Council archive · source document
0015D9DE.001
Text sections not matched to the original PDF pages. See original document to check page numbers.
Form 6 – Compiled Decision Notice
INTEGRATED PLANNING ACT 1997, S3.5.15, IDAS DEVELOPMENT APPLICATION
File No: 2006/1991 Date of Decision: 27 August 2007
1. APPLICANT DETAILS
Name: Timothy E Sipp
Postal address: PO Box 1009
NOOSAVILLE QLD 4566
Phone no: Fax no: Mobile: 0418 500 521
2. PROPERTY DESCRIPTION
Street address: 22, 1/22, 2/22 and 24 Elizabeth Street
Suburb/locality NOOSAVILLE
Real property Lots 0, 1 and 2 on SP151420 and Lot 6 on RP64525
description:
3. OWNER DETAILS
Name: Jeremy E C Griffiths
Postal address: 24 Elizabeth Street
NOOSAVILLE QLD 4566
4. REFERRAL AGENCIES
Referral Agency Address Basis
Nil
5. APPLICATION TYPE
Development Development Details Preliminary Development
Approval Permit
Operational Works - Stormwater In accordance with Engineering No Yes
drawing No.12051-GD-E dated
11 October 2006 by SCG
Consulting Engineers or as
modified herein.
6. DECISION DETAILS
Council on 20 November 2006 decided to approve the application and grant a Development Permit, subject to
conditions.
In relation to the representations made in respect to condition 22, Council on 5 February 2007 resolved to delete
condition 22.
In relation a to a request to change conditions of the development approval, Council on 27 August 2007 resolved
to:
A. Agree to amend Condition 5 as follows:
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalFull text of the other 7 sections
Section 2
NOOSA COUNCIL IDAS Development Application Decision Notice 2
Condition 5
New private easements for the Drainage of stormwater, minimum 1.4 m wide shall be created, (a) within
Lot 2 SP 151420 to benefit Lot 6 RP 69150, (b) within Lot 1 SP 151420 to benefit Lot 6 RP 69150 & Lot 2
SP 151420, (c) within Lot 6 RP 64525 to benefit Lot 6 RP 69150, Lot 2 SP 151420 & Lot 9 RP 64525. The
easement is to be centrally located over the pipework and is to be of sufficient width to ensure all
associated pits and pipes are wholly contained within the easement.
B. Issue a Compiled Decision Notice.
7. APPLICABLE CODES
The developer must comply with the following codes for self-assessable development related to the development
approved under this Development Permit:-
NA
8. CONDITIONS
This approval is subject to conditions. Noosa Council conditions are attached.
9. FURTHER DEVELOPMENT PERMITS REQUIRED
Type of Development Permit required Subject of the required Development Permit
NA
10. RIGHTS OF APPEAL
Rights of appeal in relation to this application are attached.
11. ASSESSMENT MANAGER
Name: Noosa Council Signature: Date:
DECISION NOTICE HISTORY
Original Decision Notice 20 November 2006.
Negotiated Decision Notice deleting condition 22.
Compiled Decision Notice with amendment to
Condition 5.
NSC c:\docume~1\amoore\locals~1\temp\bcl technologies\easypdf 5\@bcl@80007420\@[email protected]
Section 3
NOOSA COUNCIL IDAS Development Application Decision Notice 3
Noosa Council Conditions
INTEGRATED PLANNING ACT 1997, IDAS DEVELOPMENT APPLICATION
1. The development shall be carried out in accordance with Engineering drawing No.12051-GD-E dated 11
October 2006 by SCG Consulting Engineers or as modified herein.
2. The method of connection to Council’s existing drainage as shown on plan No. 12051-GD-E is not
acceptable. The 375mm dia. Pipe must be connected Council’s existing box culvert via a 1050mm dia
manhole.
3. A Construction Management Plan for works in Elizabeth Street shall be submitted to Council prior to the
“pre start” meeting. This plan shall detail any road closures, traffic control and necessary signage required
to carry out the works.
4. A minimum of 300mm depth of lean mix backfill must be used over the new 375mm dia pipe within the
Elizabeth Street pavement area.
5. New private easements for the Drainage of stormwater, minimum 1.4 m wide shall be created, (a) within
Lot 2 SP 151420 to benefit Lot 6 RP 69150, (b) within Lot 1 SP 151420 to benefit Lot 6 RP 69150 & Lot 2
SP 151420, (c) within Lot 6 RP 64525 to benefit Lot 6 RP 69150, Lot 2 SP 151420 & Lot 9 RP 64525. The
easement is to be centrally located over the pipework and is to be of sufficient width to ensure all
associated pits and pipes are wholly contained within the easement.
