20220171 - 14 Wyandra St SWMP

of 31

Page text shows just the words. Original shows the document exactly as it was published.

Page text read automatically using OCR, there may be inaccuracies

Original PDF page 9, section 1. The text section number identifies this passage in the reader.

The result of the iterative sizing process determined that the OSD storage will need to provide an attenuation
capacity of 3,000L/unit for the proposed roof area with the maximum possible roof area to be plumbed to the tank.
A low flow outlet consisting of a 42mm orifice plate is to be provided to the base of the OSD storage of each tank,
and a 100mm high flow outlet at the head of the tank will provide discharge for larger storm events.

Using this mitigated development model, the proposed developed flows were again compared to the existing state
as shown below in Table 3.2 Existing and proposed mitigated site peak discharge rates.

                                Table 3.2 Existing and proposed mitigated site peak discharge rates

                                                                      Wyandra Street
                                                                                                      Qchange
                                           A.E.P               Qexisting    Qmitigated   Qchange       (%)
                                                               (m³/s)       (m³/s)       (m³/s)
                                             1EY                0.022        0.022        0.000         0%
                                            50%                 0.025        0.025       0.000          0%
                                           0.2 EY               0.037        0.033       -0.004        -11%
                                            10%                 0.047        0.041       -0.006        -13%
                                             5%                 0.056        0.046       -0.010        -18%
                                             2%                 0.064        0.060       -0.004         -6%
                                             1%                 0.070        0.070       0.000          0%



As the total peak flows are equal to or below the existing site conditions for all storm events, the proposed OSD area
will provide the mitigation required for the peak flow storm events from the development.




Project number 20220171
File RECOR Preliminary Stormwater Management Report - 20220171.docx, 2022-08-24                                   Page 9 of 15
Revision 1


P +61 7 5211 1003                 A 75 Noosa Drive, Noosa Heads,Qld 4567             E [email protected]    recorconsulting.com
Log in to download the original file

20220171 - 14 Wyandra St SWMP.pdf · 3.9 MB (large file)

Large file: the download may take up to a minute.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.