Delegated Report - Code - Planning OPW21 0216

of 1

Page text shows just the words. Original shows the document exactly as it was published.

Author	Coordinator Engineering, Mark Lewis
Development Assessment

APPLICATION DETAILS
Application No.	OPW21/0216
Applicant	Terry Allan Johnson
Proposal	Operational Works - Earthworks
Properly Made Date	27 July 2021
Information Request Date	Not Applicable
Information Response Date	Not Applicable
Decision Due Date	29 September 2021
Report Completed Date	27 August 2021
Report Reviewed By	Laurie Schreck

PROPERTY DETAILS
Property Address	32 Campbells Rd Cootharaba Qld 4565
RP Description	Lot 6 RP 810777
Land Area	20000.000 m²
Existing Use of Land	Rural

STATUTORY DETAILS
SEQRP Designation	Regional Landscape and Rural Production
Zone	Rural
Precinct	Not Applicable
Local Plan Area	Not Applicable
Overlays	Acid Sulfate Soils, Biodiversity, Bushfire
Assessment Type	Code
PROPOSAL
The application seeks approval for Operational Works - Earthworks.
The locality and proposal plan are included below.

Figure 1 – Locality

Figure 2 – Site Plan
site details
Background
The subject application was submitted in response to an advisory letter from Council. The letter was issued as works (earthworks for dam construction and use of spoil for bunds) had been undertaken without approval. The subject application seeks approval for these works.
Site Description
The site is a vegetated rural property.
assessment
The works
The works consist of the construction of the dam and the use of the spoil to construct a bund adjacent to the rear property boundary.
The dam has been constructed between 10m and 15m from the side boundary with the spillway approximately 12m from the boundary. It is considered that given the natural slopes of the land that 12m is sufficient for the overflows from the spillway to return to natural surface runoff patterns before crossing the boundary.
The toe of the bund is setback approximately 5m from the rear boundary, approximately 9m from the side boundary (south-eastern corner of the property) and extends approximately 60m across the site. It is considered that the bund location will not significantly change the surface drainage patterns in the area and will not result in a worsening or erosion for the adjoining property.
Relevant conditions have been in the recommendation.
Instruments for Statutory Assessment
Under the Planning Act 2016 the application must be assessed against each of the following statutory planning instruments to the extent they are relevant to the development:
State Planning Policy;
South East Queensland Regional Plan;
Planning Regulation 2017; and
Noosa Plan 2020.
Noosa Plan 2020
The following codes from the Noosa Plan 2020 are applicable to this development:
Earthworks Code;
Water Quality and Drainage Code
The application has been found to generally comply with all applicable statutory instruments.
cONSULTATION
Referral Agencies
Not Applicable
Internal Council Referrals
Not applicable
conclusion & reasons for decision
The proposed development generally complies with the requirements of the planning scheme and does not raise any significant issues that cannot be addressed by reasonable and relevant conditions. The application is therefore recommended for approval.
The report is provided in accordance with Section 63(5) of the Planning Act 2016.
RECOMMENDATION
With regard to Application No OPW21/0216 for Operational Works - Earthworks situated at 32 Campbells Rd Cootharaba Qld 4565 and described as Lot 6 RP 810777, it is recommended the application be approved in accordance with the following details for the Decision Notice:
application details
Application No:	OPW21/0216
Street address:	32 Campbells Rd Cootharaba Qld 4565
Real property description:	Lot 6 RP 810777
Planning Scheme:	Noosa Plan 2020 (25 September 2020)
Decision details
Council decided to issue the following type of approval:
Development Permit for Operational Works - Earthworks
CURRENCY PERIOD of approval
The currency period for this development approval is stated in the conditions below.
assessment manager conditions
APPROVED PLANS
Development undertaken in accordance with this approval must generally comply with the approved plans of development. The approved plans are listed in the following table unless otherwise amended by these conditions.
Plan No.	Rev.	Plan/Document Name	Date
21513-C000	A	Locality Plan, Drawing Index & General Notes prepared by TOD Engineers and Project Managers	27 July 2021
21513-C001	A	General Arrangement, Sections & Details prepared by TOD Engineers and Project Managers	27 July 2021
CURRENCY PERIOD
The Currency Period for this development approval lapses if the development has not substantially started by 27 August 2023, unless an application to extend the currency period is approved by Council.
SITE SPECIFIC CONDITIONS