6. A site control and/or compliance bond of $5,000 is to be submitted to Council prior to the pre-start meeting.
The pre-start meeting will only be held once Council's Construction Technical Officer has confirmation that
the bond monies have been received by Council.
The bond will be refunded less any costs incurred by Council in ensuring compliance with these conditions
or any additional inspections incurred for substandard work or work undertaken not in accordance with this
permit.
7. Council’s Construction Technical Officer (ph 0410 512 505), shall be given seven (7) days’ notice of
intention to commence works to arrange a “pre start” meeting regarding the civil works.
8. The principal contractor must have all the appropriate insurance and public liability documentation to carry
out the works. The principal contractor is also responsible to ensure that any sub contractors also have the
appropriate insurance and public liability documentation.
9. Prior to the “pre start” meeting, the principal contractor must be provided with a copy of Council’s
signed approved drawings and conditions by the applicant.
10. The Consulting Engineers for the project shall be currently Registered Professional Engineers of
Queensland (RPEQ). The consulting engineers are responsible for arranging all inspections, with
Council’s Construction Technical Officer or nominated staff. Council’s Construction Technical Officer shall
provide an inspection form for signing off by the Engineer at appropriate stages of construction, during on-
site meetings. Construction Technical Officer will also sign the form at each stage when conditions
required have been satisfied. The works will be accepted “On Maintenance” after this form, signed by the
inspector for each stage is complete, together with a letter from the Engineer requesting that the works go
“On Maintenance”.
11. Prior to works commencing, Council is to be advised of the Engineer (RPEQ) supervising the project. (This
person will be the contact for the project).
12. Council standards shall apply to these works unless otherwise modified herein.
13. The person acting on this permit shall ensure that its consultants and contractors take all reasonable care
during the construction of the engineering works to ensure that Council property, road pavements or
facilities (such as underground drainage, water supply, sewerage, footpaths, kerbing, landscaping, street
furniture etc.) are protected against any damage or interference whatsoever.
NSC c:\docume~1\amoore\locals~1\temp\bcl technologies\easypdf 5\@bcl@80007420\@[email protected]
Section 4
NOOSA COUNCIL IDAS Development Application Decision Notice 4
If any Council property or facilities should be damaged by the Applicant or any of its Consultants or
Contractors through any cause whatsoever in the course of, directly or indirectly, carrying out the
engineering works, the Applicant and/or its Contractors shall forthwith notify the Manager-Land
Development and shall forthwith rectify the damage to that property or facility at its cost and to the
satisfaction of the Manager-Land Development, prior to the sealing of the easement plan or, alternatively,
the Applicant may request the Council to carry out the rectification work at the Applicant’s cost, such cost
being paid by the Applicant to the Council prior to the sealing of the easement plan, provided that in the
case of emergency the Council shall be entitled to rectify such damage at the cost of the Applicant, such
cost being paid prior to the sealing of the easement plan`.
A management strategy to ensure no damage occurs to Council services shall be given to Council for
assessment prior to the pre start meeting.
14. The development of the site shall be carried out in such a manner as to prevent dust and/or sand nuisance
to residents and/or tenants in the vicinity of the development.
15. Construction work and other associated activities are permitted only during the hours of 7.00 am and 6.00
pm Monday to Saturday. No work is permitted on Sundays or public holidays, except where extended
hours are approved by the Manager-Land Development or his nominee.
16. All signage, including that for safety during construction shall be in accordance with the Manual of Uniform
Traffic Control Devices and Traffic Infrastructure (Roads) Act.
17. Safe pedestrian access on Elizabeth Street shall be maintained at all times. Should footpath / road
closures be necessary to carry out construction works, Council’s Construction Technical Officer (ph 0410
512 505) must be notified prior to the proposed closure.
18. Sediment and erosion control measures must be in place prior to works commencing. If such measures
are not in place or are not satisfactory, “on the spot “fines may be issued. Such fines can be issued if
sediments from the site are found to enter or have the potential to enter Council’s stormwater system or
natural waterways. Although the sediment and erosion control measures have been approved on drawing
No<, Council’s Manager – Land Development may request further controls to be installed should approved
measures be inefficient.
