Minor Change Existing Approval 131999.982588.2

of 1

Page text shows just the words. Original shows the document exactly as it was published.

Officer: 	Lisa Pienaar
Direct Telephone: 	07 53296514
Our Reference:	131999.982588.2
Your Reference:	n/a
12 July 2021
CJ Young & PW Young
C/- Ken Drew Town Planning Pty Ltd
PO Box 860
HAMILTON  QLD  4007

[email protected]
Dear Applicant
Decision Notice – Minor Change
Planning Act 2016
I refer to your application received on 26 May 2021, requesting a minor change to an existing development approval. Council decided your requested changes.
Details of the decision are as follows:
APPLICATION details
Application No:	131999.982588.2
Street address:	Noosa Pavilions 9/34 Bushlands Dr Noosaville Qld 4566
Real property description:	Lot 9 SP 131675
Planning Scheme:	Noosa Plan 2020 (25 September 2020)
Decision details
The following type of approval was issued on 6 March 1999.
Development Permit for Material Change of Use of Premises – Multiple dwelling (46 units)
In relation to the request to make a minor change to the existing approval, Council on 8 July 2021, decided to approve the requested changes. The changes are detailed below.
A.	Approve the change.
B.	Amend condition 56.
C.	Include the following additional condition 57
currency period of approval
The currency period for this development approval is stated in Condition 52.1 of the Assessment Manager Conditions.
assessment manager conditions
Building
The plans submitted for a Development Permit for building works are to comply with the approved plans.
Construction work and other associated activities are permitted only during the hours of 7.00 a.m. to 6.00 p.m. Monday to Saturday. No work is permitted on public holidays, except where extended hours are approved by the Manager of Building.
Health
Any flat or unit intended to be let out for fee or reward is to be licensed annually with Council’s Health Department in accordance with the provisions of Chapter 43 of Council’s Local Laws prior to such letting.
Swimming pools are to be licensed annually with the Council’s Health Department in accordance with the provisions of Chapter 42 of Council’s Local-Laws.
Swimming pool or spa pumps are to be located in a manner which prevents noise disturbance beyond the subject land in accordance with the Environmental Protection (Noise) Policy.
From the 1st January 2000, a requirement will exist to apply under the Environmental Protection Act (EPA) for an “approval” to conduct the following works:-
Land development - clearing (other than for agricultural purposes) or reclaiming land having an area of more than 20,000m²
Constructing premises or civil engineering structures - constructing or demolishing:-
residential premises (other than a class 1 or 2 building, containing not more than 2 dwelling units, or a class 10 building under the Standard Building Law) or commercial or industrial premises;
bridges, roads or other engineering structures (other than roads, bridges or other engineering structures on rural properties used for primary production, railways or road maintenance or repairs).
In accordance with the Environmental Protection (Water) Policy 1997, all sand, silt, mud, paint, cement, concrete, builders waste or rubbish shall not be permitted to enter or be placed where it could reasonably be expected to move into a roadside gutter, stormwater drain or a water course. On the spot fines apply for such offences.
Engineering
THE FOLLOWING CONDITIONS ONLY APPLY TO PRECINCT ‘F’
The location of the garbage refuse points in the vicinity of lots 5-8 of Precinct ‘F’ shall be relocated northward and the ‘T’ intersection widened to facilitate the turning manoeuvres of Noosa Council’s garbage trucks.
In Precinct ‘F’, the common driveways shall be constructed without a central median to facilitate turning manoeuvres for car spaces 5-7 and 8-10.
The hammerhead turning facility at the end of Satinwood Street in Precinct ‘G’ is to be reconstructed to provide an overland flow path for 1:100 storm events flowing from adjoining properties.
Floor levels of units 1 and 2 shall be 300 mm above the Q100 level of any overland flow path.
THE FOLLOWING CONDITIONS ONLY APPLY TO PRECINCT ‘H’
In Precinct ‘H’, the common driveways to lots 3/4 and 13/14 shall be constructed without a central median to facilitate turning manoeuvres for car spaces 9-10 and 1-2 respectively.
In Precinct ‘H’, units 10-14 shall be located in such a manner so as to provide an overland flow path past the buildings during a 1:100 year design storm event.
Floor levels of units shall be a minimum of 300 mm above the Q100 level of any overland flow path.
Particular care shall be taken to ensure that overland flows do not include the driveways leading to garages within the buildings.
THE FOLLOWING CONDITIONS ONLY APPLY TO PRECINCT ‘M’
In Precinct ‘M’, the manoeuvring area outside unit 16 shall be increased to facilitate the turning of Council’s garbage trucks.
In Precinct ‘M’, the north western corner of the fencing to Unit 1 shall be constructed from the front corner of the unit parallel with the adjacent road until it intersects with the side fence shown.