Stormwater runoff from the development works must be controlled on-site and discharged without causing scour or damage to the subject site or any adjoining property.
All vegetation on the site must be retained and suitably protected during the construction of the works.
No vegetation removal is permitted without obtaining prior written approval from Council.
PRIOR TO COMMENCEMENT OF WORKS
Engineering
Any changes to the details associated with the supervising RPEQ or Principal Contractor during construction, must be notified to council in writing within five business days of the change occurring.
Any conflict between the development and an existing or proposed service must be referred to the relevant service authority for determination prior to commencement of works.
DURING CONSTRUCTION
Engineering
All works must be supervised by a Registered Professional Engineer of Queensland (RPEQ) who is independent of the Developer and Principal Contractor, and they must certify that all works conform to the Operational Works permit. Where municipal works are involved, such confirmation must be submitted for the respective hold points prior to any site inspection by Council Officers.
All works must be constructed and work procedure undertaken in accordance with:
The approved plans/documents and conditions detailed in this Decision Notice
All relevant Noosa Council Planning Scheme Policies, standard drawings, standard specifications and guidelines
The latest version of the Healthy Waterways document “Water Sensitive Urban Design Technical Design Guidelines for South East Queensland” for all water quality devices to be constructed on site
Earthworks
All earthworks shall be undertaken in accordance with the provisions of AS 3798 Guidelines on Earthworks for Commercial and Residential Development
Stormwater Drainage
Appropriate scour protection must be provided at the outlet of all stormwater systems including temporary outlets.
Works associated with this permit must not adversely impact on the existing drainage conditions on other properties (eg by blocking or interfering with natural overland flows).
Erosion and Sediment Control
Prescribed Water Contaminants (as defined in Schedule 10 of Environmental Protection Regulation 2019) must not be released from the site or to waters within the site, or be likely to be released should rainfall occur, unless all reasonable and practicable measures are taken to prevent or minimise the release and concentration of contamination.
Sediment and erosion control measures must be in place prior to works commencing and be maintained until the disturbed areas have achieved the required stabilisation. If such measures are not in place or are not satisfactory, “on the spot” fines may be issued. Such fines can be issued if sediments from the site are found to enter or have the potential to enter Council’s stormwater system, natural waterways, any downstream stormwater filtration system or adversely impacting on other properties.
The developer must ensure non-essential exposure of soil is prevented by restricting the extent of disturbance and minimising the duration of soil exposure to adverse weather conditions and effectively turf, cover or stabilise any disturbed area without delay and prior to rainfall occurring.
The developer must ensure sediment does not leave the site or enter onto adjoining properties or Council’s drainage system due to surface runoff or on tyres of vehicles and/or machinery. It is essential to implement appropriate approved erosion and sediment control measures throughout the site during all phases of construction including vehicle shakedown pad/grid (or similar) at the access to the construction site. Where sediments or other contaminants are deposited on a road, they must be removed so as not to enter Council’s drainage system or waterways.
Prior to the completion of the development, all site surfaces must be effectively stabilised using methods which have achieved effective short-term stabilisation and which will continue to achieve effective stabilisation in the medium to long-term. For the purpose of this condition, an effectively stabilised surface is defined as one that does not, or is not likely to result in visible evidence of soil loss caused by sheet, rill or gully erosion or lead to sedimentation, or lead to water contamination.
Damage to Services and Assets
Any damage caused to existing services and assets as a result of the development works must be repaired at no cost to the asset owner at the following times:
where the damage would cause a hazard to pedestrian or vehicle safety, immediately; or
where otherwise, upon completion of the works associated with the development.
Any repair work which proposes to alter the alignment or level of existing services and assets must first be referred to the relevant service authority for approval.
FOLLOWING CONSTRUCTION
Certification
