT 1997
COMMUNITY INFRASTRUCTURE Pe ke et
1.6
Is any.part of the premises designated for community infrastructure?-
jo-Gotoar7 (] Yes
If yes, is the community infrastructure intended to be provided by a public sector entity?
(No 0 Yes
If yes, is the land owned by or on behalf of the State?
Chyes ([INo
if no, is the development for the following?
(i) For the designated purpose Lino [Yes
(ii) \ Cartied out by, or on behalf of, the designator No OYes
If no to either or both (i) or (ii) above, is the proposed development assessable under the planning: scheme?
O No | Yes - This application must be referred to the Queensland Government department administering the Act authorising the
“ development for the designation as Concurrence Agency,
Ir Feguieton § sohedule 2, table 3, tent ?.
[Does the | proposal involve the ‘establishment or expansion of a waste water disposal system?
(No - End of Section? [_] Yes
Ifyes, is any‘part of the disposal system proposed to bé located | in an area declared to be a catchment area under. the Water Act 2000?
CJ No; End of Sectiin 1, iE Yes’ :
, lf yes, is the, ‘proposed waste water disposal system an environmentally relevant activity (ERA) unde? the Enwonmentl
Protection Act 19942. * 0 :
(1 Yes - End of Section 1 CINo
{fno, is the proposed develypment involving the waste water disposal system assessable under the planning scherne?
Oo No - End of Section 1 oO Yes - This application 1 requires assessment by the Department of Natural Resources and Water (NRW) as
. Concurrence Agency. End of Section
EP Reegquaitationn, sitendtite 2. taka 3, tein 8,
”
Page §
Page 18
IDAS Assessment Checklist, Version 22 INTEGRATED PLANNING ACT 1997 we ae eh ged TR ae tae , re ‘, sod See Page 6
Page 19
INTEGRATED PLANNING ACT 1997 IDAS Assessment Checklist, Version 22
SECTION 4 Section 4 must be completed when the application seeks Spprovel to cary out o, operational work,
PLANNING SCHEME ag. i. ;
41 ls the proposed operational work assessable under any State ® planning regulatory provisions?
CINo
If no, is the proposed operational work assessable under the planning scheme?
oO No - Goto Q4.2 | YeS — Complete Form 1, Part E and answer Q4.1.1 - 4.1.7 below
tes .
If yes, is the proposed operational work-assessable under the planning scheme?
[LI] No = Answer Q4.1.1- 4.1.7 Yes — Complete Form 1. Part € and answer Q4.1.1 - 4.1.7 below
I STATE-CONTROLLED ROAD, at
814:1.4 “Ils any’part of the premises located in part of a future State-controlled rc road, or F within 100m of a State-controlled road?
No
does it exceed the threshold?
CINo (2 Yes - This application must be referred to the Department of Main Roads (OMR) as Concurrence Agency.
(1 Yes
If yes, is all of the proposed operational work associated with either -
« — Reconfiguring a lot that increases the total number of lots, or increases the total ruber ot lots
: . aS 7 . my
ok x . 7 . . a
«. 7 _ tino. - Aniswer (a) - “bow cm
(a) Is any of the proposed operational work associated with’access to a State-controlled toad?
(b) 4s any of the proposed operational work for filling or excavation?
Clno = LYes
If yes, is the operational work proposed in a future State-controlled road not defined by route?
1" No - This application must be referred to the Department of Main Roads (DMR) as Concurrence Agency
Ol, Yes:; This application must be referred to OMR as Advice Agency.
Pep, Ono ‘L1Yes ,
“IL yes, is the operational work proposed in a future State- conirolted toad not defined by route?
oO No - This application must be referred to the Department of Main Roads {OMR) as Cohcuménce Agency. ‘
4 : 1 Yes - This appiication must be referred to OMR as Advice Agency. . . .
fan, schuadule 2 tae 2. dams 3 1? 410) ~
No «+ | Yes - This application must be referred to the Department of Main Roads (oMR) Bs Concurrence Agency.
*
oT]. abutting the State- controlled road eke ot . . foe
If no, is the proposed operational work for filling or excavating listed in integrated Planning Regulation 1 998, schedule 5 and
+ Amateriat change of use that is assessable under the planning scheme; or - : Ono 'C] Yes
we (c) “Does any of the proposed operational work involve the redirection or intensification of site stormwater from the land,
“f through a pipe with a cross-sectional area greater than 625cm? that directs stormwater to a State-controlléd road?
ACID SULFATE SOILS
Oey {opment involving Acid Sulfate Soils?
[No~ Gotoas.t3 (J Yes
‘If yes, is the natural ground level of any point where work is being carried out less than 20m AHD?
CINo CL] Yes
It yes, does the proposed operational work involve the following?
{i} Excavating more than 1,000m# of soil or sediment at or below 5m AHD
{ii) Filling the premises with 1,000m® or more of material with an average depth of 0.5m on
land, soi! or sediment at or below 5m AHD
iabie A hea €, Slats
4.1.2 {Is any 0 of the operational work proposed i in a local government area a isted* ‘in State Planning Foley 2/02: Planning and Manegig
LNo Cyes *
f
oP
7 gh tt
If yes to either or both (i) or (ii} above - This application must to be referred to the Department of Natural Resources and Water (NRW) as *
Advice Agency
4) Aurukun, Bowen, Brisbane, Broadsound, Bundaberg, Burdekin, Burke, Burnett. Caboolture, Cairns, Calliope, Caloundra, Cardwell, Carpentaria, Cook, Cooloola, Douglas,
Fitzroy, Gladstone, Gold Coast, Hervey Bay, Hinchinbrook, Isis, Johnstone, Livingstone, Logan, Mackay, Maroochy, Maryborough, Miriam Vale, Mornington, Noosa, Pine _ a
Rivers, Redcliffe, Rediand, Rockhampton, Sarina, Thuringowa, Tiaro, Torres, Townsville, Whitsunday
Page 27
2 gts,
Ban
wor
Page 20
INTEGRATED PLANNING ACT 1997 IDAS Assessment Checklist, Version 22
EASEMENTS AND SUBSTATIONS
4.1.3. |Is aniy of the proposed operational work for filling or excavation?
No-Gotoas14 []Yes
I yes, is the filling or excavation associated with reconfiguring a lot?
Yes No - Answer both (a) and (b) below
(a) Is any part of the premises Subject to an easement in favour of a distribution entity or transmission entity
under the Electricity Act 1994? :
[] No Yes
If yes, is any of the operational work proposed to be iocated in any part of the easement?
CI No L_] Yes - This application must be referred to the entity as Advice Agency.
(b) Is any of the operational work proposed to be located within 10m of a substation site under the Electricity Act
1994?
IN) LJ Yes - This application must be referred to the entity responsible for the substation as Advice Agency.
JP Regulation, sefedila 2, lable 2dem ta} iP Rew
spheduuie 2, table 2, tem 10th}
4.1.4 |\s any part of the premises subject to an easement in favour of the holder of Pipeline Licence Number 1 issued-under the Petroleum
‘ Act 1923 for the construction or operation of the Moonie to Brisbane strategic pipeline under that Act?
LINo-Gotoas15 LC] Yes
If yes, is any of the proposed operational work for filling, excavation, compaction, drilling, boring or piping, not associated with e
reconfiguring a lot?
CINo OyYes
If yes, is any of the operational work proposed to be located in any part of the easement?
No O YeS - This application must be referred to the licence holder as Advice Agency,
iP Regukiion, schedule 2. tabla 3, tem 17.
PUBLIC PASSENGER TRANSPORT : >
415 ils any, of the proposed operational work fisted in schedule 13C of the ° Integrated Planning Regulation 18 1998 and 1 does it exceed the
specified threshold? a we
No - Go to Q4.1.6 Ol Yes - This application must be referred to Queensland Transport (QT) as Concurrence Agency.
schedule 2. table 3. item 14
RAILWAY SAFETY AND EFFICIENCY
4.1.6 | Is any of the proposed operational work listed in schedule 13D of the integrated Planning Regulation 1998 and does it exceed the
specified threshold? :
vA No - Go to. 04.1.7 oO YeS - This application must be referred fo Queensland Transport (Q7) as Concurrence Agency.
ip
ip
th
KOALA CONSERVATION (outside SEQ urban footprint)
4.1.7 |\s afly part of the premises in a koala conservation area or koala sustainability area, other than in an SEQ urban footprint area? ° e@
No - Goto 04.2 O Yes
if yes, is all of the proposed operational work associated with a material change of use or reconfiguring a lot for which referral
is required in relation to koala conservation the. e, did you answer ‘yes’ fo all questions in either Q2. 1.8.0F Q 3. 12}?
CYes-Gotoosz2 [No
Iino, is the proposed operationa! work for a domestic activity, as defined by the Environmental Protection Act 1994?
C1 Yes-cotoas2 [INo
If no, will the activity result in the following?
. _ (i} Clearing of native vegetation over an area greater than 2,500m2 (LINo fl Yes |
(ii) Extracting gravel, rock or sand from an area greater than 5,000? i Lino !( Yes
{iil) Excavating or filling an area greater than 5,000m2 {Ne {Fes
Hf yes to one or more of (i) — (ili} above - This application must be referred to the Environmental Protection Agency {EPA} as
Concurrence Agency.
1 schadule 2 lalte 2. dem 19.
WILD RIVER AREA - although legislation provices for assessment of operational wor
for residential, commercial and industria! development for the purposes ot the
Wild Rivers Aci 2005, currenlly no declarations for any of the wild river areas apply the Wi
Fs Code lo that type of development.
Page 28
Page 21
INTEGRATED PLANNING ACT 1997 IDAS Assessment Checklist, Version 22
| ASSOCIATED WITH RECONFIGURING ALOT. RESIDENTIAL, “COMMERCIAL OR, INDUSTRIAL DEVELOPMENT INA WILD RIVER
AREA~:
42 Is any’f the proposed operational work associated with reconfi iguring 2 a alot and the reconfiguration i is also assessable?
CAN Gotoo.3 (_]Yes
If yes, is any part of the premises in a wild river area declared under the Wild Rivers Act 2005?
oO No - (Complete Form 1, Part } If the premises are completely within a single toca! government area, the operational work associated with reconfiguring
is assessed by the local government.
(1 Yes
If yes, is the proposed operational work for residential, commercial or industrial purposes outside a designated urban area,
as defined by the Wild Rivers Act 2005?
No - (Complete Form 1, Part E) if the premises are completely within a single focal government area, the operational work associated with
reconfiguring is assessed by the focal government,
O Yes (Complete Form 1, Part E) ifthe premises are completely within a single local government area, the operational work associated with
* reconfiguring is assessed by the local government, and subject {o.the declaration for the relevant wild river area, assessment by the local
government is required for the purposes of the Wild Rivers Act 2005.
wt % table 3, 2em 1¢c}. Wed Rivers cade iicte. the code doas nol cami
contain appizahle provsions for msxienta!
434, any pant of the premises i in an interim koala habitat protection area?