19. All stormwater drainage lines including private drainage lines (also known as inter-allotment drainage
lines) or as otherwise approved by Council’s Manager of Land Development shall be inspected by closed
circuit television (CCTV) at the completion of all works and immediately prior to acceptance ‘On
Maintenance’. Council’s Construction Technical Officer shall be advised of the timing of this inspection.
A report of the CCTV inspection, including photographic records (which includes photos & video
recordings burnt onto a CD) of the inspection shall be submitted to the Council for approval. Any defects
or substandard works shall be recorded and accurately illustrated on the drainage plan showing the
location of the defect(s).
Substandard work will not be accepted ‘On Maintenance’ and must be rectified at the applicants expense
with a further CCTV inspection arranged once the rectification works have been completed.
To this extent all CCTV inspections, including any additional inspections necessary following defect
identification and rectification, shall be entirely at the applicant’s expense. Any costs incurred by Council
in reviewing the CCTV inspection results shall also be borne by the applicant.
20. Prior to acceptance of civil works to become Council assets "On Maintenance", the lodgement of
satisfactory “As Constructed” records shall be submitted to Council.
As Constructed drawings and data shall be certified by a qualified experienced Civil Engineer (RPEQ) for
design intent, and a Licensed Surveyor shall certify the cadastre and the location, level and type of all
services and structures. All of which shall be submitted to Council for checking and for Council’s records.
The data must fully detail levels for all engineering works including but not limited to drainage structures,
finished ground levels and pavement surface levels. The data shall be submitted in the Asset Design and
As Constructed (ADAC) digital format. (Guidelines on the use of ADAC are available at
www.adac.com.au) and Council’s Planning Scheme Policy 5 – Engineering Design Standards – Roads,
Drainage and Earthworks.
Approval of works shall not be granted until all As Constructed information has been supplied and
accepted by Council.
NSC c:\docume~1\amoore\locals~1\temp\bcl technologies\easypdf 5\@bcl@80007420\@[email protected]
Section 5
NOOSA COUNCIL IDAS Development Application Decision Notice 5
21. A 5% cost of works to become Council assets or $1,500 bond (whichever is the greater) will be imposed
on construction works during the maintenance period, which is a minimum period of 12 months duration.
Such bond must be lodged by, and shall only be accepted from the Developer for the works.
22. Deleted.
23. Pursuant to Section 3.5.21(5) of the Integrated Planning Act 1997, the Relevant Period is two (2) years
from the day this permit takes effect during which time all conditions must have been complied with and
the Plan of Survey lodged with the Council for endorsement.
24. Notwithstanding that Council has checked the plans with due care, where it is found during construction
that variations from Council's standards exist, then Council standards shall apply
NSC c:\docume~1\amoore\locals~1\temp\bcl technologies\easypdf 5\@bcl@80007420\@[email protected]
Section 6
NOOSA COUNCIL IDAS Development Application Decision Notice 6
Local Laws, Policies & State
Regulation Requirements
INTEGRATED PLANNING ACT 1997, IDAS DEVELOPMENT APPLICATION
THE FOLLOWING ADVICES ARE FOR INFORMATION PURPOSES ONLY AND DO NOT FORM
CONDITIONS OF APPROVAL
1. Should any changes or modifications to the approved plans be required as a result of construction
constraints, a Change to an Existing Approval Application under the Integrated Planning Act must be
made. Amended plans clearly indicating the changes must be lodged with this application along with the
appropriate fees.
NSC c:\docume~1\amoore\locals~1\temp\bcl technologies\easypdf 5\@bcl@80007420\@[email protected]
Section 7
NOOSA COUNCIL IDAS Development Application Decision Notice 7
Appeal Rights
INTEGRATED PLANNING ACT 1997, IDAS DEVELOPMENT APPLICATION
The following is an extract from the Integrated (6) If an application involves assessment against a
Planning Act (Chapter 4). concurrence agency code, appeal rights for
submitters for the application are not available against
Division 8 - Appeals to court relating to the part of the approval that represents the
development applications concurrence agency’s response for the code.
Appeals by applicants Appeals by advice agency submitters
4.1.27.(1) An applicant for a development application 4.1.29.(1) An advice agency may, within the limits of
may appeal to the court against any of the following- its jurisdiction, appeal to the court about the giving of
(a) the refusal, or the refusal in part, of a development a development approval for a development
application; application if-
(b) a matter stated in a development approval, (a) the development application involves impact
including any condition applying to the assessment; and
development, and the identification of a code (b) the advice agency told the applicant and the
1
under section 3.1.6; assessment manager to treat its response to the
(c) the decision to give a preliminary approval when a application as a submission for an appeal.
development permit was applied for; (2) The appeal must be started within 20 business
(d) the length of a currency period; days after the day the decision notice or negotiated
decision notice is given to the advice agency as a
(e) a deemed refusal. submitter.