Upon completion of the work a certificate must be issued by an RPEQ certifying that the works have been constructed in accordance with the Operational Works permit.
referral agencies
Not applicable.
Advisory notes
The following notes are included for guidance and information purposes only and do not form part of the assessment manager conditions:
Aboriginal Cultural Heritage Act 2003
There may be a requirement to establish a Cultural Heritage Management Plan and/or obtain approvals pursuant to the Aboriginal Cultural Heritage Act 2003 (ACH Act).
The ACH Act establishes a cultural heritage duty of care which provides that: “A person who carries out an activity must take all reasonable and practicable measures to ensure the activity does not harm Aboriginal cultural heritage”. It is an offence to fail to comply with the duty of care. Substantial monetary penalties may apply to individuals or corporations breaching this duty of care. Injunctions may also be issued by the Land and Resources Tribunal, and the Minister administering the ACH Act can also issue stop orders for an activity that is harming or is likely to harm Aboriginal cultural heritage or the cultural heritage value of Aboriginal cultural heritage.
You should contact the Cultural Heritage Unit to discuss any obligations under the ACH Act.
Council has undertaken an audit check of the Operational Works drawings in relations to the proposed works.  A detailed check of the calculations and drawings has not been undertaken, as they have been certified by a RPEQ. The RPEQ bears full responsibility for all aspects of the engineering design.  Council reserves the right to require further amendments and/or additions at a later date should design errors become apparent.
Council reserves the right to call up any performance bond held or levy charges against the property, should emergency works be required to be undertaken by Council to make the site safe due to inactivity on the development site for extended periods of time.
Should any changes or modifications to the approved plans be required as a result of construction constraints, a “Request to change an existing approval” under the Planning Act 2016 must be made. Amended plans clearly indicating the changes must be lodged with this application along with the appropriate fees.
Environmental Advisory Notes
The Environmental Protection Act 1994 states that a person must not carry out any activity that causes, or is likely to cause, environmental harm unless the person takes all reasonable and practicable measures to prevent or minimise the harm. Environmental harm includes environmental nuisance. In this regard persons and entities, involved in the civil, earthworks, construction and landscaping phases of this development are to adhere to their ‘general environmental duty’ to minimise the risk of causing environmental harm.
Erosion and Sediment Control
Accepted best practice standards include International Erosion Control Association Australasia Best Practice Erosion and Sediment Control
Qualified Person, for the purpose of erosion and sediment control is a Certified Professional in Erosion and Sediment Control (CPESC) or suitably experienced Registered Professional Engineer of Queensland (RPEQ).
As a general rule, a site is determined to have achieved effective short-term stabilisation if at the time of the final inspection:
Methods of stabilisation are:
appropriate for slopes and slope lengths; and
are consistent with best practice environmental management practices such as in the Manual for Erosion and Sediment Control or the IECA Manual; and
Stormwater runoff from the site is not currently, and is not likely to result in visible evidence of sedimentation or erosion, or lead to water contamination.
property notes
Not applicable.
VARIATION approval details
Not applicable.
further development permits required
Not applicable.
submissions
Not applicable.
RIGHTS OF APPEAL
You are entitled to appeal against this decision. A copy of the relevant appeal provisions from the Planning Act 2016 is attached.
During the appeal period, you as the applicant may suspend your appeal period and make written representations to Council about the conditions contained within the development approval. If Council agrees or agrees in part with the representations, a negotiated decision notice will be issued. Only one negotiated decision notice may be given.
OTHER DETAILS
If you wish to obtain more information about the decision, electronic copies are available on line at www.noosa.qld.gov.au or at Council Offices.

[word/footer1.xml]
Page 7 of 8

[word/header1.xml]
3

[word/header2.xml]
DEVELOPMENT ASSESSMENT DELEGATED REPORT

[Attachment: image2.jpeg (image text)]
(
\
\
\
%
tore
EROSION AND CONTROL,
CONTROL
Log in to download the original file

Delegated Report - Code - Planning OPW21 0216.docx · 313 KB (small file)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