: 0 - Go to. 04,38 Yes
1... Ifyes, is the proposed operational work for clearin
+ planning regulatory provisions (koala regulatory pI
~ EINo-cotoosas [1 Yes. cee " a
‘ If-yes, does the following apply?
| |() the proposed clearing is for a domestic activity, as defined in
| the koala regulatory provisions 3
the proposed clearing is for a building or structure of less than 500m?
gross floor area
‘iy the proposed clearing will result in -
° the clearing of less than 2,500m? of native |
vegetation, as defined in the koala regulatory i
. provisions; and | ‘
|
{
| * — no.loss of mature koala habitat trees, as defined in
i
i
tive vegetation, as defined in draft. South East Queensiand Koala State
ClYes
Ces |
(Dyes |
the’ koala regulatory provisions.
|
i(iv) the proposed clearing is consistent with a development approval |
for a material change of use, reconfiguring a lot or operational i
work that has not lapsed, where 1
* the application for the development approval was |
made before 12 December 2008 ; or
* — the development approvai was given under Division i
2 of the draft South East Queensland Koala State
ing ing regulator
If no,to all of (i) - iv) above - The proposed operational work for clearing native vegetation may not occur and an application involving that! -
component cannot be made. *
*? Native vegetation is defined in the draft South East Queensland Koala State planning regulatory provisions. The term ‘clearing’ has the meaning given in the integrated
Planning Act 1997, schedule 10 (dictionary).
Page 29
Page 22
INTEGRATED PLANNING ACT 1997
IDAS Assessment Checklist, Version 22
VEGETATION CLEARING; KOALA CONSERVATION (outside SEQ urban footprint); WILD RIVER AREA
43B
Is afty of the proposed operational work for the clearing of native vegetation to which the Vegetation Management Act 1999 applies?
No -Gotoa44 L1 Yes
‘tf yes, is the proposed clearing assessable (i.e. not an exception) under schedule 8, part 1, table 4 of the IPA?
CINo-Gotoass L1Yes
If yes, is the proposed vegetation clearing a relevant purpose under the Vegetation Management Act 1999, section 22A
for one or more of the following?
(i) A project declared to be a significant project under the State Development and Public Works [[_]No |(J Yes
Organisation Act 1971, section 26
(ii} Necessary to control non-native plants or declared pest CNo jC} Yes
(ili) To ensure public safety : C)No |[) Yes
(iv) For establishing a necessary fence, firebreak, road or vehicle track, or for constructing Cino | Yes
necessary built infrastructure, if there is no suitable alternative site for the fence, firebreak,
road, track or infrastructure
(v) Anatural and ordinary consequence of other assessable development for which a (no |O1 Yes
development approval as defined under the Planning Act was given, or a development .
application as defined under the Planning Act was made, before 16 May 2003
(vi) For fodder harvesting CINo {C1} Yes
(vii) For thinning CNo jC) Yes
(vii) For clearing of encroachment vt sey ve ut LINo O Yes
(ix) For an extractive industry ” (No |[1Yes
(x) For clearing regrowth on leases issued under the Land Act 1994 for agriculture or grazing Cino |) Yes
purposes ae Se
(x) For clearing regrowth on freehold land, or ‘indigenous ini ina awild tiver high present Lino {C1 Yes
-atea wee . ce
If no to all (i) - (xi) above - The clearing is not a relevant purpose and the Assessmen! Manager must refuse fo recelve the application,
If yes to any one of (i) — (xi) above, is the proposed clearing associated with a material change of use or reconfiguring a
tot for which referral is weaned in relation to clearing vegetation (ie. did you answer 'yas' to all questions in either Q2.1.4 or Q 3.3)?
C1 Yes - Goto 04.4
oO No - Answer (a) {b} and (c} on the next page of this Checklist.
Page 30
Page 23
INTEGRATED PLANNING ACT 1997 IDAS Assessment Checklist, Version 22
‘ ‘ Rivers Act 2005 applying to the land?
{a) Is any of the proposed clearing in an area declared as an area of high nature conservation value (other than a
wild river high preservation area) or an area vulnerable to land degradation under the Vegetation Management
Act 1999?
Oo No - (Complete Form 1, Part J). This application requires assessment by the Department of Natural Resources and Water {NRW).
If NRW is not the Assessment Manager, the agency has jurisdiction as Concurrence Agency.
D1 Yes
If yes, is any of the proposed clearing for (v), (vi), (ix) or {x) above?
0) No ~ (Complete Form 1. Part J), This application requires assessment by the Department of Natural Resources and Water
(NRW). IFNRW is not the Assessment Manager, the agency has jurisdiction as Concurrence Agency,
Oo Yes - The Clearing is nat a relevant purpose and the Assessment Manager must refuse to receive the application
{b) Is any of the proposed clearing inthe high preservation area of a declared wild river area?
Oo No - (Complete Form 1; Part J). This application requires assessment by the : Department of Natural Resources and Water (NRW). |
ff NRW is not the Assessment Manager, the agency has ‘furis fiction as Concurrence Agancy.,
LJ Yes
Ifyes, is any of the proposed clearing for the following purposes?
_()._.. For (i), (vi), (vil) or (ix) above C1No | ClyYes
1 (ii). For (x) or (xi) above and in a high preservation area outside of a (No [1] Yes
| fegistered area of agriculture as defined under the Vegetation
Management Act 1999 ot . Satie oa be
a atte, tlfne to'either or both (i ii ) or (ii) ‘above's Subj sit to the declaraiion for ihe relevant’ ‘ld river area, ‘ihe ‘application
) requires aéséssment for the, purposes of td Wild Rivers Act 2005 - Complete Form 1, Part J. This. application
. requifes assessment by (he! Department of Natural Resources and Water (NRW)... NRW is not the Assessment
Manager, thé agency has jurscicton as Concurrence Agency.
A Itfyes to either or both (i (' ) or (i) above, s there a property development plan approved under the Wild
El No - The clearing is nota relevant purpose and the Assessment Manacer must refuse (0 receive the application. ‘
C] Yes ~ Unless the application is consistent.with any approved property development plan applying to the land, the
” Assessment Manager must rétuse to receive it, Subject to the declaration for the relevant wild river area, the
ce . ' application requires assessment for the purposes of the Wild Rivers Aci 2005 - If an application is made
¢2.complete Form 1, Part J: This application requires assessment by the Department of Natural Resources and
Water (NRW). If NRW is not the Assassment Manager, the agency has jurisdiction as Concurrence Agency.
ny of the proposed clearing | in akoala conservation” area or koala sustainability area, other than.it in an
“SEQ urban footprint area? . we,
CINo -Gotoasa [7] Yes :
“lf yes, is any oft he proposed clearing associated with reconfiguring alot for which referral is required in
relation to proposed clearing in a koala conservation area or koala 1 sustainability area a th @, did you answer
‘yes’ tor ail questions in Q3,12)? : . r :
(lYes-cotoass CINo , : :
If no, is any of the proposed clearing over an area greater than 2,500m2?
LI No - Goto. 4.4
D1 Yes ~ This application must be referred to the Environmental Protection Agency (EPA) as Concur
Agency.
Page 24
INTEGRATED PLANNING ACT 1997 IDAS Assessment Checklist, Version 22
TAKING OR INTERFERING WITH WATER; WILD RIVER AREA
44
t's any of the proposed operational work for any thing constructed or installed that allows, under the Water Act 2000, for taking or
interfering with water from a watercourse, lake or spring (other than using a water truck to pump water; and other than under the Water
Act 000, section 20(2}, (3) or (5)), or from a dam constructed on a watercourse or lake?
No - Go fo 04.5 (71 Yes - Answer (a) and (b) below
(a) Are the operations mentioned as self-assessable development in the following?
(i) A water resource plan under the Water Act 2000 Cino - (Yes
(ii) A wild river declaration under the Wild Rivers Act2005 (JNo [J Yes
(iii) A regulation under the IPA or the Water Act 2000 CNo D Yes
If no to all of (i) to (iii) above - This application requires assessment by the Department of Natural Resources and Water (NRW). IfNRW Is not the
Assessment Manager for the application, the agency has jurisdiction as Concurrence Agency. Go to (b}
(b) Is any of the proposed operational work to be carried out in a wild river area under the Wild Rivers Act 2005?
OYes
If yes, is the work for the following?
(i) A water pump . LINo | (1 Yes (Complete Form 1, Part Ki)
(ii) Water storage : CNo : D1 Yes (Complete Form 1, Part a). e}
(ili) Gravity diversion from a watercourse CINo | [1] Yes (Complete Form 1, Part Ky)
(iv) Watercourse diversion : CINo | C1 Yes (complete Form 1, Part Ke)
(v) Other work for taking or interfering with water CINo | (Yes (complete Form 1, Part Ks)
If yes to any one of (i) to (v) above ~ if any part of the proposal relates to operational work that interferes with water in a high preservation
area, or in a nominated waterway {other then for a dam or weir), the application will be taken lo be not properly made and the Assessment
Manager must refuse to receive it. All ather proposals are subject to the declaration for the relevant wild river area, and assessment mey
be required for the purposes of the Wiki Rivers Act 2005. The application will require assessment by the Department of Natural Resources
and Water (NRW). If NRW is nat the Assessment Manager for the application, the agency has jurisdiction as Concunsnce Agency.
(Complete the relevant Form 1, Part K as indicated in the table above if an application is made.)
CI No-
no the wrk or the folowing? _ cnn am wegen
(i) Awater pump ’ LINo {17 Yes (Complete Form 1, Part Ki)
(ii) Water storage - : LJNo (1 Yes (Comptete Form 1, Part Ky)
(iii) Gravity diversion from a watercourse ee CINo ON Yes (Complete Form 1, Part Ky)
(iv) Watercourse diversion CINo 3 (1 Yes (Comptete Foun 1, Part Ky)
(v) Other work for taking or interfering with water LINo Oves {Complete Form 1, Part Ke)
if yes to any one of (i) to (v) above - The application will require assessment by the Department of Natural Resources and Water (NRW), If NRW
“is not the Assessment Manager for the application. the agency has jurisdiction as Concurrence Agency.
_ (Complete the relevant Form 1. Part K as indicated in the table above.) @
4.5
is any of the proposed operational work for any thing constructed or installed that allows, under the Water Act 2000, for taking or
interfering with artesian water (other than using a water truck to pump water)?
No ~ Goto 04.6 oO Yes ~ (Complete Form 1, Part Ki) This application requires assessment by the Department of Natural Resources and Water (NRW). If
NRW is not the Assessment Manager for the application, the agency has jurisdiction as Concurrence Agency.
idanian schedule f, pan
ut woler)
2 table 2 tam at
Page 32
Page 25
INTEGRATED PLANNING ACT 1997 . IDAS Assessment Checklist, Version 22.” ft
TAKING OR INTERFERING WITH WATER; WILD RIVER AREA (continued) *
46 Is any of the proposed operational work for any thing constructed or installed that allows, under the Water Act 2000, for taking :
overland flow water (other than using a water truck to pump water)? :
No-Gotoas7 [1] Yes - Answer (a) and (b) below .
(a) Are the operations mentioned as assessable development i in the following?
