Cover Letter, DA Form 1, Plans, Owners Consent, Coastal Environment Assessment · OPW21/0049

Attached to the e-mail Operational Works Application OPW21/0049 - Noosa Spit Erosion Protection Works.

of 146

Check the original when the exact wording matters.

Plans and drawings: the text below has words only, no drawings.

Log in to see the plans as drawn
Noosa Spit Coastal Protection Environmental Assessment                                                                                                      B-19
State Codes


 Performance outcomes                                    Acceptable outcomes                            Code compliance
 PO15 Development does not adversely impact              No acceptable outcome is prescribed.           Complies – works will not restrict commercial fishing
 on commercial fishing access and linkages                                                              activity
 between a commercial fishery and infrastructure,
 services and facilities.
 Note: In some cases, compensation for impact
 on fisheries access, operations and/or
 productivity may be necessary. The Guideline on
 fisheries adjustment provides advice for
 proponents on relevant fisheries adjustment
 processes and is available by request from the
 Department of Agriculture and Fisheries
 Private marine infrastructure
 PO16 Evidence of a relevant development                 No acceptable outcome is prescribed.           N/A
 approval for the removal, damage or destruction
 or marine plants is required if a material change
 of use or reconfiguration of a lot occurred since 1
 March 2005.
 Erosion control structures and beach replenishment
 PO17 Removal, destruction or damage to marine           No acceptable outcome is prescribed.           Complies – erosion is currently impacting beach
 plants as a result of erosion control structures or                                                    ammenity and vegetation.
 beach replenishment only occurs where there is
 an immediate and significant threat of erosion to:
 1. the use of the land for its existing or approved
 purpose; and
 2. infrastructure, structures or buildings are not
 expendable or not able to be relocated.

 Note: Further detail on erosion control is
 provided in Tidal fish habitats, erosion control
 and beach replenishment (FHMOP 010),
 Department of Primary Industries and Fisheries,
 2007.
 PO18 The area that the beach replenishment is           No acceptable outcome is prescribed.           Complies – the Noosa River mouth in it’s entirety is a
 to be carried out on is a high-energy, sandy                                                           dynamic environment that experiences frequent sand
 sediment shoreline with biological communities                                                         movement.
 adapted to mobile sediments.



 G:\Admin\A10342.g.mpb.NoosaSpitSEMPdesign\03 approvals\R.A10342.002.00_Environmental Assessment.docx

Used in these records

About this file

File size
9.0 MB (large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Cover Letter, DA Form 1, Plans, Owners Consent, Coastal Environment Assessment.pdf · 9.0 MB (large file)

The download may take up to a minute.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.