(2) An appeal under subsection (1)(a) to (d) must Appeals for matters arising after approval given
be started within 20 business days (the “applicant’s (co-respondents)
appeal period”) after the day the decision notice or
negotiated decision notice is given to the applicant. 4.1.30.(1) For a development approval given for a
development application, a person to whom any of the
(3) An appeal under subsection (1)(e) may be following notices have been given may appeal to the
started at any time after the last day a decision on the court against the decision in the notice-
matter should have been made.
(a) a notice giving a decision on a request for
Appeals by submitters extension of the currency period for an approval;
4.1.28.(1) A submitter for a development application (b) a notice giving a decision on a request to make a
may appeal to the court about- minor change to an approval.
(a) the giving of a development approval, including (2) The appeal must be started within 20 business
any conditions (or lack of conditions) or other days after the day the notice of the decision is given
provisions of the approval; or to the person.
(b) the length of a currency period for the approval. (3) Subsection (1)(a) does not apply if the
approval resulted from a development application
(2) The appeal must be started within 20 business
(superseded planning scheme) that was assessed as
days (the “submitters appeal period”) after the day
if it were an application under a superseded planning
the decision notice or negotiated decision notice is
scheme.
given to the submitter.
(4) Also, a person who has made a request
(3) If a person withdraws a submission before the
mentioned in subsection (1) may appeal to the court
application is decided, the person may not appeal the
against a deemed refusal of the request.
decision.
(5) An appeal under subsection (4) may be started
(4) If an application involves both impact
at any time after the last day the decision on the
assessment and code assessment, appeal rights for
matter should have been made.
submitters are available only for the part of the
application involving impact assessment. Division 9 - Appeals to court about other matters
(5) If an application is processed under section Appeals for matters arising after approval given
6.1.28(2), appeal rights for submitters for the (no co-respondents)
application are available only for the aspects of the
development that would have required public 4.1.31.(1) A person to whom any of the following
notification under the repealed Act. notices have been given may appeal to the court
against the decision in the notice-
1
Section 3.1.6 (Preliminary approval may override local planning (a) a notice giving a decision on a request to change
instrument) or cancel a condition of a development approval.
NSC c:\docume~1\amoore\locals~1\temp\bcl technologies\easypdf 5\@bcl@80007420\@[email protected]/08/07
Section 8
NOOSA COUNCIL IDAS Development Application Decision Notice 8
2
(b) a notice under section 6.1.44 giving a decision to
change or cancel a condition of a development
approval.
(2) The appeal must be started within 20 business
days after the day the notice of the decision is given
to the person.
(3) Also, a person who has made a request
mentioned in subsection (1)(a) may appeal to the
court against a deemed refusal of the request.
(4) An appeal under subsection (3) may be started
at any time after the last day the decision on the
matter should have been made.
Appeals against decisions to change approval
conditions under the repealed Act
4.1.33A.(1) A person who is dissatisfied with a
decision made on an application to change the
conditions attached to an approval given under
section 2.19(3)or section 4.4 of the repealed Act may
appeal to the court against-
(a) the decision; or
(b) a deemed refusal of the application.
(2) An appeal under subsection (1)(a) must be
started within 20 business days after the day notice of
the decision is to be given to the person.
(3) An appeal under subsection (1)(b) may be
started at any time after the last day a decision on the
matter should have been made.
Appeals against local laws
4.1.33B.(1) An applicant who is dissatisfied with a
decision of a local government or the conditions
applied under a local law about the use of premises or
the erection of a building or other structure permitted
by the planning scheme may appeal to the court
against the decision or the conditions applied.
(2) The appeal must be started within 20 business
days after the day notice of the decision is given to
the applicant.
2
Section 6.1.44 (Conditions may be changed or cancelled by
assessment manager or concurrence agency in certain
circumstances)
NSC c:\docume~1\amoore\locals~1\temp\bcl technologies\easypdf 5\@bcl@80007420\@[email protected]/08/07
Used in these records
0015D9DE.001.pdfRelated documentPublic source context ↗
COMPILED Decision Notice [As Published]Related documentApplication case desk ↗
About this file
- File size
- 38 KB (small file)
- File type
No other editions are linked here.