Original source · versioned page text
Form 61 Non-Compliance Final
4. Non-compliance Indicate the stage/s that do not comply
Either a competent person or a certifier Final Stage
can give a non-compliance notice
The following stages do not comply with the
building development approval.
The builder must perform the work required to
ensure the stage, the subject of the notice
complies with the building development
approval. A subsequent notice for inspection
for a stage of building work must be given to State reasons for non-compliance
the building certifier. 1/ Provide Surveyor Setout Certificate from Licensed Surveyor
A competent person must be assessed as 2/ Provide Council Relaxation for Mean Height to exceed 3.5
competent before carrying out the inspection.
A competent person is assessed by the
building certifier for the work as competent to
practice in an aspect of the building and
specification design, because of the individual’s
skill, experience and qualifications. The
competent person must be registered or
licensed under a law applying in the State to
practice the aspect. Signature (If being completed by a competent person a copy must be sent to the private certifier)
If no relevant law requires the individual to be
licensed or registered, the certifier must assess
the individual as having appropriate
experience, qualifications or skills to be able to
give the help.
If the chief executive issues any guidelines for
assessing a competent person, the building
certifier must use the guidelines when Date
assessing the person.
26/06/2020
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalSearchable page text hides email addresses. Original files are unchanged and may show email addresses.