(i) A waterresource plan under the Water Act 2000 No (Yes
(il) A regulation under the IPA or the Water Act 2000 ONo O Yes
If yes to either or both of (i) or (ii) above - (Complete Form 1, Part Ka}. This application requires assessment by the Department of Natural
Resources and Water (NRW). If NRW is not the Assessment Manager for the application, the agency has jurisdiction as
a Concurrence Agency. “
: (b) Is any of the proposed operational work mentioned as assessable in a wil river declaration and to be caried out in a wild
tiver area declared under the Wild Rivers Act 2005? * °
oO No oO Yes - if any part of the proposal relates to operational work in a high preservation area other than works stated ina + wild river
+ . . . deciaration for the area to be assessable development ior which a development application may be made, the epplication will
. be laken to be not properly made and the Assessment Manager must refuse to receive it’ Ailother ‘Proposais are subject to the
declaration for the relevant wild river area, and assessment may be required for the purposes of the Wild Rivers Act 2005.
{Complete Form 1, Port Falf an epptcation is mods)
e IPA, schext
Rivers Act 200
chetiuie |. part J. tabig
fees Act OO. 34:
we TAT Ts! any of the proposed operational work for any thing constructed orinstalled that allows, under the Wate’ Act 2000; for taking or
. terfering with ‘subartesian water (other than using awater truck’ to ‘pump water)? |
yooh 0 - Goto a4.8 *
GGA (wild river area),
“4 Yes” : ay . .
"<1 '* Ifyes, are the operations mentioned as aisessable development in the following? co Ss
(i) Awater resource plan under the Wafer’ Act 2000 [LNo LJ Yes ,
*(ii). A regulation under the IPA or the Water Act 2000" ™ DNo UO Yes
>
lf yes to either or both of or (ii) above - (Complete Form 1, Part K;) This appticalion requires assessment by the Department of Natural
“ Resources and Water (NRW). If NRW is not the Assessment Manager for the application. the agency has jurisdiction as
so Concurrence * Agency
‘ YNARP, Pea cern RE
} wale),
48 : Does any of the. proposed operational work ‘or any thing constructed or installed that allows, under the Water Act 2000, for interfering
yooays ith overland flow water (other: than using a water truck to pump water)? . m
. ase. Got6049 “Yes ~ Ansiner both (9) and (b) below
* “(a ) is the proposed operational work to be carried Gut in a floodplain management area of a wild river area declared under the
uo Wild Rivers Act 2005?
(1 Yes
. * "If yes, indicate what the proposed operational work relates to
@ ™ (i) Specified works forthe area a (No (J Yes fs
(i) Work state in the relevant wild river declaration to be [] No ClYes .
assessable development for which an application may : .
be lodged -
If yes to either or both of (i) or (ii) above - (Complete Form 1, Part Kis, Subject to the declaration for the relevant wild river area, asse:
may be required for the purposes of the Wild Rivers Act 2005)
-LINo
‘ If no, are the operations mentioned as assessable development in the following?
(i) A water resource pian under the Water Act 2000 CJNo Yes
(ii) A regulation under the IPA or the Water Act 2000 CI No C1 Yes
. . os . res
If yes to either or both of {i} or (ii) above - (Complete Form 1, Part Kis} This application requires assessment by the Department of. Natural
Resources and Water (NRW). If NRW is nol the Assessment Manager ‘or the application, the agency has jurisdiction as Concurrence Agency.
(b} Is the interfering with overland flow water proposed in an area declared under the Water Act 2000 to be a drainage and |
embankment area (other than a wild river floodplain management area) and declared to be assessable under that Ad?
oO No oO Yes - (Complete Form 1, Part K:2} This application requires assessment by the Department of Natural Resources and Waler ©
(NRW). Hf NRW is not the Assessment Manager for ihe application, ihe agency has jurisdiction as Concurrence Agent
Page 33
Page 26
INTEGRATED PLANNING ACT 1997 IDAS Assessment Checklist, Version 22
TAKING OR INTERFERING WITH WATER; WILD RIVER AREA (continvea)
4.9 — |\s the proposed operational work for the following?
(i) For the construction of a referable dam as defined under the Water Supply (Safety []No {] Yes
and Reliability) Act 2008
(ii) To increase the storage capacity of a referable dam by more than 10% CNno ClyYes
If yes to either-or both of (i) or (ii) above - (Complete Form 1, Part Ks) This application requires assessment by the Department of Natural Resources and
Water (NRW). IFNRW is not the Assessment Manager for the application, the agency has jurisdiction as Concurrence Agency,
IPA scheduls @ peut 1, table 4, hem 4: 1P Re pedula 2. tabla 2, tem 10, :
TIDAL WORK; WILD RIVER AREA
4.10 | Is any of the proposed operational work tidal work, other than excluded work defined under the IPA?
LI No - Goto a4.11 ‘eS — Answer (a) and (b) below
{a)__ Is.any of the proposed tidal work prescribed tidal work? .
Eyes ‘
If yes, is any of the proposed prescribed tidal work to be carried out in a wild river area declared under the Wild Rivers
Act 2005?
lo
Ifno, is the work proposed in a canal? : e
[4No
If no,.is any of the proposed tidal work for a marina with more than 6 vessel berths?
No - (Complete Form 1, Part P). if the Environmental Protection Agency (EPA) is not the Assessment Manager for the
application, the agency has jurisdiction as Concurrence Agency. The application also requires assessment by Queensland
Transport (Maritime Safely Qld) as Concurrence Agency.
oO Yes — (Complete Form 1, Part P). if the Environmental Protection Agency (EPA) is not the Assessment Manager for the
application, the agency has jurisdiction as Concurrence Agency. The application also requires assessment by Queensiand
Transport (Marilime Safety Qid) as Concurrence Agency and Qid Fire and Rescue Service as Advice Agency.
> C1 Yes >
| oe is any of the proposed tidal work for a marina with more than 6 vessel berths? 4-
No - (Complete Form 1, Part P). This application must be referred to Queensland Transport (Maritime Safely Qid) as
i Concurrence Agency. oF .
{ oO Yes - (Complete Form 1. Part P). This application must be referred to Queensland Transport (Maritime Safety Qid) as
Ln. ~ Concurrence Agency and Qld Fire ang Rescue Service as Advice Agency.
C Yes.
It yes,.is all of the proposed prescribed ti tidal work for specified works under the Wild Rivers Act 2005?
: Lalo - ‘An application for the operational work will be taken fo be not properly made and the Assessment Manager must
i refuse to receive it.
! ‘L1Yes
If yes, is the work Proposed i in a canal?
cine , @
{fno, is any of the proposed tidal work for a marina with more than 6 vessel berths?
oO No — Unies the application is consistent with any property development plan applying to the land, the Assessment
. Manager must reluse to receive it. (Complete Form 1, Part P} If the Environmental Protection Agency (EPA) is
i not the Assessment Manager for the application, the agency has jurisdiction as Cancurrence Agency. The
application also raquies assessment by Queensland Transport (Maritime Safety Qid) as Concurrence Agency
and assessment for the purposes of the Wild Rivers Act 2005,
QO Yes ~ Unloss the application is consistent with any property development plan applying to the land. tho Assessment
Managar must refuse to receive it. (Complete Form 1, Part P) If the Environmental Protection Ageiicy {EPA) is
not the Assessment Manager for the application, the agency has jurisdiction as Concurrence Agency. The
application also requires assessment by Queenstand Transport (Maritime Safety Qid) as Concurrence Agency
whee . oe - and Qid Fire and Rescue Service as Advice Agency. Subject tothe declaration for the relevant wild river area, the |] —
application also requires assessment for the purposes of the Wild Rivers Act 2005.
C1 Yes .
} If yes, is any of the proposed tidal work for a marina with more than 6 vessel berths?
i) No - Unless the application is consistent with any property development plan appiying io the iand, the Assessment
Manager must reluse to receive it, (Complete Form 1, Part P) This application must be referred to Queensland
i Transport (Maritime Safety Old) as Concurrence Agency. Subject to the declaration for the relevant wild river
: avea, the application also requires assessment for the purposes of the Wild Rivers Act 2005.
O Ye@S - Unigss ihe application is consistent with any property development plan applying to the land, the Assessment
Manager must refuse to receive it. (Complete Form 1, Part P) This application must be referred fo Queensland
Transport (Maritime Safety Qld} as Concurrence Agency and Qld Fire and Rescue Service as Advice Agency.
The application also requires assessment for the purposes of the Wild Rivers Act 2005,
aa No - Go to the first question on the next page of this Checklist
Page 4
Page 27
INTEGRATED PLANNING ACT 1997
AL: WORK} WILD. RIVER AREA (continued)
fino, is any of the proposed tidal work to be carried out in a wild river area declared under the Wild Rivers Act 2005?
[Yes
If yes, is all of the proposed operational work for specified works under the-Wild Rivers Act 2005?
LINo - An application for the operational work will be taken to be not properly made and the Assessment Manager must
refuse fo receive it.
CyYes
If yes, is any of the proposed tidal work for a marina with more than 6 vessel berths?
O No - Uniess the applic consisteni with any property development plan applying to the land, the Assessment Manager
must refuse ta receive it. (Complete Form 1, Part M) This application requires’ assessment by the Environmental Protection ,
Agency (EPA). If EPA is not the Assessment Manager for the application, the agency has jurisdiction as Concurrence '
Agency. The application also requires assessment by Queeiisiand Transport (Maritime Safely Qid) as Concurrence Agency
and, subject to the declivation for the relevant wild river area, assessment for the purposes of the Witd Rivers Act 2005.
. O Yes - Unless the application is cansislent with any property development plan applying tothe lad, the Assessment Manager
‘must refuse to receive it, (Complete Form 1, Part M) This application requires assessment by't the Environmental
Protection Agency (EPA). If EPA is nol the Assessment Manager for the application, the agency has jurisdiction as
Concurrence Agency. The application also requires assessment by Queensland Transport (Maritime Safety Qld) as
Concurrence Agency and Qld Fire and Rescue Service as Advice Agency. Subject to the’ declaration for the relevant wild
river area, the application also requires assessmeht for the purposes of the Wild Rivers Act 2005,
OS oo If no, is any.of.the proposed tidal work fora marina v with more than 6 6 vessel berths?
ne * Oo No- (Complete Form.1. “Part M), This ‘application requires asséssment ‘by the Environinénia Protection Agency (EPA), IT EPA
. . is not the Asséssment Manager ‘for the application, the agency has jurisdiction as Concurrence Agenicy. The application
, a “t also requires assessment by Queensland Transport (Maritime Safety Qid) as Concur¥éncé Agency..." .
> Cl Yes ~ (Complete Form 1,'Part M) This application requires assessment by {he Environmental Protection Agency (EPA), 1fEPA
“dy is not the Assessment Manager for the application. the agency has jurisdiction as Concurrence Agency. The application
. also requires assessment by Queensland Transport (Maritime Safety Qld) as Concurrence Agency) and a Fire and
Rescue Service as Advice Agency.
(b) Is any of the proposed tidal work fo be carried out in one’or more of the following tidal areas?
