ORDINARY MEETING AGENDA 16 FEBRUARY 2023
b. adequate separation of all specific pedestrian routes from vehicle access and
manoeuvring areas, and clear demarcation by pavement marking, signposts
or changes in surface materials or levels;
c. signage and lighting at strategic locations to direct people to building entries
and public toilet facilities;
d. pedestrian refuge areas at strategic locations within the carpark to ensure
safe and convenient congregating of pedestrians waiting to cross major
access driveways;
e. a total of 50 bicycle parking spaces;
f. end of trip facilities involving a minimum of 10 lockers, 3 male and 3 female
showers and change rooms. Where end of trip facilities are provided in
separate tenancies, each tenancy must have a minimum of 2 lockers and 1
unisex shower/change room, provided the overall minimum total is achieved.
41. Proposed signage for the premises must be in accordance with Council’s Local
Law requirements.
47. Revised detention tank design calculations and documentation is to be provided
which identifies all assumptions and the methodology applied in deriving the tank
design and which is based on the recommendations of Australian Rainfall and
Runoff 2019, QUDM and The Noosa Plan 2020 (Water Quality and Drainage
Code). Ensemble temporal patterns are to be utilised for the analysis as well as
the current rainfall intensities recommended by Bureau of Meteorology. The
detention tank is to either achieve non-worsening for the range of durations
relevant to the downstream drainage network or is to demonstrate flows are
consistent with the design of the network.
54. The developer must provide waste storage and disposal facilities generally in
accordance with Waste Management Plan identified as Appendix E as submitted
to Council on 14 June 2019 and Planning Scheme Policy No. 9 “Waste
Management”. The facilities must include an external impervious area correctly
sized for all refuse and recycling containers and suitably screened from public
places and neighbouring properties. A bin wash area is required with a cold-water
tap, hose and drain outlet connected to sewer, via a bucket trap. The drain outlet
must be designed to prevent storm water entry to the sewerage system.
C. Delete condition 15.
D. Note the report is provided in accordance with Section 63(5) of the Planning Act 2016.
3 MCU22/0154 – APPLICATION FOR A MATERIAL CHANGE OF USE (FOOD & DRINK
OUTLET, SHOPS & OFFICES) AT 214 DAVID LOW WAY, PEREGIAN BEACH
That Planning & Environment Committee Agenda Item 3 be referred to the General Committee
for further information.
4 MCU19/0089.02 & OPW19/0160.02 – PLANNING & ENVIRONMENT COURT APPEAL NO.
DB928/2022 – APPLICATION FOR A MINOR CHANGE TO A DEVELOPMENT APPROVAL
FOR SERVICE STATION AND SHOP AND OPERATIONAL WORKS – SIGNAGE AT 54
MARY STREET, NOOSAVILLE
That Planning & Environment Committee Agenda Item 4 be referred to the General Committee
for further consideration.
Page 6 of 16
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalSearchable page text hides email addresses. Original files are unchanged and may show email addresses.