THE FOLLOWING CONDITIONS APPLY TO ALL 3 PRECINCTS ‘F’, ‘H’ AND ‘M’
An application for Reconfiguration of a Lot shall be made for each unit site prior to or concurrent with an application for a Development Permit for Building Work.
Units shall not be occupied until a Building Format Plan has been approved by Noosa Council and registered by the Department of Natural Resources.
The maximum height of any batter or retaining wall for any unit site or lot shall not exceed 2.0 m.  Fences erected on batters more than 1.5m high shall not exceed 1.5m in height.
All carparking spaces shall be delineated using different paving materials to the adjacent roadways. These spaces shall meet the design requirements of AS2890.1 -1993 for Class 3 users.
The access off Bushlands Drive into Precinct ‘M’ shall  be constructed as public road.
Legal documentation to be presented to Council as a requirement of this Development Permit shall be submitted in the correct form, with the fees prescribed in Council's adopted fee schedule.
Any task associated with completing this or any subsequent Development Permit shall be at no cost to Council.
All roads shall be constructed to Council's requirements, including the provision of kerb and channel, asphaltic concrete pavement, and formed footpath as follows:-
Internal roads - minimum 15 metre road widths, minimum 5.5 metre wide asphaltic concrete pavement kerb to kerb.
External roads 15 metre road reserve, minimum 5.5 metre wide asphaltic concrete pavement kerb to kerb and 1.2m wide footpath
The access from Bushland Drive into Precinct ‘H’ shall be constructed with kerb radii of 10 metres, and in differing material to the through road.
Footpaths and road verges are to be topsoiled and grassed following completion of roadworks.
A raised threshold, in differing pavement material, shall be constructed within the common property at the junction with the external roads.
Alterations to lot sizes, and layout may be required following approval by Council of the internal roadworks and drainage design.
Engineering works involving the construction of pavements, kerb and channel, footpaths, turnouts, stormwater drainage, water supply and sewerage reticulation, must be designed and constructed to the standards and requirements of Council's "Engineering Design Standards" Manual.
The engineering drawings and specifications associated with these works shall be prepared by a Registered Professional Civil Engineer, QLD.  A Development Permit for operational Works must be obtained prior to commencing any work.
Any subsequently approved Operational Works are to be carried out in a manner that prevents:
Dust nuisance to residents in the vicinity.
Transfer of dirt and debris onto existing roads.
Excessive noise (less than 1.5 Dba above ambient measured at the lot boundaries).
Diminution of neighbourhood amenity (long term parking of employees vehicles, parking of construction equipment etc.)
A programme of works detailing proposed nuisance prevention measures is to be submitted for approval by Noosa Council with any operational works application.
The proposed names of new private roads shall be lodged, for approval by Council, with the application for a development permit for operational works.
Names are to be selected from any of the following categories:-
Easily pronounced words of Murri languages.
Names or words of local significance or historical interest.
Flora, fauna, industry, topographical, geological and similar features and terms relative to the district.
Surnames of persons of merit or historical significance.  (Personal names should be avoided.)
Approval will not be given to a name that is the same or similar to the name of another road in the Shire, or of a road in close proximity in a neighbouring Shire.  Names that are not easily pronounced, or may cause confusion to emergency services are to be avoided.
The name plate and signpost for the private road designed to Council’s standards may be obtained from Council upon payment of $225 per sign and must be erected as part of the operational works for road and drainage works.
Any person acting on this or any subsequent and related development permit shall prevent erosion and sediment export from the site.
Site control measures such as silt fencing, controlled gravel access to the site and controlled disposal of waste, may be necessary. The developer shall be required to submit an erosion and sediment control plan for approval by the Development Engineer, prior to the issue of a Development Permit for Operational Works.
Site control measures shall be kept in place and properly maintained until all work, including building works for the construction of the units and landscaping, is completed.
A bond of $20,000 shall be lodged with Council prior to the issue a Development Permit for Operational Works for either the construction of road and stormwater drainage works or for services associated with this development, which ever occurs first.
The bond is to ensure compliance with the conditions contained within this approval and will be refunded following satisfactory completion and acceptance of all works “On Maintenance”, less any expense incurred by Council in effecting compliance with these conditions of the Permit.