{i) One only local government tidal area LINo [Yes |
Hii) Starting i in one local government tidal area and-extending into another local government tidal [_]No |L] Yes
area (but i ini no.strategic port tidal area) i
- .A(ili)’ In two of. mofe local government tidal areas but not starting in either local government tidal area |] No. |] Yes ;
r(iv) One only strategic port tidal area oy oy “CINo -}E1 Yes | ‘
. aa (vs cA tid Hared that isnot.a strategic port tidal area.or a 5 local government tidal area O No TE] Yes
"Note: The: answers yoir piovide i in (i) - (v) above may affect who the Assessment Manager| is for the application.
Hens dA and §
Page 35
Page 28
INTEGRATED PLANNING ACT 1997 , : IDAS Assessment Checklist, Version 22
COASTAL MANAGEMENT DISTRICT; WILD RIVER AREA
411
Is any-of the operational work proposed to be carried out within a coastal management district?
jo -Goioast2 [Yes
It yes, is the proposed operational work for the following?
(i) _ Interfering with quarry material on State coastal land above high-water mark (No |Z Yes
{i) Disposing of dredge spoil or other solid waste material in tidal watera : : CI No |(1 Yes:
(iii) Draining or allowing drainage or flow water or other matter across State costal land above high-water LJNo | Yes
mark .
(iv) Constructing or installing works in a watercourse where the works are nat assessable under IPA, (1 No | Yes
schedule 8, part 1, table 4, items 3 or 4
(v) Reclaiming land under tidal wateru CI No | Yes
(vi) Constructing an artificial waterway, other than a canal, associated with reconfiguring a lot . CI No | Yes |
(vii) Constructing an artificial waterway that is a canal, associated with reconfiguring a lott (_]No |D Yes
(viii) Constructing an artificial waterway not associated with reconfiguring a lot on land, other than State C1 No }L1 Yes
coastal land, above high-water if the maximum surface area of water on the waterway is at least 5,000m?
(ix} Constructing a bank or bund wall to establish a ponded pasture on land, other than State coastal tand, (no (Yes
above high-water mark @
(x) Removing or interfering with coastal dunes on land, other than State coastal land, that is in an erosion CI nNo |[J Yes
prone area and above high-water mark
If yes to one or more of (i} - (x} above, is any of the proposed work to be carried out in a wild river area under the Wild Rivers Act
, 2005?
a No - (Complete Form 1, Part M) This application requires essessment by the Environmental Protection Agency (EPA). if EPA is nol the Assessment
Manager for the application, ihe agency has jurisdiction as Concurrence Agency. if yes, above, to any shown botd and marked with the symbol ™,
the application also requires assessment by Queensland Transport (Marine Safety Qld) as Concurrence Agency.
Cl Yes >
if yes, is all of the proposed operational work for specified works under the Wild Rivers Act 2005?
Oo Yes - Unless the application is consistant with any properly development plan epplying (0 the land, the Assessment Manager musi refuse to receive it .
{Completa Form 1, Part M) This application requires assessment by the Environmental Protection Agency (EPA). If EPA is not the Assessment
Manager for the application, the egency has jurisdiction as concurrence Agency. If yes, above, to any shown bold and marked with the symbol, the
application also requires assessment by Queensland Transport (Marine Safety Qi) as Concurrence Agency. Subject to the declaration for the relevant
wild river area, the application also requires assessment for the purposes of the Wild Rivers Act 2005.
oD No - An application for the operational work will be taken fo be not properly made and the Assessment Manager must refuse to receive it.
a] 5 1P Fi is 2 lable 2 itanis 12
AL AINS Rivers Art 2005, secti
16: 1P Requshon. schedule |. att 2. tebhy 4, Hains 4A and 8, Coastal Pr
Hon and Marasgenent
WATERWAY BARRIER WORKS; WILD RIVER AREA
4.12
Is any of the. proposed operational work for constructing or raising waterway barrier works under the Fisheries Act 1994? . :
CINo-cotoar13 «= ] Yes ,
If yes, is any: of the proposed operational work to be carried out in a wild river area declared under the wild Rivers Act 2005? e
LNo
Hf no, is all of the operational work for constructing or raising waterway barrier works - tick applicable box/es and answer (a) and/or (b} below
(i) temporary [no ClyYes |
(ii) minor Ono _ | OYes .
(iii) rebuilt on a regular basis 1No Olyes
(a) tf yes to one or more of (i) - (iil) above, does all the proposed operational work comply with any applicable Department
of Primary Industries and Fisheries (DPI&F) self-assessable code?
(71 Yes = A permit for that aspect of ihe operational work is nol required. Go to 04.13 ~ DINo- Goto (a) . we
(b) If no to all of (i) ~ (iii) or no to (a) above - (Complete Form 1, Part Os) This application requires assessment by thé Department of Primary
Industries and Fisheries (DPI&F). If DPI&F is not the Assessment Manager for the application, the agency has jurisdiction as Concurrence Agency.
C1 Yes
if yes, Is any of the proposed operational work to be carried out in a wild river high preservation area?
CJ No - Uniess the application is consistent with eny property development plan applying to the iand, the Assessment Mana! veluse to receive
it (Complete Form 1, Part O3) This application requires assessment by the Department of Primary Industries and Fisheries (DPI&F). and,
‘subject to the declaration for the relevant wild river area, assessment for the purposes of the Wild Rivers Act 2005. If DPI&F is not the
Assessment Manager for the application, the agency has jurisdiction as Concurrence Agency.
O Yes - An application for the operational work will be taken to be not properly made and the Assessment Manager must refuse to receive it
assessable codas). IP Regulation,
Page 29
INTEGRATED PLANNING ACT 1997
DECLARED FISH HABITAT AREA; WILD RIVER AREA. :
4.13
ls any of the proposed operational work to be carried out completely or partly within a declared fi sh habitat 2 area under the Fisheries
Act 1994,
LINo-Gotooss4 [1 Yes
ILyes, is the operational work reasonably necessary for: (Tick applicable box/es and answer (a) and/or (b) below)
{i) The maintenance of existing structures, including for exampie the following structures, if the structures | [_]No [1] Yes
were constructed in compliance with all the requirements, under any Act, relating to a structure of that
type -
« Boat ramps, boardwalks, drains, fences, jetties, roads, safety signs, swimming enclosures & weirs;
+ Existing powerlines or associated powerline infrastructure
(ii) Educational or research purposes relating to the fish habitat area No} C1 Yes
(iii) Monitoring the impact.of development on the declared fish habitat area Ono D1 Yes
(iv) The construction or placement of structures, Including for example, safely signs, swimming enclosures (no| [Yes
and aids to navigation, if - . . . woot
+ The impact on the area is minor; and ‘ ‘ . ‘
» The structures are constructed in compliance with all the requirements, under any Act, relating to a
structure of that type
(v) Public benefit works, including, for example, the construction of runnels for mosquito control, the (]No |] Yes
removal of Lyngbya and seed coilection for site ‘ehabilitation if the impact on the area is minor
a) If yes to one or more of (i) - (v) above, does ail the proposed operational work comply with any applicable Department of
Primary Industries and Fisheries (DPI&F) self-assessable code?’ °°
i] Yes - A permit for that aspect of the operational work is not required. Go to 04.14 . C Now Goto (by
(b) If no to alll of (i) - (v) or no to (a) above, is that proposed ‘operational. work to be carried out in in.a wild river area declared
under the Wild Rivers Act 2005?
LI No - (Complete Form 1, Part 02) This application requires assessment by the Departrient of Primary industries and Fisheries (DPI8F). If DPISF is not
g y the Assessment Manager for the application, the agei sy will have jurisdiction as Concurrence Agency.
es : ‘
_ Ifyes, is all of tie proposed operational work’for specified works under the Wild Rivers Act 2005?
Yes - Unless the appiization is consistent with any property development plan apoiying to the land, the Assessment Manager must refuse to
receive il, (Complete Form 1, Past O2) This application sequires assessment by ihe Department of Primary Industries and Fisheries
(DPI&F) and assessment for the purposes of the Wild Rivers Act 2005. if DPI&F is not the Assessment Manager for the application, the
an agency has furisciction as Concurrence Agency. .
: G No #, . .
If no, is any of the Bioposed operational work to be carried out in a awild river high preservation area?
Sw ; Mo ees
-oO No - Uniess the application i is consistent j Hi any property develbpmerit plan ‘pp¥ing fo the land. the Assessment Manager must reluse
to receive it. (Complete Form 1, Part 0.) This application requires assessment by the Department of Primary Industries and
Fisheries (DPI&F) and, subject to the deciaralion for the’relevant wild river area, assessment for the purposes of the Wild Rivers
Act 2005. if DPI&F is not ihe Assessment Manager for the application. the agency has jurisdiction as Concurrence Agency.
Oo Yes - An application for the operational work wil HI be takba to be nto propery made and the assessment manager must refuse ta
“receive it. « :
1?
Page 30
INTEGRATED PLANNING ACT 1997 IDAS Assessment Checklist, Version 22
REMOVAL, DESTRUCTION OR DAMAGE OF A MARINE PLANT; WILD RIVER AREA
414
\s any of the proposed operational work removing, destroying or damaging marine plants under the Fisheries Act 1994?
CINo-Gotoasis [Yes
If yes, is the proposed operational work reasonably necessary for: (Tick applicable box/es and answer (a) and/or (b) below)
(i) The removal, destruction or damage of dead marine wood on unallocated State tand, other than ina i[-1No '(J Yes
wild river area, for trade or commerce
(i) The maintenance of existing structures, including, for example, the following structures, if the Cno (C1Yes
structures were constructed in compliance with ali the requirements, under any Act, relating to a
structure of that type —
* boat ramps, boardwatks, drains, fences, jetties, roads, safely signs, swimming enclosures and
weirs; ,
+ — existing drainage structures;
« _ existing powerlines or associated powerline infrastructure
(iii) For educational or research purposes or for the monitoring the impact of development on marine CINo 'L] Yes
plants _.
(iv) For the construction or placement of structures, including, for example, swimming enclosures, safely No j( Yes
signs, aids to navigation, fences, pontoons, public boat ramps and pipelines, if -
+ The structures were constructed in compliance with all the requirements, under any Act, relating
to a structure of that type
(v) For the construction of runnels-for mosquito nivel removal of Lyngbya, seed collection for site LJ No |[J Yes
rehabilitation or the collection of marine plants for fishing bait, or handicraft I. ,
(a) If yes to one or more of (i) ~ (v) above, does all the proposed operational work comply with any applicable Department of
Primary Industries and Fisheries (DPI&F) self-assessable code?
G) Yes — A permif for that aspect of the operational work is nal required. Go fo Q4.15 C1 No- oto (b)
{b) If no to all of (i) - (v) or no to (a) above, is that proposed operational work to be carried out in a wild river area declared
. +. under.the Wild. Rivers. Act 2005? we ee eee :
a) No - (Complete Form 1, Part Oz) This application requires assessment by the Department of Primary Indusiries and Fisheries (DPI8F). if DPI&F is not
the Assessment Manager for the application, the agency has jurisdiction as Concurrence Agency.
oO Yes
If yes, is all of the proposed operational work for specified works under the Wild Rivers Act 2005?
