Council archive · source document
Decision Notice OPW23 0179 · OPW23/0179
34. The erosion and sediment control measures must be designed, installed and maintained in
accordance with the supervising engineer instructions and the current best practice
standards * (Refer to Advisory Note).
35. The developer must ensure non-essential exposure of soil is prevented by restricting the
extent of disturbance and minimising the duration of soil exposure to adverse weather
conditions and effectively turf, cover or stabilise any disturbed area without delay and prior
to rainfall occurring.
36. The developer must ensure sediment does not leave the site or enter onto adjoining
properties or Council’s drainage system due to surface runoff or on tyres of vehicles and/or
machinery. It is essential to implement appropriate approved erosion and sediment control
measures throughout the site during all phases of construction including vehicle shakedown
pad/grid (or similar) at the access to the construction site. Where sediments or other
contaminants are deposited on a road, they must be removed so as not to enter Council’s
drainage system or waterways.
37. Prior to the completion of the development and commencement of use, all site surfaces must
be effectively stabilised using methods which have achieved effective short-term stabilisation
and which will continue to achieve effective stabilisation in the medium to long-term. For the
purpose of this condition, an effectively stabilised surface is defined as one that does not, or
is not likely to result in visible evidence of soil loss caused by sheet, rill or gully erosion or
lead to sedimentation, or lead to water contamination.
LANDSCAPE
During Construction
38. All works must be constructed, and work procedure undertaken in accordance with:
a. The approved plans/documents and conditions detailed in this Decision Notice.
b. The relevant conditions of the higher order Material Change of Use approval viz.
MCU22/0171 to which this approval relates.
c. All relevant Council Planning Scheme Policies, standard drawings, standard
specifications, and guidelines.
Landscaping Works
39. Landscape works must be supervised, undertaken, and certified by qualified persons*. All
works must be completed in accordance with this Decision Notice.
(* Refer to Advisory Note)
40. Landscape works must:
a. Ensure amenity or sales signage and ancillary infrastructure is not installed within the
road reserve.
b. Ensure permanent irrigation is not installed within the road reserve.
41. Where damage occurs to any Council asset as a result of the development works, it must be
repaired immediately where it creates a hazard that presents risk to person or property. Other
damage must be repaired prior to completion of works.
42. Street trees must:
a. Meet AS2303 Tree stock for landscape use.
b. Be located in accordance with engineering requirements for safe vehicle and
pedestrian sight lines.
Plans and Documents
43. Development undertaken in accordance with this approval must generally comply with the
approved plans of development. The approved plans are listed in the following table unless
otherwise amended by these conditions.
Page 8 of 14
Document Set ID: 22929254
Version: 3, Version Date: 05/04/2024
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Decision Notice OPW23 0179.pdfRelated documentApplication case desk ↗
About this file
- File size
- 194 KB (small file)
- File type
No other editions are linked here.