Stormwater drainage shall be designed and constructed to Council's requirements, and shall include measures to protect proposed allotments from run-off from surrounding land.  The design shall include controls for; gross pollutants, nutrient runoff, oil and grease, and silt and sediment.
Underground stormwater systems shall be designed in accordance with Noosa Council’s Engineering Design Standards, and shall be connected, where possible to Council's existing systems.
An easement of minimum width 4.0 metres shall be granted in favour of Council over any stormwater pipes which traverse private property.
Suitable overland escape routes shall be provided for stormwater runoff in excess of the piped design frequency.
Designs that concentrate stormwater onto adjoining land shall require separate formal approval from the owner of the land or relevant Government Authority.  This approval shall be submitted with the design and application for a development permit for operational works.
Property drains including field inlets shall be provided along the rear of all lots falling away from the road where roof water cannot be connected to the frontage kerb and channel.  Property drains shall be designed to carry roof water and allotment surface drainage.  The minimum size shall be 150 mm. diameter uPVC.
Appropriate documentation shall be prepared by the applicant's Solicitor and submitted to Council's Solicitor for approval prior to approval of any Plan of Survey.
A property note shall be attached to each lot advising prospective owners that they and the Body Corporate are responsible for maintenance of the property drain.
Where areas are to be affected by earthworks, the top 100 mm of topsoil shall be stripped and stockpiled for later reuse.  At the completion of all building and construction works, and prior to landscaping and turfing, the stripped topsoil shall be respread in total over the site.
Where the filling of the allotments is required by the Shire Engineer, the site shall be filled so that the allotments drain towards road frontage or the proposed drainage system.
Filling works undertaken on the site shall be carried out in accordance with Section 3.8 of Council's "Engineering Design Standards" Manual so as not to cause any ponding of water on any adjoining land, or the blockage of, or interference with any natural water courses.
Fill shall be compacted to 95% relative dry density as per Main Roads Department Test No. Q8A, and all work shall be supervised by a recognised Geotechnical Engineer who shall certify that all lots have been compacted to the required standard.
As Constructed drawings showing the extent and finished levels of the filling works are to be submitted for Council's records.  An appropriate noting shall be placed on Council's rates records to advise prospective purchasers of the lots that special foundations requirements apply.
Any existing fill on the site which does not comply with Council's requirements shall be removed to the satisfaction of the Shire Engineer prior to additional filling works commencing.
Alteration of any public utility, mains, or facilities necessitated by the development of the land or associated development external to the site shall be at no cost to Council.
A contribution in an amount of $615 per additional unit is required to be paid towards the upgrading of the Beckmans Road/Eumundi Road intersection. This contribution is subject to CPI variation from December 1998 up to the date of payment.
Payment of the contribution is required prior to approval of the Building Format Plan.
Contributions shall be paid in accordance with Council's Policies for Water Supply Headworks Contributions’ and ‘Sewerage Headworks Contributions’.
An estimate only of the charges as at December 1998 under the current policies is as follows:-
Water Supply	$ 2,705 	per additional unit
Sewerage	$ 2,146	per additional unit
The actual rate of contribution to be paid will be the contribution rate current at the time of payment of the contribution.
This payment shall be made prior to approval of the Building Format Plan.
Underground electricity service shall be supplied to each unit.  Full details of the proposal forwarded to ENERGEX for its approval shall be submitted to Council for its information.
The approval of ENERGEX and a “Certificate for Electricity Supply to Subdividers” will be required to sighted by Council prior to accepting the subdivision on maintenance.
Such agreement shall be wholly at the applicant's expense, and shall not entail a financial encumbrance on future purchasers of the proposed lots.
Lighting of the internal roads is to be provided throughout each precinct in accordance with the recommendations of the relevant Australian Standard.  Details of the design and the standards applied shall be submitted to Council for its information.
The lighting design shall be carried out by a qualified lighting designer.
The electrical reticulation design shall be carried out by an Electrical Design Consultant approved by ENERGEX.  The consultant shall liaise with Council’s Works Technical Officer during preparation of the design.