Yes - Unless the application is consistent with any property development plan applying to the land, the Assessment Manager must refuse to
receive it. (Complete Form 1, Part Q2) This application requires assessment by the Department of Primary Industries and Fisheries
{DPI8F} and, subject to the declaration for the relevant wild river area, assessment for the purposes of the Wild Rivers Act 2005. If
DPI&F is not the Assessment Manager for the application, the agency. has jurisdiction as Concurrence Agency.
[I No
If no, is all of the proposed operational work necessary and unavoidable part of installing or maintaining works or e@
infrastructure required to support other development for which a development permit is not required or, if a
development permit is required, the permit is held.or has been applied for?
oO Yes — Uniess the application Is consistent with any property development plan applying to the land, the Assessment Manager must refuse to
receive it, (Complete Form 1, Part O2) This application requires assessment by the Department of Primary Industries and Fisheries
(DPIEF) and, subject fo the declaration for the relevant wild river area, assessment for the purposes of the Wild Rivers Act 2005. if
DPISF is not the Assessment Manager for the application, the agency has jurisdiction as Concurrence Agency.
oO No - An application for the operational work will be teken to be not properly made and the Assessment Manager must refuse to receive it.
Page 38
« The extent of the removal, destruction or damage is minor; and e
Page 31
“4
INTEGRATED PLANNING ACT 1997
WILD RIVER AREA ‘.:<*
4.15
| STATE-CONTROLLED ROAD: «
ls any of the operational work proposed to be carted out i in a wild river area declared under ihe Wild River Act 20057
LJNo-Gotoas16 [Yes
if yes, is the proposed operational work for the following and also declared under the wild river declaration for the areas to be
assessable?
{i) Agricultural activities as defined under the Wild Rivers Act 2005
CINo CYes
{ii} Animal husbandry activities as defined under the Wild Rivers Act 2005 LINo OYes
If yes to either (i) or {ii) above, is any part of the premises in the wild river high preservation area?
C Yes - An application for the operational work will be taken to be not properly made and the Assessment Manager must refuse to receive it
CONo
If no, is the proposed use in relation to the production of a high risk species as defined under the Wild Rivers Act 2005?
oO Yes - An application for the operational work will be taken to be not properly made and the Assessment Manager must refuse to receive it
Oo No - Unless the application is consistent with any property development plan applying to the land, the Assessment Manager must refuse to
“receive it (Compiete Form 1, Part Q if agriculture. Complete Form 1, Part R if animal husbandry) Subject to the declaration for the
relevant wild river area, this application requires assessment by the Department of Natural Resources and Water (NRW). If NRW is not
the Assessment Manager for the application, the agency has jurisdiction as Concurrence Agency.
ig 4, lem 10; iP Reg
part |,
4.16
Is any part of the premises located in part of a future State. ‘controlled foad, or within 400m ofa Stale- controled road?
EINo - Eng of section 4 0} Yes . Sy, ”
Ifyes, is the proposed operational work associated with either - 2 oO mo
A material change of use.that is assessable under the planning scheme; or
No L1Yes
Reconifiguring a lot that intréases the total number of lots, or incréases the total number of lots
abutting the State-controlled road
.
\f no, and answers to questions in this section of the checklist indicate the proposed operational work is assessable under
IPA, schedule 8 - Answer (a) - (c) below.
(a) an of the proposed operational work associated with access to a State-controlled road?
No
Yes - This application must be referred to the Department of Main Roads (DMR) as Concurrence Agency.
(b) Is any of the proposed operational work for filling or excavation? °
_ CINo CJ Yes
If yes, is the operational work proposed in a future State-controlled road not defined by route?
. C) . /
No - This application must be referred to the Department of Main Roads (ODMR) as Conéurrence Agency.
Yes --This application must be referred to the DMR as Advice Agency.
(c)
Does any of the proposed operational work involve the redirection or intensification of site stormwater from the land,
through a pipe with a cross-sectional area greater than 625m? that directs stormwater to a State-controlled road?
CINo O Yes ”
If yes, is the operational work proposed in a future State-controlled road not defined by route?
Oo
No - This application must be referred to the Department of Main Roads (DMR) as Concurrence Agency. .
| Yes - This application must be referred to the DMR as Advice Agency.
Page 39
Page 32
INTEGRATED PLANNING ACT 1997 ook NC TPO IS Ae baer ae Jt ui wa we WA? Faia: as i wee oh ” Cyl wood yt a va lial mys st me 2 Ps, aw & Noe Pot if you's ~ . orgy re i ee Page 40 ONE re, "| IDAS Assessment Checklist, Version 22 Bs) De ATS) IQED Ave be em L ER sl EL.Y 3 i “NS ann ©@ 4 f ie nfl ht . ae 1) RRS Rye we
Page 33
Vb so. ATINS =a sreozeoto = tome smavecon | ee coreep SOVUUSL FdMAO TT um | Wu L¥08.0. OOF es | We oor =: sSTeEN Mapee - oe anaes vce Poros casters esse secs rece SERIE oe 4 ' 1 : : : : : : ' a ' a i : a z woguod . i : : ‘ jst ure 77 t page t i a ar “ ' mt ere BE tee eee be + ‘ i : ‘ | ‘ORY 9706 J mm 1 ‘SOINVL BOVHOLE TOHISd ‘ GNTICRONSONN ‘ , ‘ “9 ee 2 tI | me ae Zz “meat eer ‘© on $ oO axe ' 'O ae be--- 2 PD rcswoa == * i@ af 1 < OTA U onTIATLEEE? Seet is iu) i ga ‘a 2 doHswOM ' 440 GNSS ' : : : -------------------- e--4 Bao a & g | We I 3 E
Page 34
. ms ‘ALLar Wistannos Gr bb eo. Ate ween amuveoon romania GR0d0ns wages “=e ‘BOWUNAL BIUMAO Zzz uses te vee cep ou wid ane 34H 1¥08.0, wn | me sew — ne|__ Fatrenoea aap pocccccccc cece eee eeeee ee eet pa * ' 5 , , ' ! ' i ' i ' F j eedemgena AF ' i ame » ' ” ‘ be------ wens ke ~ : : ‘9901 $708 ‘Aedes Fey , BUNWL BOvHOIS TOMIad 5 t : QNNHONSONN ff" ' i jinped 1 i ~23N eats ae? — ‘> ase ay iQ ee} ' '@ d---------- ' ’ | i) 7 nS is am i aa a 1 1 1 1 1 ------------- 522 --- ff -- 4 ‘steer vere
Page 35
INTEGRATED PLANNING ACT 1997 Part A. Version 3.1, 3 March 2008 ies Part A Common details OTE: Answer all questions unless directed to go to a part cueston. Ref Refer to the end of the form for advice on how to complete this form. ‘approval that may be issued as.a consequence sei tis copeaton Will be issued to the Applicant}. Company/organisation name (if applicable) [Noosa River Enterprises Pty Ltd Individual appticant/Contact person (if there is more than one applicant, provide advitional applicant details on an attachment to this form) Postal address [222 Gympie Tca, Noosaville QLD 4566 Contact telephone number [54497513 Mobile phone number 0418708545 Facsimile number 54740994 e-mail address [email protected] Details of the Premises (jc. the land on which the development is proposed: refer to the advice at the end of the form) ° . oot 7 1. Identify the premises by completing Table A, or Table B and/or Table C (ensure adequate information is given to identify the premises) Table A If the application is for a mobile and temporary Environmentally Relevant Activity (ERA), complete Table A only, Then go to Q2. | mae _, Name of each local govemment aréa in which the mobile and temporary ERA is proposed to operate *: = oR Table B Street address for the premises (tick applicable box/es below and insert property description in the table. Identify cach lot in a separate row.) () (CJ Street address / lot on plan for the premises (Appropriate for most applications including building apptications); OF (ii) [() Street address Aot on pian for the land adjoining or adjacent to the premises (Appropriate for development in water e.g. jety, pontoon etc} (Note: Loton pian details may be obtained from title documents, a ‘Rate’ notice, or from vena) Ae | Sieet Soaet Name and offal suburtotalty nate [1 222 | Gympie Tea, Noosavile QLD AND/OR Table C Coordinates and/or a map of the premises (Appropriate for development in remote areas, aver part of a fot, in waler (e.g. channel dredging in Moreton Bay) etc.) Coordinates aise : ninco seid © fs Nothing [Latte lies T4] CJ vcpas4 (7 weses (Other - 2. Identify if any of the following apply to the premises by completing Tables D, E, or F. (Note: in most instances, the premises will not involve any of the following characteristics, however some appfications may involve one or more of these characteristics - complete only if applicable)
Page 36
INTEGRATED PLANNING ACT 1997 Part A. Version 3.1. 3 March 2008 Table D Complete if the premises are adjacent to or associated with a water body, watercourse or aquifer (e.g. river, creek, lake, canal) Name of water body, watercourse or aquifer (if known) [1 [Noosa River Table E Complete if the premises are on Strategic Port Land under the Transport infrastructure Act 1994 Lot on pian description for strategic port land’ . . Port Authority for the tot [1 Table F Complete if the premises are in tidal water Name of local goverment for the tidal aréa (f appficabte} . Name of port authortty for the tidal area. (¥ appficabte) [1 Sunshine Coats Regional Counc 3. Indicate the total area of the premises on which the development is proposed: (Note: The total area may inchude land both above and below water) Total area of premises 1,658.00 [X)m? [_] hectares (Tick applicable unit) [Existing use of the premises ! 4. — Current use/s of the premises: (e.g. vacant land, house, townhouses, apartment building, shop, service station, school, sugar cane farming etc.) [1] Boat hire and associated serves 5. Are there any existing easements on the premises? (e.g. for vehicular access, electricity, overland flow, water etc.)? & No oO Yes - Ensure the type. location and dimensions of each easement are included in plans, submitted with the application (Proposal details | 6. Brief description of the proposal (e.g. 6 unit apartment building, 30 lot residential subdivision, a bore, aquaculture) Dredging approx. 300m2 of sand from our leased area to an approved location along the river bank. 7. Does the poposal include new buildings or operational work (including any services) on the premises? & No O Yes - Ensure the nature, location and dimensions of the proposed works are included in plans, submitted with the application [Resource entitlement (f ppicabie) - further information is provided in the advice section at the ond of the form } 8. Does the application involve taking or interfering with a State resource and therefore require a resource entitlement? (e.g. the application involves State land (leased and freehold), dectared Fish Habitat areas, taking quarry material, taking or interfering with water under the Water Act 2000, etc.) & No. - Goto a9 oO Yes - Complete Table G - provide details for each evidence required on a separate row, if applicable. Evidence of resource allocation or entitlement must be submitted with the application. You do not need to answer Q9 - go ta the next section. [Owner's consent (i applicable) _- further information ts provided in the advice section at the end of the form j 9. Complete Table H for applications involving a material change of use; reconfiguration of a lot; work on land below high-water mark and not within a canal as defined under the Coastal Protection and Management Act 1995; or work on rail corridor land defined under the Transport Infrastructure Act 1994 - provide details for each owner on a separate row, or on an attachment to this form if applicable. Premises Owner's name/s > Details of the premises owned . . Date consent: Table H ___ and postal address ~| Gare adtess or lt on plan descrpion). |... Owmers signature”, | vas obtained Noosa River Enterprises Pty 1 Ltd 222 Gympie Tce, 222 Gympie Tce Lot 151 Plan No 908649 Noosaville Q 4566 * Owner's signature cannot be provided on the form if you intend to submit the application electronically. Owner's consent must be provided to the assessment manager on an attachment contalning appropriate written documentation of the owner's consent. If the owner Is a company, $127 of the Corporations Act 2001 (Cwealth) details how a company may sign as owner, Templates for the provision of owner's consent are available on the IPA website . ‘Attachments and supporting information (Complete Table | - Use @ separate row for each type of attachment or information, including information required “under this Part) Please ensure al! documentation submitted with this form, inchuding other Parts of Form 1, or owner's consent, etc. are securely attached to this Part of the Form. Description of attachment or information: > Te wappteane) | | Method of dtvery to Table | (09 Per eobavettione pas dye pat) (69: Goneral Autor. Jones Speet Tate Repor) |. Date cs assessment manager 4 see attached e-mail
Page 37
INTEGRATED PLANNING ACT 1997 Part A. Version 3.1. 3 March 2008
Portable Long Service Leave (PLSL) levy (Applicable for certain buikting and construction work valued over $80,000 onty) mE
10. The Portable Long Service Leave Levy (PLSL) is not applicable to this application if any of the following apply: ¢ Tick box if applicable)
{[] the application seeks a preliminary approval only;
{X] the application is not for building and construction work under the Building and Construction Industry (Portable Long Service
Leave) Act 1991, section 3AA (e.g. the application is only for a change of use, or for the following types of work carried out solely for
farming purposes: land clearing, site preparation, earthworks, fences, fodder harvesting. clearing of encroaching vegetation, clearing of
regrowth, thinning vegetation or controlling weeds of pests);
{X] all costs, that relate to the work both directly and indirectly, are less than $80,000, inclusive of GST; or
(C1 the work is being carried out under an owner-builder permit issued under the Queensland Building Services Authority Act 1991 -
Complete and submit 2 Qleave Notification and Payment Form {no payment required i ownex-builder permit number stated). The receipted form inust be
Sighted by the assessment manager before a development permit can be given.
