Fauna Management Plan
1 Serenity Close Noosa Heads
4.0 Conclusion
This FMP focuses on the works carried out within the site prior to, during and following vegetation
clearing. This FMP has been prepared to ensure all works associated with construction activities are
undertaken in such a way as to minimise any potential risks to fauna values in order to achieve effective
site-based environmental management.
This FMP has been prepared in accordance with the relevant legislation and approvals, applicable to
the project. Through this implementation FMP, the operator demonstrate that all reasonable and
practicable measures have been taken to comply with relevant conditions of approval and the general
environmental duty.
Mitigation measures outlined in this report can be summarised as:
• Protection and retention of ecological value area through the use of temporary fences; and,
• Minimise direct impact of vegetation clearing on fauna species with the presence of a qualified
fauna spotter on site at all time during vegetation clearing.
The proposed development has been designed to satisfy the environmental requirements of the Noosa
Council. By implementing a number of key recommended actions designed to minimise impacts during
the construction and operational phases, it is considered that the proposed development will not have
significantly adverse impacts upon fauna values within the local area.
PR18082_FMP_Settlers Cove Page 8
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records