The requirements of ENERGEX and TELSTRA in relation to any existing services which currently traverse the subject site shall be satisfied.  Arrangements shall be made to formalise any existing informal services arrangements to the satisfaction of the relevant authorities prior to Council endorsing its consent on the Plan of Survey.
A reticulated water supply system for each precinct shall connect to Council’s existing systems, including a metered water connection to the property boundary of each proposed new unit within the development site.
Fire hydrants are to be provided throughout the development site in accordance with Council and Queensland Fire Service standards.
The system is to be designed in accordance with Council's standards and submitted for approval with an application for a Development Permit for Operational Works.
All connections to existing systems are to be carried out by Council at no cost to Council.
Conduits and kerb markers shall be installed for all necessary service crossings of roads to Council's satisfaction.  An "As Constructed" plan showing the  locations of the conduits shall be submitted to Council prior to acceptance of the works "On Maintenance".
A sewerage system shall be designed and constructed to the standards and requirements set out in Council’s Engineering Design Standards, to connect all new units to Council's existing sewerage reticulation system .
If the design requires the construction of a pump station and a rising main, the connection point to Council's existing system will be nominated by the Shire Engineer.
Registered easements are to be provided on the plan of survey over all sewerage mains within private property.  Easements are to be equivalent in width to twice the depth to invert level of the sewer at the deepest point within the allotment.  Easements are to be provided to and centred over the sewer line, with a minimum width of 3.0 metres.
A Development Permit for Operational Works must be obtained prior to the commencement of works.
All existing noxious weeds, including but not limited to Groundsel bush (Baccharis halimifolia), Giant Rats Tail Grass (Sporobolus pyramidalis and S. natalensis), and Salvinia molesta, shall be cleared from the entire property, prior to the release of the sealed Survey Plan.
Under State Legislation, Gall Fly (Rhopalomyia Califormica) is not a recognised means of control or destruction of groundsel bush.  Any existing Declared Noxious Plants under the Rural Lands Protection Act (1985) which have a control category of P2, P3 or P4 be controlled in a manner pursuant to the Rural Lands Protection Act (1985).Note that Council requires thirty (30) days notification following completion of eradication works prior to Council's Noxious Weeds Officer inspecting the subject site.
Existing vegetation on the site is to be retained except where required to be removed to enable construction of approved earthworks, roadworks, and services or as otherwise approved by Council.  Clearing will only be approved in areas to be affected by earthworks.
Prior to the ‘Pre Start’ meeting, a site inspection is to be carried out with relevant Council officers, the Contractor and Supervising Engineer after road centrelines have been established, and before any clearing.
This inspection is to define the limits of clearing for this development.
Cleared vegetation is to be suitably processed by a method approved by the Shire Engineer or removed from the site.
The disposal method is to be approved by the Shire Engineer prior to approval for the clearing works being given.
Burning off is not an acceptable means of disposal and will not be approved.
The following methods disposal are suggested, though other methods will be considered:-
Processing through a woodchipper or shredder.
The resulting mulch is to be stockpiled loose in heaps of less than 1000 cubic metres, less than 2.5 metres high with a minimum of 10 metres between edges of heaps.
Disposal for firewood.
Disposal for landscaping purposes.
Transport to alternative site for breaking down materials.
The development site shall be landscaped in accordance with Council’s Policy ‘Landscaping Guidelines’, and properly prepared landscaping plans are to be submitted for approval with an application for a Development Permit for Operational Works (Landscaping).
The landscaping plans shall at least address:-
Street tree planting
Tree planting and landscaping of common property
Removal of undesirable species
Such landscaping is to be completed in accordance with the approved landscaping plan prior to acceptance of the development on maintenance and maintained thereafter during the maintenance period to the reasonable satisfaction of the Shire Engineer.
A Development Permit for Operational Works must be obtained prior to the commencement of any works.
A vegetation retention plan is to be submitted with the landscaping plan.  The vegetation retention plan is to indicate:-
road and service locations
vegetation to be retained
measures employed to ensure vegetation retention.