11. Is payment of a PLSL levy applicable to this application? (Refer to Q10 and the Advice below for mote information)?
BX) No - EngorPart a
Yes - Answer 012 below
OFFICE USE ONLY (For use by the Assessment Manager / Private Certifier) (Optional)
Fee @Z 374 | Caerecemed| qla\ea | name PS Lisp, | number | OT
{ NOTIFICATION OF ENGAGEMENT OF PRIVATE CERTIFIER j
To: Council. | have been engaged as the private certifier for the building work referred to in this application.
Date of 7 = . Name : oe f BSA Certification . number | te
engagement
QLEAVE NOTIFICATION AND PAYMENT (for compietion by assessment manager or private certifier if applicable)
Desctptonaf the work | Leave Project Number |Amount pai$)|: Date paid | fOr sighed by | Name of offcar who sighted he
manager :
1
Privacy Statement
The information collected on Form 1 will be used by the Department of infrastructure and Planning (DIP) in accordance with the processing and assessment of your Application.
Your personal details will not be disciosed for a purpose outside of the IDAS process, except where required by legisiation (including the Freedom of information Act 1992) or as}
required by Parliament. This information may be stored in a DIP database. The information collected will be retained as required by the Public Records Act 2002.
Advice for completing Part A
General advice
io Part A of IDAS Development Application Form 1 must be completed and accompany all development applications. The applicant is responsibte
for answering all questions fully and correctly, unless following a response there is a statement to go directly to another question, The
Assessment Manger may refuse to receive an application that is not properly made,
a The IDAS Assessment Checklist must also be completed for all development applications, other than those requiring assessment against the
Building Act 1975 only, |.e. those applications requiring the comptetion of Parts A and B only.
Applicant details
a # the applicant is a company or organisation, a contact person must be nominated. The applicant's signature is not required to be provided
under the IPA.
Page 38
oan, say
Page 39
INTEGRATED PLANNING ACT 1997 Part A, Version 3.1, 3 March 2008
Details of the premises
eo
aD
®
The tarm ‘premises’ is defined by the IPA, schedule 10 to mean a building or other structure, and land (whether or not a building or other
structure is situated on the land). The term ‘land is also defined to include the estate In, on, over or under the land.
Details of the land are not required if the application involves a mobile and temporary Environmentally Retevant Activity only. Instead complete
Table A.
The premises may be Identified in a number of ways ~
Street address and lot on plan are most common and will apply to most applications.
Gbordinates may provide the best means of accurately identifying the location of development proposed in waters, or on a relatively small
development site distant from property boundaries on a large lot. Sufficient coordinates need to be provided to identify the boundary of the
premises the subject of the application. Eastings and northings using GDA94 datum ts preferred, but longitude and latitude and other
(specified) datum such as Zone Reference or GS84 may be provided.
The definition of ‘water body’ and ‘watercourse’ can vary from Act to Act.
StrategicPortLandis within a local goverment area but a local govemment’s planning scheme does not apply onStrategicPortLand.
StrategicPortLandis declared under the Transport infrastructure Act 1994. For further information go to IDAS Guide 11 (Development on
strategic port land) and the Queensland Transport (Ports) website.
“Tidal water’ is defined in the Coastal Protection and Management Act 1995 (Schedule) and ‘tidal area’ for a local government and for strategic
port land Is defined in the IPA (schedute 10). Generally, the area below ‘high-water mark’ (defined by the Coastal Act in relation to high water
mark at spring tides) establishes the boundary of a tidal area. Land below high water mark is not within a local government's area untess
provided for under the Loca! Goverment Act 1993. Unless otherwise provided for by tegistation, a focal government has no jurisdiction betow
high water mark. A tidal area for strategic port land Is within the jurisdiction of the retevant port authority, while the Environmental Protection
Agency generally has jurisdiction for a local goverment tidal area. However, the IPA gives local governments jurisdiction for assessing and
deciding applications for prescribed tidal works within the focal goverment tidal area, and the planning scheme may be applied to that
assessment (to the extent provided for in the code for prescribed tidal work).
Resource entidement
oO
Section 3.2.1(5) of the IPA requires evidence of resource entitement be given for applications If they invotve taking or interfering with a
prescribed Stata resource. Schedute 10 of the /ntegrated Planning Regulation 1998 (IPR) prescribes the State resources, including State-
owned land, where evidence Is required to be given, and the evidence required to support the application. Link to Integrated Planning
Regulation. Section 3.2.1(10)(a)(if) states an application cannot be taken to be properly made without the required evidence.
For applications involving the taking or interfering with water under the Water Act, the development application may be made at the same
time as the request for resource entitlement, and the Department of Natural Resources and Water will accept the application as property made.
For State-controlled roads, a resource entitlement is not required for an activity that is exempt ancillary works or encroachment (identified by
gazette.notice under the Transport infrastructure Act 1994, section 50), or if the activity requires refesral to the Department of Main Roads.
Evidence may be required from more than one Department responsible for a State-owned resource, e.g. from the Environmental Protection
Agency for quarry material below high water mark, and the Department of Natural Resources and Water in relation to the State-owned land
above high water mark.
(Owner's consent
iD
e 6 8
98
Section 3.2. 1(3) of the IPA prescribes that an application must contain, or be supported by, the written consent of the land owner/s, if the
application involves: a material change of use; reconfiguration of a lot, work on land below high-water mark and not within a canal as defined
under the Coastal Protection and Management Act 1995, or work on rait corridor land defined under the Transport infrastructure Act 1994.
Evidence of this consent may need to be provided before the application will be accepted as properly made by the Assessment Manager, during
the processes of the appfication or in the event of an appeal about the outcome of the application,
“Owner for the purpose of a lodging an IDAS development application means the person at the time of lodging the application, entitled to
receive the rent for the land (or would be entitled to receive the rent for it if it were let to a tenant at a rent).
Templates are available from the {PA website for the provision of owner's consent as an attachment to this form. However other documentation
may be used for providing owner's consent provided it is clear the documentation relates to the development application for the premises,
Owner's consent, if required, must be provided even if the applicant is the owner, Owner's consent is not required for a mobile and temporary
ERA.
Portable Long Service Leave (PLSL) Levy
oO
The Building and Construction Industry Portable Long Service Leave Scheme provides long service leave entittements to workers in the building
and construction industry who would be unlikely to accrue enough service with one employer to qualify for long service leave. To fund the
scheme, a Portable Long Service Leave Levy {PLSL levy) is collected on certain building and construction work carried out inQueensland.
The PLSL levy amount and other prescribed percentages and rates for calculating the levy are stated in the Building and Construction Industry
(Portable Long Service Leave) Regulation 2002, Included in the amount collected by QLeave is the Workplace Health and Safety Fee and the
Building and Construction IndustryTrainingLevy.
The Building and Construction industry (Portable Long Service Leave) Act 1991 {PLSL Act) defines the building and construction work subject to
the PLSL levy and includes renovating, relocating, constructing, altering, demolishing, maintaining or repairing buildings, pools, roads, jettles,
pipelines, fences or earthworks, and works for subdividing, irrigating or draining land.
The PLSL levy need not be paid when the application Is made, but the PLSL Act requires the fevy to be paid before a development permit may
be issued.
The Assessment Manager must sight an approved form issued by QLeave advising of the status of the payment of the PLSL levy. Building and
Construction industry Notification and Payment Forms are available from anyQueensiandpost office or agency, on request from QLeave, or can
be completed on the QLeave website at www.aleave,qld.gov.au. For further information contact QLeave (Tel: 1800 803 481 Web:
www.gleave.qid.gov.au )
Page 40
INTEGRATED PLANNING ACT 1997 Part P. Version 2.1. 3 March 2008
idas)
Nature of the prescribed tidal works... he es aR
1. Whatis the nature of the proposed prescribed tidal work and the type of approval sought? (Tick applicable box/es)
st Nature of use” *]# Estimated value of. 7"
: (Tick applicable box)-|:;, completed works ($)-#.|.. 2
: . (Private use
Jetty, pier or wharf .
0 ety P 3 (Non-private use
7 . (7 Private use
ihwe
OO (i Boat ramp or spillway (7 Non-prvate use
sa (J Private use
M is Develo; Permi
om cong (JNon-private use O pment Perit
Private use i
oO ww Deck or boardwalk 5 Non pate se (1 Pretiminary approval
ui
(Private use
P
OM ontoon (J Non-private use
C Private use
: f .
Oo wi Revetment, sea wall or retaining wall CI Non-private use
oO (vii) Other (e.g. abutment, basin, bridge, breakwater, dam,
dock, dockyard, embankment, groyne, pipeline or other |[_] Private use
underground service etc.) - Provide delails below
Dredging approx. 300m2 of sand Bq) Non-private use
2. s the application within a cul-de-sac, a bend in a waterway or other location where the side-boundaries of the lot connected to the
work and neighbouring lots are not at right angles to the waterway?
a)
oO Yes - Submit, with the application, photos of any constructed neighbouring structures, or information about approved but unconstructed
neighbouring structures.
s : BE ky
3. __ Is the application supported by evidence that the proposed work will not prejudice the access rights of adjoining property owners?
