Site Specific Conditions
3. A site control and/or compliance bond of $10,000 is to be submitted to Council prior to the
pre-start meeting. The pre-start meeting will only be held once Council's Construction
Engineering Officer has confirmation that the bond monies have been received by Council.
The bond will be refunded less any costs incurred by Council in ensuring compliance with
these conditions or any additional inspections incurred for substandard work or work
undertaken not in accordance with this permit.
Bonds must:
a. meet the requirements of Council’s relevant Planning Scheme Policy for performance
and uncompleted works;
b. be calculated using a schedule of works and relevant bond equation;
c. Include GST;
d. have approval of the bond calculations and amount from Council prior to lodgement;
e. be lodged with Council and accompanied by the Bond Administration Fee/s; and
f. be requested for release by writing to Council, when relevant approval requirements
have been met.
PRIOR TO COMMENCEMENT OF WORKS
Engineering
4. Submit amended plans to Council as described in the List of plans requiring amendments.
Plans must be submitted and approved prior to the pre-start meeting.
5. All necessary approvals from external service providers (eg Unitywater) and external parties
on which the development works are proposed have been obtained and a copy supplied to
Council.
6. Copies of the approved plans, duly signed by the consultant Registered Professional
Engineer of Queensland (RPEQ) must be provided to Council’s Engineering Officer
Construction at the “pre start” meeting.
7. A condition report including photographs of the frontage of the site must be completed and
submitted to council at the prestart meeting / prior to any works commencing.
8. Certificates demonstrating currency of public liability insurance and works insurance covering
the works must be submitted to Council prior to the prestart meeting.
9. Council must be contacted at least 5 working days prior to any works commencing to
organise a prestart. The contact number to arrange a pre-start meeting is 5329 6500. The
pre-start meeting must include the relevant parties for the following aspects of the works:
a. Civil engineering works;
b. Landscape works;
c. Erosion and sediment control works; and
d. Other relevant parties.
10. A preliminary Construction Management Plan must be submitted with the Operational Works
application and must address the following:
a. Traffic management during all phases of construction;
b. Adequate parking arrangements for works and deliveries;
c. appropriate traffic signage in accordance with the Manual of Uniform Traffic Control
Devices (MUTCD); and
d. provision for safe pedestrian access across the frontage of the site both during daily
construction and after daily construction has ceased.
Page 10 of 21
Document Set ID: 24087855
Version: 5, Version Date: 03/09/2025
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Decision Notice - Approved by Delegation of Authority - MCU25 0054 & OPW25 0077 (As Published).pdfRelated documentApplication case desk ↗
Decision Notice - Approved by Delegation of Authority - MCU25 0054 & OPW25 0077 (As Published)Related documentApplication case desk ↗
About this file
- File size
- 211 KB (small file)
- File type
No other editions are linked here.