If any Council property or facilities (such as underground drainage, water supply and sewerage) is damaged by the applicant or any of its consultants or contractors through any cause whatsoever in the course of, directly or indirectly, carrying out the engineering works, the applicant and/or its contractors shall immediately notify the Shire Engineer and immediately rectify the damage to that property or facilities at its cost.
Alternatively, the applicant may request the Council to carry out the rectification works. In cases of emergency or at its own determination, Council shall be entitled to carry out rectification of such damage.
In all cases the responsibility for the cost of the rectification work rests with the applicant, such cost must be paid prior to approval of the Building Format Plan.
Town Planning
Development undertaken in accordance with this approval must generally comply with the approved plans of development. The approved plans are numbered 8680-F.01A, H.01A and M.01A prepared by Kenneth Matheson Surveys dated 10 March, 1999 and plans A-G and associated Floor Plan prepared by Geoff Mitchell & Associates Pty Ltd dated December, 1998 and as may be amended by these conditions.
The development must be undertaken and operated in a manner that causes no detrimental effect upon the amenity of the neighbourhood by reason of the creation of excessive noise, lighting nuisance or other emissions.
The open space and setback areas are to be landscaped in accordance with Council’s Policy on Landscaping Guidelines and a properly prepared landscape plan. Such landscaping is to be completed prior to the premises being occupied and maintained at all times thereafter to the reasonable satisfaction of the Manager of Planning.
Existing trees on the site and within road reserves are to be retained, except where required to be removed due to building operations or the conduct of the approved use. The landscape plans referred to above are to denote areas of existing vegetation or existing trees proposed to be retained.
All cleared vegetation is to be suitably processed or removed from the site at the developer's expense by a method approved by the Shire Engineer. Burning off is not considered an acceptable means of disposal and will not be approved.
The developer's preferred means of disposal of cleared vegetation is to be approved by the Shire Engineer, prior to approval for the clearing works being given.
The following means of disposal are suggested, though Council is willing to consider other means on application:-
Processing through a woodchipper.
Disposal for firewood.
Disposal for landscaping purposes.
Transport to alternative site for breaking down materials.
This Development Permit for a material change of use of premises lapses if:-
the use or erection of a building or other structure associated with the use, has not been commenced within four (4) years of the date of issue of the Development Permit, unless application is made and approved by Council for an extension; or
the use of any premises pursuant to the Development Permit ceases.
Prior to the commencement of development, the developer must obtain the following Development Permits:-
Development Permit for building works;
Development Permit for plumbing and drainage works;
Development Permit for operational works of landscaping, carparking and access;
The developer shall comply with relevant conditions of the rezoning approval for this site (File R 355).
Additional conditions – 6 March 2019 – Unit 7
Additions to Unit 7 are to be in accordance with approved plan SC 1070, Rev A drawn by Apollo Patios.
The addition to Unit 7 and Unit 9 is to be connected to existing stormwater.
Additional condition – 8 July 2021 – Unit 9
Additions to Unit 9 are to be in accordance with approved Site plan, Drawing no. 001, Rev A, Roof and Section plan, Drawing no. 002, Rev B and Front and side elevations, Drawing no. 003, Rev C, prepared by Altec
referral agencies
Not applicable.
advisory notes
Infrastructure Charges
All developments and/or changes to existing developments may require payment of “Infrastructure Charges” (as applicable) in accordance with Council’s “Charges Resolution” made pursuant to the planning legislation and regulations current at the time of issue.
property notes
Not applicable.
variation approval details
Not applicable.
further development permits required
Development Permit for Building Works.
Development Permit for Plumbing and Drainage.
submissions
Not applicable.
rights of appeal
You are entitled to appeal against this decision. A copy of the relevant appeal provisions from the Planning Act 2016 is attached.
During the appeal period, you as the applicant may suspend your appeal period and make written representations to Council about the conditions contained within the development approval. If Council agrees or agrees in part with the representations, a negotiated decision notice will be issued. Only one negotiated decision notice may be given.
other details
If you wish to obtain more information about the decision, electronic copies are available on line at www.noosa.qld.gov.au or at Council Offices.