LJ No = &X Yes - Complete 03/a)
[Adjoining property access. and evidence of SUPPOIT. . 4.2 > w+
3{a) What is the nature of the evidence?
(C1 Letters of support from adjoining property owner - Submit, witl the application, the letters of support.
Plans illustrating a water allocation area - Submit, with the application, the plans illustrating the water allocation area.
Page 41
INTEGRATED PLANNING ACT 1997 Part P. Version 2.1, 3 March 2008 Certification 3 4. Has a Registered Professional Engineer of Queensland (RPEQ) or interstate equivalent certified that the works comply with the design and safety provisions of the State IDAS code for Prescribed Tidal Works contained in the Coastal Protection and Management Regulation 20037 & No (1 Yes - Provide details below ‘Mandatory information 5 . J i 5. Confirm the following mandatory information accompanies this application. Confirmation of lodgemeitt< Method of odgement Plans and written documentation. (i) TT locaton and dimensions of the proposed Wal workin reaton wo The os abng Te proposed | work and the tidal land on which the work is proposed to be located S<] Confirmed | over the counter (ji) Allother structures on the waterfront and within 20 metres of the proposed works [X] Confirmed over the counter (iii) The current location of Lowest Astronomical Tide (LAT), Highest Astronomical Tide (HAT) and Oo Confirmed Mean High Water Springs (MHWS) (iv) The slope angles of the beds and banks of the tidal area [X] Confirmed over the counter (v) Details of the proposed work in accordance with the IDAS code for prescribed tidal work in the Coastal Protection and Management Regulation 2003, schedule 4A (e.g. physical appearance, lighting, |X] Confirmed —_| over the counter signage. earthworks, public access, infrastructure, structural components, engineering design standards) (vi) The finished levels of the proposed works [] Confirmed —_| over the counter (1 Confirmed (vii) Details of the largest vessel, if any, to be moored at the structure EX] Not applicable (vi) Evidence that the proposed work will nt prejudice the access rights of adjoining property [7] Confirmed owners (XJ Not applicable OFFICE USE ONLY Date Received Reference Numbers [sid EPA cost code | 433061 Advice for completing Part P General advice le — Part A must also be completed for all IDAS development applications. l» — The applicant is responsible for answering all questions fully and correctly, unless following a response there is a statement to go directly to another question. >» When paying fees to the Environmental Protection Agency by electronic funds transfer (EFT) use the process from the information sheet Electronically paying fees to the Environmental Protection Agency (EPA) and attach the form Electronic Funds Transfer (EFT) payment notification to the application, e For further Information about completing this form go to: . IDAS Guide 24 (Prescribed tidal work) ° Eooaccess website . EPA Guidelines and procedural quides 01 A development permit authorises development to occur, while a preliminary approval is a step in the approval process and does not authorise development to occur. a4 A Registered Professiona! Engineer of Queensland (RPEQ), or the interstate equivatent, may certify that the proposed work complies with the design and safety provisions of the IDAS code for prescribed tidal work in the Coastal Protection and Management Regulation 2003, schedule 4A. The provision of the certification may reduce the applicable fee for assessment of the work by the local goverment.
Page 42
INTEGRATED PLANNING ACT 1997 IDAS Assessment Checklist. Version 22 tas IDAS Assessment Checklist IDAS S Dele Aiesion Form Vi is.the afraid form, for all development applications’ under the: Inearated lamin A Act.* ° . 1997 Al. Form: 4 is fate tid of various Parts. . the nature of the application. ' ae Font also inchudes: this DAS Assessment ChecMlist, which Is used to'assist ii determining State sssessmentand teferral requirements, and the Parts 0 Fe 1 relevant to the application. . "Section 4 and all other relevant Sections of the IDAS Assessment Checktist, as identified in ihe ‘able below, must ; completed for att I development applications except-those proposed-on land in'an‘urban development, arda, or for building work "Ee . requiring assessment against the 1e Building Ac Act 1975 only. ._ xuim ar “Far more information =a davclopment applications on land in an urban development area, refer to www, vida, aid gov. au. » ”” Formore advice about building applications ret refer to Patt| B of the IDAS Application Form. « , “See, Answerng the following questions wil assist you in dolominng which Sections sof the Checklist must be ssmpleied for your Spnlicaton if unsure, phone or visit your local government or log onto the DIP website www.dip.gid.gov.au for help For atl IDAS development applications (except those for building work requiring assessment against the Building Act 1975 only) - complete Section 1 of this checklist Does the application seek approval to make a material change of use of the premises? i yes - complete Section 2 of this checklist Does the application seek approval to reconfigure a lot? if yes - complete Section 3 of this checklist and Part F of IDAS Application Form 1. if the premises are completely within a single C1Yes |—XJNo focal government area assessment is by the local government. Does the application seek approval to carry out operational work? DYes |KINo if yes - complete Section 4 of this checklist fdves jCINo Does the application seek approval to carry out building work requiring assessment against the Fisheries Act 1994? Ces |5qNo if yes - complete Section 5 of this checklist Have you received a referral agency response under section 3.3.2.of the IPA, in relation to this development application? if yes - complete Section 6 af this checklist DYes |INo [Does the application seek approval to carry out building work requiring assessment against a local government planning scheme? DYes |KJNo if yes - complete Form 1 Part E of IDAS Application Form 1. Assessment is by the local government. Does the application seek approval to carry out building work requiring assessment against the Building Act 1975? if yes - go to Appendix 1 of this checklist for advice on building referrals. Complete Part B of DAS Application Form 1. OYes |[XJNo Assessment is by a building certifier Do you wish the application to be assessed against a superseded planning scheme? Jf yes - complete Form 7 Attachment 1 (Yes |5No \s the application for development completely or partly on Caims and Mackay airport land under the Airport Assets (Restructuring and Disposal) Act 20087 if yes - Assessment is by the Department of infrastructure and Planning. Complete Form 1 Part D of DAS Application Form 1 if the OYes |XINo application is for a material change of use, and Part E if for building or operational work. Also, the application must be referred ta the focal government as Advice Agency.
Page 43
INTEGRATED PLANNING ACT 1997 (DAS Assessment Checklist. Version 22 SECTION 1 Section 1 must be completed for all applications that require completion af the IDAS Assessment Checkiist. HERITAGE 1 411A !s any part of the proposal intended to be carried out on a Queensland heritage place under the Queensiand Hentage Act 1992? RINo-cowr18 [J Yes be Meat pe hea tn SNe ee 11B Does the proposal involve development intended to be carried out on a place entered in a local heritage register under part 11 of the Queensland Heritage Act 1992, other than if the place is on Caims or Mackay airport land? [IX] No-cowan2 [] Yes A Mey abt ites hk ew (REMOVING QUARRY MATERIAL; WILD RIVER AREA | 1.2 Does the proposal involve removing quarry material from a watercourse or lake as defined under the Water Act 2000? No-Gowar3 (] Yes IPA, schedule 8, part 1, table 5, item 1, IP Regulation, schedule 2, table 7, item 11; IP Regulation, schedule 1, table 5, nem 2 (wild river area), Water Act 2000 section 966C; Wild Rivers Act 2005 section 434 ‘ENVIRONMENTALLY RELEVANT ACTIVITY; WILD RIVER AREA ? 1.3 Does the proposal involve an environmentally relevant activity (ERA), other than a mining activity or a petroleum activity? [XI No-Gowors [[] Yes IPA, schedule 8 part 1, table 2, tem 1; IPA, schedule 8, part 1, table 5, items 3 and 4, IP Regulation. schedule 2, table 2, items 7 and 23, Ervronmental Protection Act 1994 section 73AA twald iver arca), Wild Rivers Act 2005, section 43A, refevant wilt iver declaration; Wild Rivers Code WITHIN THE LIMITS OF A PORT | 14 is any part of the premises within the limits of a port under the Transport Infrastructure Act 1994? DX] No -Gotoars (1 Yes IP Regulation, schedule 2, table 2, tems 15 and 16 iDECLARED FISH HABITAT AREA H 15 Does any part of the premises adjoin a declared fish habitat area under the Fisheries Act 1994? [IX] No - Goto 01.6 oO Yes - if answers to questions in other sections of this checklist indicate that the proposed development is assessable under IPA, schedule 8, this application requires assessment by the Department of Primary industries and Fisheries (DPI&F). if DPI&F is not the Assessment Manager for the application, the agency has jurisdiction as Advice Agency. IP Regulation. schedule 2. table 2, dem 26 ‘COMMUNITY INFRASTRUCTURE ] 16 |s any part of the premises designated for community infrastructure? il No - Goto Q1.7 (Yes IP Regulation schedule 2 lable 3 den * WASTE WATER MANAGEMENT ~ ee J 17 Does the proposal involve the establishment or expansion of a waste water disposal system? DX] No - End or Section [_] Yes IP Requiaton, schedule 2. tabu 3 tom 5
Page 44
INTEGRATED PLANNING ACT 1997 IDAS Assessment Checkfist. Version 22
SECTION 4 . section 4 must be completed when the application seeks approval to cary out operational work,
(PLANNING SCHEME - ‘ _ |
44 Is the proposed operational work assessable under any State planning regulatory provisions?
(No (J Yes
If no, is the proposed operational work assessable under the planning scheme?
(No - Goto 042 (7) Yes - complete Form 1, Part E and answer Q4.1.1 - 4.1.7 below
ASSOCIATED WITH RECONFIGURING A LOT; RESIDENTIAL, COMMERCIAL OR INDUSTRIAL DEVELOPMENT IN A WILD raver)
‘AREA . .
42 Is any of the proposed operational work associated with reconfiguring a fot and the reconfiguration is also assessable?
[KX] No -Gotwoas3 {_] Yes
IPA schedule 8, part t (ab'e 4, tem 2 IP Reguiation, schedule 1, part 2, table 5 tens hie)
Wild Rivers code (Note: the core does not curently contam applicable provisions for residential industrial or commercial development inside a designatcd urban
area}
[KOALA CONSERVATION (taside SEQ urban footprint) |
43A Is any part of the premises in an interim koala habitat protection area?
[KI No -Gotoas3e (] Yes
IP Regulation, schedule ¢ title 2, ten 34A
VEGEFATION CLEARING; KOALA CONSERVATION: WILD RIVER AREA ~ ° |
4.38 Is any of the proposed operational work for the clearing of native vegetation to which the Vegetation Management Act 1999
applies?
[BX No -Gotoass ([] Yes
IPA, schedule 8 part 1, table 4, lems 1A-1G; IP Regulation, schedule 2 table 7, tem $ (vegetation clearing); 1P Regulation, schodule 2 table 2, dem 34 (koala
conservation), IP Requiation, schedule 1. part 3, table 4. item (vegetation clearing/wald aver area): Vegetation Management Act 1999, section 22A (vegetation
clearingiwild river area); Wid Rivers Act 2005. sections JF and 43A
‘TAKING OR INTERFERING WITH WATER; WILD RIVER AREA |
. a
44 Is any of the proposed operational work for any thing constructed or installed that allows, under the Water Act 2000, for taking or
interfering with water from a watercourse, lake or spring (other than using a water truck to pump water; and other than under
the Water Act 2000, section 20(2), (3) or (5), or from a dam constructed on a watercourse or lake?
