DTMR Conditions for Prescribed tidal works - OPW11/0301

of 3

Text shows just the words. Original shows the document exactly as it was published.

      6.     You or your agent must supply, install and maintain any navigation lights, buoys, marks or signs
             the Harbour Master considers necessary. Any lights, buoys, marks and signs must accord with
             Maritime Safety Queensland's requirements.


      7.     You must adequately light the structure. The contractor must position all lighting so it does not
             cause a risk to the safe navigation of other vessels. Any freestanding piles must have retro-
             reflective tape fitted.


      8.     You, or your agent, must remove any obstructions and debris encountered during construction,
             and dispose of them, as the Harbour Master requires.


      9.     Any ships and equipment you or your agent use must comply with the Transport Operations
             (Marine Safety) Act 1994, the Transport Operations (Marine Safety) Regulation 2004 and the
             Transport Operations (Marine Pollution) Act 1995.

      10. Any ships using this facility must comply with the Transport Operations (Marine Safety) Act
          1994 and the Transport Operations (Marine Safety) Regulation 2004.


      11. The contractor must complete construction within two years from the date of approval. If
          construction is not completed, you will need additional or amended comments from the Regional
             Harbour Master.

      Maritime Safety Queensland does not need to be further consulted if all of the above conditions are
      met.


      A copy of this letter has been sent to the assessment manager.


      Yours sincerely




/ Captain Richard C Johnson
      Regional Harbour Master (Brisbane)




                                                                                                      Page 2 of 2

Used in these records

About this file

File size
797 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

DTMR Conditions for Prescribed tidal works - OPW11_0301.pdf · 797 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.