Yours faithfully,

Lisa Pienaar
Development Planner

Enc:	Appeal Rights
Approved Plans/Documents
cc.	Unitywater

DECISION NOTICE HISTORY
Original Decision Notice – 131999.982588 (16011 DA) - .6 March 1999.
Decision Notice - Minor change 131999.982588.1 - 6 March 2019, additional conditions 55 & 56.
Decision Notice - Minor change 131999.982588.2- 8 July 2021 - with an amendment to condition 56 and additional condition 57.

	Appeal Rights PLANNING ACT 2016 & PLANNING REGULATION 2017

Chapter 6 Dispute resolution
Part 1 Appeal rights
229 Appeals to tribunal or P&E Court
(1)	Schedule 1 of the Planning Act 2016 states –
(a)	Matters that may be appealed to –
(i)	either a tribunal or the P&E Court; or
(ii)	only a tribunal; or
(iii)	only the P&E Court; and
(b)	The person-
(i)	who may appeal a matter (the appellant); and
(ii)	who is a respondent in an appeal of the matter; and
(iii)	who is a co-respondent in an appeal of the matter; and
(iv)	who may elect to be a co-respondent in an appeal of the matter.
(2)	An appellant may start an appeal within the appeal period.
(3)	The appeal period is –
(a)	for an appeal by a building advisory agency – 10 business days after a decision notice for the decision is given to the agency; or
(b)	for an appeal against a deemed refusal – at any time after the deemed refusal happens; or
(c)	for an appeal against a decision of the Minister, under chapter 7, part 4, to register premises or to renew the registration of premises – 20 business days after a notice us published under section 269(3)(a) or (4); or
(d)	for an appeal against an infrastructure charges notice – 20 business days after the infrastructure charges notice is given to the person; or
(e)	for an appeal about a deemed approval of a development application for which a decision notice has not been given – 30 business days after the applicant gives the deemed approval notice to the assessment manager; or
(f)	for any other appeal – 20 business days after a notice of the decision for the matter, including an enforcement notice, is given to the person.
Note –
See the P&E Court Act for the court’s power to extend the appeal period.
(4)	Each respondent and co-respondent for an appeal may be heard in the appeal.
(5)	If an appeal is only about a referral agency’s response, the assessment manager may apply to the tribunal or P&E Court to withdraw from the appeal.
(6)	To remove any doubt. It is declared that an appeal against an infrastructure charges notice must not be about-
(a)	the adopted charge itself; or
(b)	for a decision about an offset or refund-
(i)	the establishment cost of trunk infrastructure identified in a LGIP; or
(ii)	the cost of infrastructure decided using the method included in the local government’s charges resolution.
230 Notice of appeal
(1)	An appellant starts an appeal by lodging, with the registrar of the tribunal or P&E Court, a notice of appeal that-
(a)	is in the approved form; and
(b)	succinctly states the grounds of the appeal.
(2)	The notice of appeal must be accompanied by the required fee.
(3)	The appellant or, for an appeal to a tribunal, the registrar must, within the service period, give a copy of the notice of appeal to –
(a)	the respondent for the appeal; and
(b)	each co-respondent for the appeal; and