DR] No -Go1oass {T] Yes - Answer (a) and (0) below
IPA, schedule 8, part 1. table 4, dems 3(a): IP Regulation, schedule 2, (able 2, item 8:1P Regui:tion schedule t, patt 3. table 4, doms 3 and 3A, Water Act 2000, section 968A (wiki river
area): Wild Rivers Act 2005, section 434; relovant wiki aver declaration; ‘Wild Rivers Code
45 Is any of the proposed operational work for any thing constructed or installed that allows, under the Water Act 2000, for taking or
interfering with artesian water {other than using a walter truck to pump water)?
ER No Gotoas6 [] Yes - (Complete Form 1, Part K,) This application requires assessment by the Department of Natural Resources and Water
(NRW). ff NRW is not the Assessment Manager for the application, the agency has jurisdiction as Concurrence Agency.
IPA schedule & part 1, table 4, tern 3(b), IP Regulation, schedule 2, fable 2 item 8, 1 Requlation, schedule 7, part 3, table 4, tem 3
Wild Rivers code {Nole: the code does not currently contain applicable provisions for taking of mlesfecng with aitesian water)
46 \s any of the proposed operational work for any thing constructed or installed that allows, under the Water Act 2000, for taking
overland flow water (other than using a water truck to pump water)?
(No -Gotoaa7 ([] Yes - Answer (a) and (b) below
IPA scnodiie 8 pat) fable 4 om Stchid WP Regulanion schcdule 2 able 7 stom § oP Reguiaion schedule | part 3 lanle 4 dom 3 Vater Act 2000, section 966A fuald aver ae),
Wild Rivers Act 2005. sevnon 434 relevant wid fiver declaration vatd Rivers Code
47 ls any of the proposed operational work for any thing constructed or installed that allows, under the Water Act 2000, for taking or
interfering with subartesian water (other than using a water truck to pump water}?
[XJ No -Gotoare [_] Yes
IPA, schedite 8 part} table 4 item 3ferfi IP Requtation, scnedute 2 table 7 tem & IP Regulauon, scheduie 1 part 3 taille 4. kent 3
Water Act 2000. sechon S864 fwild nver arca¥Note no current Wild Rever declaranon identifies takiin or interfonna sith subartesian water as assessable’
Wict River cove (Note the come aos vot cunenty conan applicable prowsions for sub artesian water
48 Does any of the proposed operational work for any thing constructed or installed that allows, under the Water Act 2000, for
interfering with overland flow water (other than using a water truck to pump water}?
6] No -Gotoaa9 [[] Yes - Answer bath (a) and (b) below
Page 45
INTEGRATED PLANNING ACT 1997 IDAS Assessment Checklist. Version 22
FA sehouudee part? tate 4 teas Toru ond dy IP Requiten » imdu’s 2 tabh 2 den 9 IP Regutahon scretee * part 3 lake + tem 3A déater Act 2000 secnon 9658 veo
saen fe ree Hop Goyer. ot
49 Is the proposed operational work for the following?
(i) For the construction of a referable dam as defined under the Water Supply (Safety and Reliability)
Act 2008
(i) To increase the storage capacity of a referable dam by more than 10% RI No CO Yes
If yes to either or both (i) or (ii) above - (Complete Form 1, Part Kg) This application requires assessment by the Department of Natural Resources and
Water (NRW). If NRW is not the Assessment Manager for the application. he agency has jurisdiction as
& No ( Yes
Concurrence Agency.
PA shed Sy Be cesta PF Roguuhod seme ks. taba A cece
MDAC WORK; WILD RIVER AREA J ; . 7
4.10 ls any of the proposed operational work tidal work, other than excluded work defined under the |PA?
(CI No -Gotoas.11 §X] Yes - Answer (a} and (b) below
{a) |s any of the proposed tidal work prescribed tidal work?
Yes [7] No
If yes, is any of the proposed prescribed tidal work to be carried out in a wild river area declared under the Wild
Rivers Act 2005?
(No [(] Yes
(b) Is any of the proposed tidal work to be carried out in one or more of the following tidal areas?
{i) One only local government tidal area [No Yes
(ii) Starting in one focal government tidal area and extending into another local BZ) No CO Ye
goverment tidal area (but in no strategic port tidal area) o s
(iti) In two or more local government tidal areas but not starting in either local
govemment tidal area IX] No C) Yes
(iv) One only strategic port tidal area &] No 0 Yes
{v) ‘ ical area that is not a strategic port tidal area or a local government tidal Bd No Cl Yes
Note: The answers you provide in (I) - (v) above may affect who the Assessment Manager is for the application.
IPA, schedule 8. part 1, table 4, item 5: IP Regulation, schedule 2. table 2 items 12, 14 and 17, IP Regulation schedule 1. pant 3, table 4, stems 4A and b
Coastat Protection and Management Act 1995, section 104A {wild river area)
|\COASTAL MANAGEMENT DISTRICT; WILD RIVER AREA i}
4.11 Is any of the operational work proposed to be carried out within a coastal management district?
IK} No -Gotoaaiz [_] Yes
IPA, schedule 8, part 1. table 4, item 5; IP Reguiavon, schedule 2, table 2. kems 12 and 14; IP Regulation. schedule 1. pant 3, table 4, items 4A and 5
Coastal Protection and Management Act 1995 Act 1995, section 104A (wild aver area). Wild Rivers Act 2005, section 43A
WATERWAY BARRIER WORKS; WILD RIVER AREA J
4.12 Is any of the proposed operational work for constructing or raising waterway barrier works under the Fisheries Act 1994?
EK] No -Gowas13 [J Yes
IPA schedule 8 part tablet stem 6 IPA schodule & part 2, tablet wer 2 Festi
Requiatian schetiae 1 pad 3 tube 4 Cem 6 bushes Art T9GS 51 WON 6D) jars
us Regulation’ 1995 31134 foel-assessabh: codes! #P Reaulavon, schedule 2 fable & ene do ie
Pe anat Aut Rivers Act 200% sectuin 138
[DECLARED FISH HABITAT AREA; WILD RIVER AREA |
4.13 ts any of the operational work proposed to be carried out completely or partly within a declared fish habitat area under the
Fisheries Act 19947
BX] No - Goto 04.14
1 Yes
IPA, scheduby 8 part 1 table fem» IPA schedule & part 2, table totem 3 Fisheries Rexpdainn 1965 4113 (seit assessaties vades) IP Regain, schodiur 2 ible 2 tem 9 18
Regtltiait soediie F pratt idk been 7 AWE Ree Act Os + puts IBA Fite Act sitar Ze0C ieee et te te
REMOVAL, DESTRUCTION OR DAMAGE OF A MARINE PLANT; WILD RIVER AREA ~ 1
414 {s any of the proposed operational work removing, destroying or damaging marine plants under the Fisheries Act 1994?
f] No -Gotoas15 {) Yes
Page 46
INTEGRATED PLANNING ACT 1997 IDAS Assessment Checklist. Versi
1A sehettaks @ por) feb S28 ThA ~hedule & pat hic 3 dem tt siete s Regulation 19S> oF 1JA (sev asst sable Cudess I Regulahuit 9071
Rexadaian sehoaeie 2 part 3 iabie Litem 8 Fisheries Act sognp TADB ald iver ste7!, Wild Rivers Aat 200% so 70n GQA fale ant eal ee Gor
WILD RIVER AREA . }
4.45 1g any of the operational work proposed to be carried out in a wild river area declared under the Wild River Act 2005?
BK No -Gowoas7s ([] Yes
IPA schedule 8 pat? iavte 4 dem 10 1P Requlanon schedule 2 (bic 2 dem 37 Wild Rivers Aci N09, seciions Ad 43a
|STATE-CONTROLLED ROAD "J
4.16 Is any part of the premises located in part of a future State-controlled road, or within 100m of a State-controlled road?
BX] No -Endofsection4 {_] Yes
IP Regulatiun, schedule 2 table 2 ten: 3
Disclaimer:
While the Department of Infrastructure and Planning (DIP) believes that this information contained on this form and provided as part of
this process will be of assistance to you, itis provided on the basis that you will not rely on the information without first making your own
enquiries regarding the interpretation and application of the applicable legislation to your circumstances.
To the full extent permitted by law DIP expressly disclaims all liability (including but not limited to liability for negligence) for errors or
omissions of any kind or for any loss {including direct and indirect losses), damage or other consequence which may arise from your
feliance on this process and the information contained on this form.
Page 47
se Sunshine Coast LAND USE SECTION FEES Regional Council . : RECEIPT TYPE SALE OF DOCUMENTS Superseded Planning Scheme Documentation - 520 Copy of Permit/Approval Letter 110 The Noosa Plan Documentation = 111 APPLICATION FEES ‘ Material Change of Use - Code/Impact ; . . Consistent > ~ SO _ . 524 inconsistent . , . : 521 Assessment under Superseded Planning Scheme oo . 521 Modification to a Development Permit . "521 . Extension of a Currency Period . : 1. 521 * . Operational ‘Works - Landscaping . 521 : @ Bldg Work assessable against the Planning Scheme. ge ee 21> : =e PRE LODGEMENT REVIEW , : . ‘ on Half Hour ° , , / : . 522 « One Hour , , . oo : - . 522° ADVERTISING . m, / . Purchase Advertised Applications | ; a - 523 JETTIES . . / . . Jetty Application Fee -. — . HS 1b 524. Jetty Bond “0 . “Soo . 5t . . Lo . o . (Category 4) - BONDS . _ — te Performance Bond. : oo a) . St + : : : _ (Category 9} SIGNS, . : / .. Registration Fee : ot - . 222 s@cu FEE: . | — Search of Land Use Section: file. , 112 Liquor Licensing Request mo oO : 113 TOTAL $. 2P%TLo NAME: Noor Sea bxoer Gatien S40 ADDRESS: . 222.) Gprgs Tee , OWS BOsfA SE us be FILE NO: =] QR2. = DATE: ~— St os RECEIPT NO: _ Is Ae U 2S Signature of TP Officer: es Sua - AUTHORITY NO: " << 4/200 [aeefi
Page 48
CALCULATION OF FEES APPLICATION FEE TOTAL FEES MCU - CODE ASSESSMENT Details of Development Consistent 1.0 Inconsistent 3.0 FEE CALCULATION MCU - IMPACT ASSESSMENT Details of Development Consistent 1.0 Inconsistent 3.0 FEE CALCULATION ~ JOPERATIONAL WORKS Details of Development FEE CALCULATION _ TOTAL FEES
Used in these records
09/0982 - Op Works - Prescribed Tidal Works - Extensions to Jetty [As Published]Related documentApplication case desk ↗
About this file
- File size
- 2.6 MB (large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take up to a minute.