OPERATIONAL PLAN 2020-21 PROGRESS REPORT
ATTACHMENT 1
THE NOOSA ENVIRONMENT
No. Project Responsibility Update Status
1 Continue the implementation of Council's Fire Director Environment & Sustainable Council is currently implementing on-ground actions related to fire trail On track @
Management Plans Development creation and maintenance, and finalising its controlled burns for the season. A
new Bushland Reserve Fire Management Plan is being drafted to replace the
2015 plan, and site-specific multi-agency plans for some of our highest risk
sites are being developed. All are expected to be in place by early 2021, in
preparation for works in the lead-up to the following season.
2 Implement the Noosa Environment Strategy Environmental Services Manager With an adopted Environment Strategy, appropriate monitoring mechanisms On track @
are now being put in place for implementation and actions are progressing.
The first annual report on the progress of the Environment Strategy was
reported to Council in August 2020.
3 Adopt the Noosa River Management Plan and commence Environmental Services Manager The second draft of the Noosa River Plan went out to public consultation in Behind Schedule QO
implementation December 2019/January 2020 and responses have been collated. This has
been workshopped with Councillors and a Stakeholder Reference Group is
being developed to finalise and support implementation of the Plan.
Discussions are currently occurring with stakeholders around the format and
Terms of Reference of this group.
4 Continue to implement and undertake a review of Zero Director Environment & Sustainable In August, Council approved the Climate Change Response Project Plan, On track @
Emissions Noosa (ZEN) Strategy and Action Plan Development Community and Stakeholder Engagement Plan and the updated PCG
Charter. When completed, the Climate Change Response Plan will include
measures to reduce Council's operational emissions, effectively replacing the
ZEN Organisational Plan.
5 Finalise the strategic review of landfill emission reduction Waste and Environmental Health Additional methane extraction wells currently being installed. Capping of cells On track @
opportunities Manager at interim completion level to be completed in the 2020/21FY.
6 Continue to partner with The Nature Conservancy to Director Environment & Sustainable The project plan was reported to Council in July and the first annual report in On track @
implement the Oyster Reef Restoration Project in the Development September. The project is progressing well, despite COVID restrictions on
Noosa River bringing the community together around the project, and the Project Manager
has had extensive one-on-meetings with key stakeholders. Scientific surveys
to determine site selection options is complete and the Technical Advisory
Group has met twice and is progressing significant actions around preparing
for permits. TNC has secured significant Commonwealth funding for building
oyster reefs across Australia, with the Noosa project the only Queensland
project included.
7 Continue the implementation of the Yurol and Ringtail Chief Executive Officer The Transition Committee met on 25 August 2020. The harvesting schedules On track @
Forestry Project for the pine plantation areas are ahead of anticipated timing. Further, early
indications are that the regrowth on harvested areas are also better than
expected. Negotiations continue with Greenfleet to undertake a broad scale
re-generation project across the entire site.
Page 120 of 131See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.