(c)	for an appeal about a development application under schedule 1, table 1, item 1 – each principal submitter for the development application; and
(d)	for and appeal about a change application under schedule 1, table 1, item 2 – each principal submitter for the change application; and
(e)	each person who may elect to become a co-respondent for the appeal, other than an eligible submitter who is not a principal submitter in an appeal under paragraph (c) or (d); and
(f)	for an appeal to the P&E Court – the chief executive; and
(g)	for an appeal to a tribunal under another Act – any other person who the registrar considers appropriate.
(4)	The service period is –
(a)	if a submitter or advice agency started the appeal in the P&E Court – 2 business days after the appeal has started; or
(b)	otherwise – 10 business days after the appeal is started.
(5)	A notice of appeal given to a person who may elect to be a co-respondent must state the effect of subsection (6).
(6)	A person elects to be a co-respondent by filing a notice of election, in the approved form, within 10 business days after the notice of appeal is given to the person.
231 Other appeals
(1)	Subject to this chapter, schedule 1 and the P&E Court Act, unless the Supreme Court decides a decision or other matter under this Act is affected by jurisdictional error, the decision or matter is non-appealable.
(2)	The Judicial Review Act 1991, part 5 applies to the decision or matter to the extent it is affected by jurisdictional error.
(3)	A person who, but for subsection (1) could have made an application under the Judicial Review Act 1991 in relation to the decision or matter, may apply under part 4 of that Act for a statement of reasons in relation to the decision or matter.
(4)	In this section –
decision includes-
(a)	conduct engaged in for the purpose of making a decision; and
(b)	other conduct that relates to the making of a decision; and
(c)	the making of a decision or failure to make a decision; and
(d)	a purported decision; and
(e)	a deemed refusal.
non-appealable, for a decision or matter, means the decision or matter-
(a)	is final and conclusive; and
(b)	may not be challenged, appealed against, reviewed, quashed, set aside or called into question in any other way under the Judicial Review Act 1991 or otherwise, whether by the Supreme Court, another court, a tribunal or another entity; and
(c)	is not subject to any declaratory, injunctive or other order of the Supreme Court, another court, a tribunal or another entity on any ground.
232 Rules of the P&E Court
(1)	A person who is appealing to the P&E Court must comply with the rules of the court that apply to the appeal.
(2)	However, the P&E Court may hear and decide an appeal even if the person has not complied with the rules of the P&E Court

[word/footer2.xml]
Page 11 of 11

[word/footer3.xml]
PO Box 141		P. (07) 5329 6500	[email protected]	
	TEWANTIN  QLD  4565	F. (07) 5329 6501	www.noosa.qld.gov.au
				Page 1 of 11

[word/footer4.xml]
Page 2 of 3

[word/header4.xml]
3

[Attachment: image3.png (image text)]
ee) NOOSA COUNCIL
Log in to download the original file

Minor Change Existing Approval 131999.982588.2.docx · 336 KB (small file)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.